Home / Browse projects / Nashik, Maharashtra / GURUSIDDHI KRUPA
GURUSIDDHI KRUPA
By DEVIDAS RAMCHANDRA KULKARNI
RG-MH-34748 · RERA P51600050655 · Last updated on MahaRERA portal: 22 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 15 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GURUSIDDHI KRUPA is a Residential / Group Housing project by DEVIDAS RAMCHANDRA KULKARNI in Nashik, Maharashtra, registered with MahaRERA as P51600050655 on 21 Apr 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 8 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameGURUSIDDHI KRUPA
- TypeResidential / Group Housing
- Location
- ASHOKA MARG
- WADALA
- Nashik (M Corp.)
- Nashik
- 422011
- Pincode422011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600050655
- ReraGenie IDRG-MH-34748
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Apr 2023
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed96 files
Current status
Figures as on 22 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GURUSIDDHI KRUPA | NA | 8 | 7 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 96%.
GURUSIDDHI KRUPA: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 96% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 82% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 52% |
Progress on shared amenities15
As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed43
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GURUSIDDHI KRUPA | NA | Rs 3.50 cr | Rs 2.08 cr |
| - | NA | Rs 10.00 lakh | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHUBHAM KULKARNI |
| Engineer | YOGESH THATTE |
| Engineer | SHUBHAM KULKARNI |
| Chartered Accountant | SHUBHAM MUNDADA |
| Chartered Accountant | DEVENDRA SOMNATH KULKARNI |
| Chartered Accountant | TRIPTI KAINTH |
| Chartered Accountant | TRIPTI AMIT KUKREJA |
| Partner | Role in project |
|---|---|
| DEVIDAS RAMCHANDRA KULKARNI | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterb. On account of personal health issues and mediocre sales of the units the development activities at the project were moving on a slow pace. Also the Promoter could not factor the time that would take for him to complete the project at the time of registration which is evident from the fact that the registration as first sought only for 31 months. Due to all such factors, the promoter has been able to complete more than 90% project by deploying additional labourers.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jan 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Withdrawal Application Form1 15042026.pdf | 22 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 15042026.pdf | 22 Jun 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 24042026.pdf | 22 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 7 Mar 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 7 Mar 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 7 Mar 2026 |
| Form 3File: form 3 q3 24-25.pdf | 30 Dec 2025 |
| Form 2File: FORM 2 Q3 24-25.pdf | 30 Dec 2025 |
| Form 1File: form 1 q3 24-25.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 31122024.pdf | 30 Dec 2025 |
| Form 1File: form 1 q2 24-25.pdf | 30 Dec 2025 |
| Form 2File: FORM 2 Q2 24-25.pdf | 30 Dec 2025 |
| Form 3File: form 3 q2 24-25.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30092024.pdf | 30 Dec 2025 |
| Form 1File: form 1 q1 24-25.pdf | 30 Dec 2025 |
| Form 2File: FORM 2 Q1 24-25.pdf | 30 Dec 2025 |
| Form 3File: form 3 q1 24-25.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30062024.pdf | 30 Dec 2025 |
| Form 1File: architect q4 1.pdf | 30 Dec 2025 |
| Form 2File: FORM 2 Q4.pdf | 30 Dec 2025 |
| Form 3File: form 3 q4.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 31032024.pdf | 30 Dec 2025 |
| Form 1File: form 1 q3.pdf | 30 Dec 2025 |
| Form 2File: Drk Form 2 q3.pdf | 30 Dec 2025 |
| Form 3File: Form 3 q1_compressed.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: unsold sold 31122023.pdf | 30 Dec 2025 |
| Form 1File: form 1 q2.pdf | 30 Dec 2025 |
| Form 2File: Drk form 2 q2.pdf | 30 Dec 2025 |
| Form 3File: Drk form 3 q3_compressed.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30092023.pdf | 30 Dec 2025 |
| Form 1File: form 1 q1.pdf | 30 Dec 2025 |
| Form 2File: DRK Form 2 q 1.pdf | 30 Dec 2025 |
| Form 3File: DRK Form 3 Q1.pdf | 30 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30062023.pdf | 30 Dec 2025 |
| Withdrawal Update Form 1File: form 1 q2 25-26.pdf | 30 Dec 2025 |
| Withdrawal Update Form 2File: form 2 q2 25-26.pdf | 30 Dec 2025 |
| Withdrawal Update Form 3File: form 3 q2 25-26.pdf | 30 Dec 2025 |
| Form 2A (FY 2023-2024)File: Form 2A 31032024 signed.pdf | 30 Dec 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 31032025 signed.pdf | 30 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 guru siddhi krupa.pdf | 30 Dec 2025 |
| Form 5 (FY 2023-2024)File: Form 5.pdf | 30 Dec 2025 |
| Form 1File: form 1 q1 25-26.pdf | 3 Nov 2025 |
| Form 2File: form 2 Q1 25-26.pdf | 3 Nov 2025 |
| Form 3File: form 3 q1 25-26.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: sold_inventory.pdf | 3 Nov 2025 |
| Form 1File: form 1 q2 25-26.pdf | 3 Nov 2025 |
| Form 2File: form 2 q2 25-26.pdf | 3 Nov 2025 |
| Form 3File: form 3 q2 25-26.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: sold_inventory q2 25-26.pdf | 3 Nov 2025 |
| Form 1File: form 1 q4 24-25.pdf | 20 Jun 2025 |
| Form 2File: Form - 2 q4 24-25.pdf | 20 Jun 2025 |
| Form 3File: form 3 24-25 q4.pdf | 20 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold_inventory.pdf | 20 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q1 24-25.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q2 24-25.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q3 24-25.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 q1 24-25.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 q2 24-25.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 q3 24-25.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q1 24-25.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q2 24-25.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 24-25.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect q4 1.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 q4.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 q4.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q1.pdf | 30 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q2.pdf | 30 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q3.pdf | 30 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DRK Form 2 q 1.pdf | 30 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Drk form 2 q2.pdf | 30 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Drk Form 2 q3.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 q1_compressed.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Drk form 3 q2_compressed.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Drk form 3 q3_compressed.pdf | 30 Jan 2024 |
| Declaration in FORM BFile: Adobe Scan Apr 12, 2023 (2).pdf | 14 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Drk form 3 (1)_compressed.pdf | 7 Apr 2023 |
| CERSAI detailsFile: Cersai declaration.pdf | 3 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Drk seperate bank.pdf | 29 Mar 2023 |
| Layout approvalFile: Layout HIGHLIGHTED-merged.pdf | 20 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| YOGIRAJ KRUPAP51600019730 | NEW KALA NAGAR, Nashik | 14 | Mar 2019 | Completed | Feb 2022 | Late, Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GURUSIDDHI KRUPA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WADALA4,100+ in Nashik
Filed coordinates, straight-line distance. 180 registered projects within 2 km.
Anandvan Housing Complex
Ravi Mahajan Buildcon LLP
SHREEJI INFINIA
SHREEJI LIFE SPACE
Waterways
Sanklecha Construction Private Limited
Shreejis Gujral Arcade
SHREEJI LIFE SPACE
VRAJ METROPOLIS SOUTH
SHREE INFRA SPACE
ALEEF BREEZE APARTMENT
KHATIB BUILDERS AND DEVELOPERS
See every Nashik project, with the district possession charts
Builder: DEVIDAS RAMCHANDRA KULKARNI
DEVIDAS RAMCHANDRA KULKARNI has 2 registrations on MahaRERA, including YOGIRAJ KRUPA and GURUSIDDHI KRUPA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if GURUSIDDHI KRUPA is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GURUSIDDHI KRUPA?
The registered promoter entity is DEVIDAS RAMCHANDRA KULKARNI, an individual as per the filing. Its GSTIN 27ABRPK1189N2ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GURUSIDDHI KRUPA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GURUSIDDHI KRUPA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GURUSIDDHI KRUPA?
The professionals named in the filing: Architect: SHUBHAM KULKARNI; Engineer: YOGESH THATTE; Engineer: SHUBHAM KULKARNI; Chartered Accountant: SHUBHAM MUNDADA; Chartered Accountant: DEVENDRA SOMNATH KULKARNI; Chartered Accountant: TRIPTI KAINTH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GURUSIDDHI KRUPA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback