Home / Browse projects / HANWARE HEIGHTS

Registration lapsed Litigation declared Others project

HANWARE HEIGHTS

By HANWARE REALTY

RG-MH-68185 · RERA P51900019260 · Last updated on MahaRERA portal: 31 May 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Litigation declared, 7 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2024Possession promised22 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

HANWARE HEIGHTS is a Others project by HANWARE REALTY in DHARAVI, MUMBAI, 400017, registered with MahaRERA as P51900019260 on 14 Jan 2019. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 42 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameHANWARE HEIGHTS
  • TypeOthers
  • Location
    • 60 FEET ROAD
    • DHARAVI
    • MUMBAI
    • 400017
  • Pincode400017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900019260
  • ReraGenie IDRG-MH-68185

Builder

  • NameHANWARE REALTY
  • Entity typePartnership
  • PartnersMASOOD ISMAIL SARANG, KIRAN KAPOORCHAND KOTHARI, MOHAMMED ARIF ABDUL HAMID TANWAR, KETAN CHHAGANLAL PATEL
  • PartnerNIYAZ AHMED ABDULLAH HANWARE

Key dates

22 months past promisethis monthRegisteredJan 2019First promiseJun 2021Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Jan 2019
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed111 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HANWARE HEIGHTSNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

HANWARE HEIGHTS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 31 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
FITNESS CENTREYes100%

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered17
Open Space30

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,541 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI9381.79
Proposed, not sanctioned8,785 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 TO 6 DHEERAJ HERITAGE DAULAT NAGAR SANTACRUZ WEST MUMBAI 400054

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectN M MAHALE OF MAHALE & ASSOCIATES
PartnerRole in project
HANWARE REALTY-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900009659Jun 2021 → Jun 2022

Reason as filed by the promoterREASON FOR DELAY ARE 1) COVID-19 LOCKDOWN 2) SHORTAGE OF LABOUR DUE TO MIGRATION OF LABOURS TO THEIR NATIVE PLACES. 3) SHORTAGE OF CONSTRUCTION MATERIALS DUE TO COVID-19 LOCKDOWN 4) INCREASED COVID-19 CASES IN DHARAVI WHERE OUR PROJECT IS SITUATED.

EXT51900012169Jun 2021 → Jun 2023

Reason as filed by the promoterSHORTAGE OF LABOURS AND BUILDING MATERIALS DUE TO COVID 19

EXT51900016894Jun 2021 → Dec 2024

Reason as filed by the promoterConstruction work is stopped in the Covid 19 period due to the increased cases in Dharavi area where project is situated. After that construction work got slow for few months due to migration of labours in their villages because of Covid 19 lockdown. The our allottees are aware of all our problems and they are co-operating with us and have given their consents for extension. We request the authority to please give us further extension to complete the project.

Litigation declared7

CaseCourtStatus
904/2010BOMBAY HIGH COURTSUIT IS PENDING
5380/2012CITY CIVIL COURT MUMBAISUIT IS PENDING
847/2013BOMBAY HIGH COURTSUIT IS PENDING
1873/2013CITY CIVIL COURT MUMBAISUIT IS FOR FRAMING OF ISSUES
102049/2021CITY CIVIL COURT MUMBAISUIT IS PENDING
547/2023CITY CIVIL COURT MUMBAISUIT IS PENDING
904/904HIGH COURTOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000171526Pramila FernandoHanware Realty13/11/2019
CC12400304Shankar YadavHANWARE REALTY02/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 May 2024

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: PLAN 1_compressed.pdf31 May 2024
Building Plan Approval (IOD)File: PLAN 1_compressed.pdf31 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE MARCH -2024.pdf31 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 ENGINEER CERTIFICATE MARCH 2024.pdf31 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SITE SUPERVISOR - FORM 2A.pdf31 May 2024
Disclosure of sold/ booked inventoryFile: SOLD AND BOOKED INVENTORY_compressed.pdf31 May 2024
Certificates of CA (Form 3)File: FORM 3 - MARCH - 2024_compressed.pdf31 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - CA CERTIFICATE_compressed.pdf31 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE PART.pdf2 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC GROUND AND FIRST FLOOR DHARAVI.pdf2 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2ND TO 18TH FLOOR OCCUPATION CERTIFICATE.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: BOOK SOLD DEC 2023.pdf27 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 2022.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE 2022.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEPT 2022.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC 2022.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 2023.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 1 MARCH 2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH 2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE 2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SEPT 2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DEC 2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH 2023.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 MARCH 2022.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 JUNE 2022.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 SEPT 2022.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 DEC 2022.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 MARCH 2023.pdf14 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - 2021-2022.pdf14 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORMAT 5 - 2022-23.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2023.pdf26 Jun 2023
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf24 Jun 2023
Form 2AFile: FORM 2A 2023.pdf24 Jun 2023
Disclosure of sold/ booked inventoryFile: SOLD BOOK INVENTORY.pdf24 Jun 2023
Building plan approvalFile: AMENDED PLAN LETTER DATED 03-04-2023.pdf13 Apr 2023
Building plan approvalFile: TYPICAL FLOOR PLAN.pdf13 Apr 2023
Building Plan Approval (IOD)File: AMENDED PLAN LETTER DATED 03-04-2023.pdf13 Apr 2023
Building Plan Approval (IOD)File: TYPICAL FLOOR PLAN.pdf13 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: DHARAVI COMMENCEMENT CERTIFICATE.pdf13 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf19 Jan 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY DEC 2022.pdf19 Jan 2023
Proforma of Agreement for saleFile: DRAFT AGREEMENT FOR SALE.pdf19 Jan 2023
CERSAI detailsFile: CERSAI Reports 1.pdf9 Jul 2022
CERSAI detailsFile: CERSAI Reports 2.pdf9 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-2020.pdf9 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-2021.pdf9 Jul 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNITS.pdf1 Jul 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCE DETAILS.pdf30 Jun 2022
Declaration about Commencement CertificateFile: DECLARATION FOR COMMENCEMENT CERTIFICATE.pdf30 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SITE SUPERVISOR CERTIFICATE.pdf30 Jun 2022
CERSAI detailsFile: ENCUMBRANCE DETAILS.pdf30 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA (Form 5) 2018-2019.pdf30 Jun 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA ACCOUNT DETAILS.pdf30 Jun 2022
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT FOR ALLOTMENT.pdf30 Jun 2022
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT FOR AGREEMENT.pdf30 Jun 2022
Form 2AFile: FORM 2A OCT 2021.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf4 Jun 2021
Building plan approvalFile: Ground flr plan Feb 2021.pdf21 May 2021
Building plan approvalFile: 1st flr plan Feb 2021.pdf21 May 2021
Building Plan Approval (IOD)File: Ground flr plan Feb 2021.pdf21 May 2021
Building Plan Approval (IOD)File: 1st flr plan Feb 2021.pdf21 May 2021
OtherFile: Amendment cum OC letter.pdf21 May 2021
Commencement Certificates / NA Order for plotted developmentFile: FURTHER COMMENCEMENT CERTIFICATE.pdf7 Apr 2021
Details of Restarting of Construction work post lockdownFile: AMENDED PLAN CUM OC.pdf7 Apr 2021
OtherFile: AMENDED PLAN CUM OC.pdf7 Apr 2021
Building plan approvalFile: REVISED GROUND FLOOR PLAN.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 2.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 3.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 4.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 5.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 6.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 7.pdf27 Nov 2020
Building plan approvalFile: REVISED APPROVED PLAN 8.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED GROUND FLOOR PLAN.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 2.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 3.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 4.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 5.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 6.pdf27 Nov 2020
Building Plan Approval (IOD)File: REVISED APPROVED PLAN 7.pdf27 Nov 2020

Keep HANWARE HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHARAVI, MUMBAI

2 kmHANWARE HEIGHTSCompleted 1Lapsed / revoked 3Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: HANWARE REALTY

HANWARE REALTY has 1 registration on MahaRERA, including HANWARE HEIGHTS. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that HANWARE HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HANWARE HEIGHTS is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HANWARE HEIGHTS?

The registered promoter entity is HANWARE REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HANWARE HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HANWARE HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HANWARE HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HANWARE HEIGHTS?

The professionals named in the filing: Architect: N M MAHALE OF MAHALE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HANWARE HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HANWARE HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HANWARE HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.