ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Halima residency

Completed No litigation declared Residential / Group Housing project

Halima residency

By IQBAL IBRAHIM SHAIKH

RG-MH-22770 · RERA P52100033220 · Last updated on MahaRERA portal: 12 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

Halima residency is a Residential / Group Housing project by IQBAL IBRAHIM SHAIKH in Pune, Maharashtra, registered with MahaRERA as P52100033220 on 9 Feb 2022. The registration is recorded completed; possession was promised by 25 Dec 2025.

At a glance

Project

  • NameHalima residency
  • TypeResidential / Group Housing
  • Location
    • KONDHWA KHURD
    • PUNE
    • Haveli
    • 411048
  • Pincode411048
  • RERA no.P52100033220
  • ReraGenie IDRG-MH-22770

Builder

  • NameIQBAL IBRAHIM SHAIKH
  • Entity typeIndividual
  • GSTIN27ARAPS3329P1Z9

Key dates

this monthRegisteredFeb 2022PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Feb 2022
  • Promised completion25 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Halima residencyNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Halima residency: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area500 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on18 Sep 2024

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI822.09
Proposed, not sanctioned822 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEast Street Pune

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Saswade
ArchitectA a a
EngineerFaruk Mulla
Engineera b c
EngineerPalak Shah
Chartered AccountantHemant Shah
Chartered AccountantEJAZ & CO.
Chartered AccountantHemant Shah and Assocaites LLP
Chartered AccountantPalak Shah
PartnerRole in project
IQBAL IBRAHIM SHAIKH-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Nov 2024

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCUPANCY CERTIFICATE_0001.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cert 30 09 2023.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cert 31 12 2023.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cert 31 03 2024.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech certificate12 07 2024.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER 30 09 23.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER 31 12 23.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2ENGINEER 31 3 24.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER 30 6 24.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cert 30 06 2023.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER 30 6 23.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory.pdf1 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1 (1).pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate .pdf31 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CERTIFICATE_signed (1).pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit_Signed.pdf31 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory-1.pdf28 Dec 2022
Declaration in FORM BFile: FORM B UPDATED-compressed.pdf1 Feb 2022
Copy of the legal title reportFile: merged legal title report-compressed.pdf21 Jan 2022
CERSAI detailsFile: CERSAI MERGED.pdf21 Jan 2022
Proforma of Allotment letterFile: draft sale deed_merged.pdf21 Jan 2022
PAN CardFile: pan.pdf4 Jan 2022
Layout approvalFile: SANCTION PLAN SET -2.pdf20 Dec 2021
Building plan approvalFile: SANCTION PLAN SET -1.pdf20 Dec 2021
Details of encumbrancesFile: encumberance merged.pdf20 Dec 2021
Copy of Layout Approval (in case of layout)File: SANCTION PLAN SET -2.pdf20 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN SET -1.pdf20 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf20 Dec 2021
Declaration about Commencement CertificateFile: declaration of commencement.pdf20 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate signed.pdf20 Dec 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Halima residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

Builder: IQBAL IBRAHIM SHAIKH

IQBAL IBRAHIM SHAIKH has 1 registration on MahaRERA, including Halima residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Halima residency is delayed beyond 25 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Halima residency?

The registered promoter entity is IQBAL IBRAHIM SHAIKH, an individual as per the filing. Its GSTIN 27ARAPS3329P1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Halima residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Halima residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Halima residency?

The professionals named in the filing: Architect: Nilesh Saswade; Architect: A a a; Engineer: Faruk Mulla; Engineer: a b c; Engineer: Palak Shah; Chartered Accountant: Hemant Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Halima residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Halima residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Halima residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.