ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / HAPPY HOME JASMINE C D

Registered No litigation declared Residential / Group Housing project

HAPPY HOME JASMINE C D

By Happy Home Corporation

RG-MH-87818 · RERA P99000048251 · Last updated on MahaRERA portal: 13 Aug 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken
  • Rs 43.00 crore secured on the land, in favour of State Bank of India

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 80%
118 of 163Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

HAPPY HOME JASMINE C D is a Residential / Group Housing project by Happy Home Corporation in Palghar, Maharashtra, registered with MahaRERA as P99000048251 on 22 Dec 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 6 months from the original filing. 45 of the 163 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.

At a glance

Project

  • NameHAPPY HOME JASMINE C D
  • TypeResidential / Group Housing
  • Location
    • RAJHANS KSHITIJ
    • MANIKPUR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401202
  • Pincode401202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000048251
  • ReraGenie IDRG-MH-87818

Builder

  • NameHappy Home Corporation
  • Entity typePartnership
  • GSTIN27AAGFH1158L2Z6
  • PartnerVIRAJ NALIN SHETH
  • PartnerNALIN NAVALCHAND SHETH
  • Other registrations2 more →
  • Completed1 of 3
  • Past their filed date1

Key dates

1 months past promisethis monthRegisteredDec 2022First promiseMar 2026Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Dec 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2026)
  • Buildings2 building records
  • Documents filed122 files

Current status

28%45 of 163 units booked
98.7%Work done, per cost certificate

Figures as on 13 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING CNA201672072
WING DNA201691091

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.

WING C81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
WING D81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 13 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed220

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots220
Closed/Covered220
BuildingClosed/CoveredTotal
WING C101101
WING D119119

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,705 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofState Bank of India
Secured amountRs 43.00 crore
CERSAI search filedYes
Declared on18 Jul 2025
LandownerVillageDistrict
AJMERA DEVELOPERSVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPORATION
Permissible FSI9794.0
Proposed, not sanctioned9,794 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndustrial Finance Branch
Estimated costRs 101.84 cr
Cost incurredRs 100.50 cr
Work done98.68%
BuildingWingEstimatedIncurred
WING CNARs 101.84 crRs 100.50 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRITHVI ARCH CONSULTANTS
EngineerNALIN NAVALCHAND SHETH
EngineerNALINKUMAR NAVALCHAND SHETH
Chartered AccountantSANJIV A JOSHI
Chartered AccountantAMPAC and Associates
Chartered AccountantSANJIV JOSHI
Chartered AccountantSingh Rajan & Co
PartnerRole in project
Happy Home Corporation-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29032620435Mar 2026 → Sep 2026

Reason as filed by the promoter1) Fire, Airport and Lift NOC Pending from Government Authorities.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A 2025-26.pdf13 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf12 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf12 Aug 2026
Withdrawal Update Form 3File: Form 3Happy Home 30-06-2026New.pdf12 Aug 2026
Layout approvalFile: Plan latest.pdf9 Jun 2026
Withdrawal Update Form 1File: form 1 31-03-2026.pdf4 Jun 2026
Withdrawal Update Form 2File: for 2 31-03-2026.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 C D 31-03-2026.pdf4 Jun 2026
Form 2A (FY 2023-2024)File: Form 2A - 2023-24.pdf9 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A - 2024-25.pdf9 Apr 2026
Form 5 (FY 2022-2023)File: FORM 5 Happy Homes CD 22-23 Sign.pdf8 Apr 2026
Form 5 (FY 2023-2024)File: FORM 5 Happy Homes CD 23-24 SIgn.pdf8 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5 Happy Homes CD 24-25 Sign.pdf8 Apr 2026
Form 2A (FY 2022-2023)File: Form 2A - 2022-23.pdf7 Apr 2026
Withdrawal Update Form 1File: form 1.pdf7 Feb 2026
Withdrawal Update Form 1File: form 1.pdf7 Feb 2026
Withdrawal Update Form 2File: Engineering Certificate Rera- Wing C D Q3.pdf7 Feb 2026
Withdrawal Update Form 2File: Engineering Certificate Rera- Wing C D Q3.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025.pdf7 Feb 2026
Withdrawal Update Form 1File: FORM 1 WING CD 30-09-25.pdf6 Feb 2026
Withdrawal Update Form 1File: FORM 1 WING CD 30-09-25.pdf6 Feb 2026
Withdrawal Update Form 2File: FORM 2 WING CD 30-09-25.pdf6 Feb 2026
Withdrawal Update Form 2File: FORM 2 WING CD 30-09-25.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025.pdf6 Feb 2026
Withdrawal Update Form 1File: FORM 1 WING CD 30-09-25.pdf5 Feb 2026
Withdrawal Update Form 1File: FORM 1 WING CD 30-09-25.pdf5 Feb 2026
Withdrawal Update Form 2File: FORM 2 WING CD 30-09-25.pdf5 Feb 2026
Withdrawal Update Form 2File: FORM 2 WING CD 30-09-25.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025 Signed.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 Happy Homes C D 30-09-2025 Signed.pdf5 Feb 2026
Withdrawal Update Form 1File: Q1 24 - 25.pdf16 Sep 2025
Withdrawal Update Form 2File: Q1 24 25.pdf16 Sep 2025
Withdrawal Update Form 3File: FORM 3 WING Cu0026D JASMINE Q1 (25-26) Singed.pdf16 Sep 2025
Form 1File: FORM 1 Q3 (22-23 ) WING C & D.pdf22 Aug 2025
Form 2File: FORM 2 Q3 (22-23) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q3 (22-23) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q3 (22-23) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q4 (22-23) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q4 (22-23 ) WING C & D.pdf22 Aug 2025
Form 2File: FORM 2 Q4 (22-23) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q4 (22-23) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q1 (23-24) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q1 (23-24) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q1 (23-24) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q1 (23-24) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q2 (23-24) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q2 (23-24) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q2 (23-24) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q2 (23-24) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q3 (23-24) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q3 (23-24) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q3(23-24) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q3 (23-24) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q4 (23-24) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q4 (23-24) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q4 (23-24) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY -Q4 (23-24) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q1 (24-25) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q1 (24-25) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q1(24-25) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q1 (24-25) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q2 ( 24-25) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q2 (24-25) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q2(24-25) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: UNSOLD INVENTORY - Q2 (24-25) WING C&D.pdf22 Aug 2025
Form 1File: FORM 1 Q3 (24-25) WING C&D.pdf22 Aug 2025
Form 2File: FORM 2 Q3 (24-25) WING C&D.pdf22 Aug 2025
Form 3File: FORM 3 Q3(24-25) WING C&D.pdf22 Aug 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY -Q3 ( 24-25) WING C&D.pdf22 Aug 2025
Form 1File: Q4 24 - 25.pdf16 Aug 2025
Form 2File: Q4 24 - 25.pdf16 Aug 2025
Form 3File: Q4 - 24 - 25.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Q4 24 25.pdf16 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4 24 - 25.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q4 - 24 - 25.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4 24 - 25.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DEC 2024.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DEC 2024.pdf23 Jan 2025

How this compares with Palghar

28%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 6 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HAPPY HOME JASMINE C D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MANIKPUR3,200+ in Palghar

2 kmHAPPY HOME JASMINE C DCompleted 46Lapsed / revoked 28Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 129 registered projects within 2 km.

Builder: Happy Home Corporation

Happy Home Corporation has 3 registrations on MahaRERA, including Happy Home Lily Kunj and HAPPY HOME JASMINE WING A B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if HAPPY HOME JASMINE C D is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAPPY HOME JASMINE C D?

The registered promoter entity is Happy Home Corporation, a partnership as per the filing. Its GSTIN 27AAGFH1158L2Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAPPY HOME JASMINE C D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAPPY HOME JASMINE C D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HAPPY HOME JASMINE C D?

The professionals named in the filing: Architect: PRITHVI ARCH CONSULTANTS; Engineer: NALIN NAVALCHAND SHETH; Engineer: NALINKUMAR NAVALCHAND SHETH; Chartered Accountant: SANJIV A JOSHI; Chartered Accountant: AMPAC and Associates; Chartered Accountant: SANJIV JOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAPPY HOME JASMINE C D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAPPY HOME JASMINE C D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAPPY HOME JASMINE C D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.