Home / Browse projects / Pune, Maharashtra / HARE KRISHNA KUNJ
HARE KRISHNA KUNJ
RG-MH-22165 · RERA P52100031579 · Last updated on MahaRERA portal: 5 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HARE KRISHNA KUNJ is a Others project by B G PROMOTERS AND BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100031579 on 31 Oct 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 51 of the 82 units on this registration are recorded sold or booked, and 15 of 33 construction stages are filed complete.
At a glance
Project
- NameHARE KRISHNA KUNJ
- TypeOthers
- Location
- KATRAJ KONDHWA ROAD
- NR ISCKON TEMPLE
- KONDHWA BR
- kondhwa BK
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100031579
- ReraGenie IDRG-MH-22165
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Oct 2021
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
- Buildings3 building records
- Documents filed127 files
Current status
Figures as on 5 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 7 | 0 | 0 | 0 | 0 |
| C WING - PHASE I | NA | 9 | 9 | 54 | 0 | 54 |
| B WING | NA | 7 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.
A WING77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
C WING - PHASE I80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
B WING77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | Yes | 70% |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed42
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A WING | 5 | 5 |
| C WING - PHASE I | 25 | 25 |
| B WING | 12 | 12 |
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| B G PROMOTERS AND BUILDERS | Pune (M Corp.) | Pune |
| B G PROMOTERS & BUILDERD | Pune (M Corp.) | Pune |
| B G PROMOTERS & BUILDERS | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C WING - PHASE I | NA | Rs 13.49 cr | Rs 8.24 cr |
| B WING | NA | Rs 6.06 cr | Rs 3.70 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AAMITESH Architect & Interior Designer |
| Engineer | KALPESH RAJENDRA ZABAK |
| Chartered Accountant | Priyanka Chordiya |
| Chartered Accountant | SAC Co & LLP |
| Partner | Role in project |
|---|---|
| B G PROMOTERS AND BUILDERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have obtained a single RERA registration number for both Wing B and Wing C; however, since the revised sanctioned plan was received and due to labour-related issues resulting in reduced workforce availability, the construction work could not be completed within the originally approved timeline. Therefore, we are extending the RERA project completion date up to 30.06.2026. This extension will ensure adequate time to complete all remaining construction activities and to comply with all applicable RERA requirements.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2021-2022)File: Form 2 A 2021-22.pdf | 5 Aug 2026 |
| Form 2A (FY 2023-2024)File: FORM 2A ENGINEERS CERTIFICATE QUALITY ASSURANCE CERTIFICATE 23_24.pdf | 5 Aug 2026 |
| Form 2A (FY 2022-2023)File: Form 2 A 2022-23.pdf | 5 Aug 2026 |
| Form 5 (FY 2021-2022)File: Form 5 2021-22.pdf | 5 Aug 2026 |
| Form 5 (FY 2022-2023)File: form 5 both sign 2022-23.pdf | 5 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sing 30 06 2026.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sing 30 06 2026.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30 06 2026 hare krushna kunj c sign.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30 06 2026 hare krushna kunj c sign.pdf | 24 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5_Hare Krishna Kunj FY 2025 2026 sign.pdf | 24 Jul 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A ENGINEERS CERTIFICATE QUALITY ASSURANCE CERTIFICATE 25_26_sign.pdf | 23 Jul 2026 |
| Form 5 (FY 2023-2024)File: from 5 Hare Krishn Kunj 31032024_compress.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: FORM -1 ARCHITECT CERTIFICATE.pdf | 21 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sing 30 06 2026.pdf | 21 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30 06 2026 hare krushna kunj c sign.pdf | 21 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 15 Jun 2026 |
| Withdrawal Update Form 2File: form 2 31_03_2026.pdf | 15 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 31032026 hare krushna kunj c sign.pdf | 15 Jun 2026 |
| Withdrawal Update Form 1File: form 1-final.pdf | 18 Mar 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 18 Mar 2026 |
| Withdrawal Update Form 3File: form 3 as on 20082026.pdf | 18 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 - Architect Certificate.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 - Architect Certificate.pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 - Architect Certificate.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 (30092025)-new.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 (31122025)-new.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 (31122025)-new.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 30092025 hare krushna kunj c sign.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 31122025 hare krushna kunj c sign.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 31122025 hare krushna kunj c sign.pdf | 27 Jan 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A ENGINEERS CERTIFICATE QUALITY ASSURANCE CERTIFICATE 24_25_sign copy.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5_Hare Krishna Kunj FY 2024_2025 sign.pdf | 27 Jan 2026 |
| Form 1File: FORM 1 Architect Certificate.pdf | 26 Dec 2025 |
| Form 2File: FORM 2.pdf | 26 Dec 2025 |
| Form 3File: Form 3 30062025 hare krushna kunj c sign.pdf | 26 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory 30062025 sign.pdf | 26 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architect Certificate.pdf | 15 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032025 hare krushna kunj c_compressed.pdf | 15 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31032025.pdf | 15 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 31032025.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 311224.pdf | 21 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Sign Copy.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 engineer certificate_signed.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold_signed.pdf | 21 Jan 2025 |
| Other - TechnicalFile: declaration cum annexure_signed.pdf | 5 Dec 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: RERA Designated Accounts_Format B.pdf | 3 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2_300624.pdf | 28 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 28 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 30092024_Both wing_signed.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 ARCHITECT'S CERTIFICATE 300924.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30092024 hare krushna kunj c sign_compress.pdf | 19 Nov 2024 |
| Declaration about Commencement CertificateFile: Format D Commencement certificate declaration new.pdf | 19 Nov 2024 |
| Layout approvalFile: 1 Layout Floor Plan AB_Compress.pdf | 15 Nov 2024 |
| Building plan approvalFile: 2 Floor Plan C_Compress.pdf | 15 Nov 2024 |
| Building plan approvalFile: 3 Elevation AB_Compress.pdf | 15 Nov 2024 |
| Building plan approvalFile: 4 Elevation C.pdf | 15 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: 1 Layout Floor Plan AB_Compress.pdf | 15 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert _Revised 2nd.pdf | 15 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 Floor Plan C_Compress.pdf | 15 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 Elevation AB_Compress.pdf | 15 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 Elevation C.pdf | 15 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Hare Krishna Kunj 30062024_compressed.pdf | 11 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: from 5 Hare Krishn Kunj 31032024_compress.pdf | 11 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Hare Krishna Kunj.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sodl Unsold Inventory.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 HARE KRISHNA KUNJ 30-06-2024_compressed.pdf | 18 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ENGINEERS CERTIFICATE QUALITY ASSURANCE CERTIFICATE 23_24.pdf | 18 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 30062023.pdf | 18 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 30092023.pdf | 18 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 31122023.pdf | 18 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory 31032024.pdf | 18 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SELF DECLARATION.pdf | 17 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_31032024.pdf | 8 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_30062023.pdf | 7 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FORM 2_30092023.pdf | 7 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 311223.pdf | 7 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2 _310324.pdf | 7 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAHA RERA FORM 2 _310323.pdf | 7 Jun 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| RADHEYA | KONDHWA BR. HAVELI PUNE | 1 | Completed | Mar 2019 | Late, Feb 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HARE KRISHNA KUNJ on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KONDHWA BR13,700+ in Pune
Filed coordinates, straight-line distance. 433 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: B G PROMOTERS AND BUILDERS
B G PROMOTERS AND BUILDERS has 2 registrations on MahaRERA, including RADHEYA and HARE KRISHNA KUNJ. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that HARE KRISHNA KUNJ shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if HARE KRISHNA KUNJ is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HARE KRISHNA KUNJ?
The registered promoter entity is B G PROMOTERS AND BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HARE KRISHNA KUNJ?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HARE KRISHNA KUNJ?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HARE KRISHNA KUNJ?
The professionals named in the filing: Architect: AAMITESH Architect & Interior Designer; Engineer: KALPESH RAJENDRA ZABAK; Chartered Accountant: Priyanka Chordiya; Chartered Accountant: SAC Co & LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HARE KRISHNA KUNJ?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback