ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / GURUSHREE HEIGHTS

Registered No litigation declared Residential / Group Housing project

GURUSHREE HEIGHTS

By GURUSHREE DEVELOPERS

RG-MH-22639 · RERA P52700031709 · Last updated on MahaRERA portal: 9 Jul 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
8 of 11Construction stages donefurthest along: Stilt Floor, 80%
13 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

GURUSHREE HEIGHTS is a Residential / Group Housing project by GURUSHREE DEVELOPERS in Satara, Maharashtra, registered with MahaRERA as P52700031709 on 8 Nov 2021. Possession is promised by 31 Dec 2026. 0 of the 13 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameGURUSHREE HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • BHAVANI PETH
    • -
    • Satara
    • 415002
  • Pincode415002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700031709
  • ReraGenie IDRG-MH-22639

Builder

  • NameGURUSHREE DEVELOPERS
  • Entity typePartnership
  • PartnersKISHOR MADHUKAR JADHAV, HEMANT MADHUKAR JADHAV, SATISH VELAYUDHAN KORATTIL, RAMANLAL GANPATDAS SHAH, NITIN RAMANLAL SHAH

Key dates

this monthRegisteredNov 2021PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Nov 2021
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed52 files

Current status

0%0 of 13 units booked
95.1%Work done, per cost certificate

Figures as on 9 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GURUSHREE HEIGHTSNA5431013

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.

GURUSHREE HEIGHTS: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area229 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jul 2025

Approvals and building plan

Sanctioning authoritySATARA MUNICIPAL COUNCIL
Permissible FSI697.78
Proposed, not sanctioned698 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGODOLI SATARA
Estimated costRs 2.09 cr
Cost incurredRs 1.99 cr
Work done95.11%
BuildingWingEstimatedIncurred
GURUSHREE HEIGHTSNARs 1.94 crRs 1.99 cr
-NARs 15.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASAD KASTURE KASTURE
EngineerRASIKA JADHAV
Chartered AccountantG C GODBOLE & CO
PartnerRole in project
GURUSHREE DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration and undertaking (Annexure A)File: ANN A.pdf9 Jul 2025
Commencement certificateFile: 1 Commencement Certificates _ NA Order for plotted development (1).pdf9 Jul 2025
Form 1File: form 1.PDF9 Jul 2025
Form 2File: form 2.PDF9 Jul 2025
Form 3File: form 3 march 2025.pdf9 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold march 25.pdf9 Jul 2025
Withdrawal Update Form 1File: form no 1.PDF9 Jul 2025
Withdrawal Update Form 2File: form no 2.PDF9 Jul 2025
Withdrawal Update Form 3File: CA DEC.pdf9 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.PDF20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 jan 2025.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 march 2025.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.PDF20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT.PDF20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI CERT.PDF20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form- 2A.PDF23 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.PDF23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.PDF8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CER CHANGE.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca dec.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DEC.PDF13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG DEC.PDF13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC.PDF13 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH 12-12-23.PDF13 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG.PDF13 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.PDF13 Dec 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE.PDF9 Dec 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE.PDF9 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: INTEREST.PDF9 Dec 2023
Proforma of Allotment letterFile: ALLOTMENT LETTRE.PDF9 Dec 2023
Proforma of Agreement for saleFile: model form of agreement ind BLANK.pdf9 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK.PDF9 Dec 2023
Deviation Report with respect to Allotment letterFile: DEV ALLOTMENT.PDF9 Dec 2023
Deviation Report with respect to model copy of AgreementFile: DEV AGREEMENT.PDF9 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 22.PDF1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 23.PDF1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.PDF1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.PDF1 Dec 2023
Layout approvalFile: plan.pdf30 Oct 2021
Building plan approvalFile: plan.pdf30 Oct 2021
PAN CardFile: pan card.pdf30 Oct 2021
Copy of the legal title reportFile: search report.pdf30 Oct 2021
Details of encumbrancesFile: non incumbrances.pdf30 Oct 2021
Copy of Layout Approval (in case of layout)File: plan.pdf30 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: plan.pdf30 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf30 Oct 2021
Declaration about Commencement CertificateFile: declaration commencement.pdf30 Oct 2021
Declaration in FORM BFile: b form.pdf30 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf30 Oct 2021
Proforma of Allotment letterFile: booking letter.pdf30 Oct 2021
Proforma of Allotment letterFile: gurushree heights agreement.pdf30 Oct 2021

How this compares with Satara

0%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep GURUSHREE HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -1,100+ in Satara

2 kmGURUSHREE HEIGHTSCompleted 22Lapsed / revoked 12Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: GURUSHREE DEVELOPERS

GURUSHREE DEVELOPERS has 1 registration on MahaRERA, including GURUSHREE HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if GURUSHREE HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GURUSHREE HEIGHTS?

The registered promoter entity is GURUSHREE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GURUSHREE HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GURUSHREE HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GURUSHREE HEIGHTS?

The professionals named in the filing: Architect: PRASAD KASTURE KASTURE; Engineer: RASIKA JADHAV; Chartered Accountant: G C GODBOLE & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GURUSHREE HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GURUSHREE HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GURUSHREE HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.