Home / Browse projects / Nagpur, Maharashtra / GURUKRIPA

Registered No litigation declared Others project

GURUKRIPA

By SHREE RENUKA INFRA LLP

RG-MH-19276 · RERA P50500078365 · Last updated on MahaRERA portal: 4 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken
  • Encumbrance declared on the project land, in favour of NA
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Sep 2027Possession promisedmoved 18 months from the original
5 of 11Construction stages donefurthest along: Staircases, 99%
16 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

GURUKRIPA is a Others project by SHREE RENUKA INFRA LLP in Nagpur, Maharashtra, registered with MahaRERA as P50500078365 on 6 Dec 2024. Possession is promised by 30 Sep 2027. The completion date has moved by 18 months from the original filing. 1 of the 17 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameGURUKRIPA
  • TypeOthers
  • Location
    • GOREWADA ROAD
    • GOREWADA
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440013
  • Pincode440013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500078365
  • ReraGenie IDRG-MH-19276

Builder

  • NameSHREE RENUKA INFRA LLP
  • Entity typeOthers
  • PartnersDILIP DATTATRAY ATKAR, GOURI DILIP ATKAR

Key dates

this monthRegisteredDec 2024First promiseMar 2026Revised toSep 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Dec 2024
  • Promised completion30 Sep 2027
  • Revised completionRevised to 30 Sep 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed56 files

Current status

6%1 of 17 units booked
94.0%Work done, per cost certificate

Figures as on 4 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GURUKRIPANA5513417

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 99%.

GURUKRIPA: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 4 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes90%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntYes85%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes90%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered22
Open Space22

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,071 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofNA
CERSAI search filedYes
Declared on13 Aug 2025
LandownerVillageDistrict
Mr SANJAY RAGHURAJ TIWARINagpur (M Corp.)Nagpur
GOURI ATKARNagpur (M Corp.)Nagpur
DILIP ATKARNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNAGPUR IMPROVEMENT TRUST
Permissible FSI3571.65
Proposed, not sanctioned2,743 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, PLOT NO.193, DR. AGRAWAL BUILDING,MEDICAL SQUARE, NAGPUR- 440 009
Estimated costRs 5.00 cr
Cost incurredRs 4.70 cr
Work done94.0%
BuildingWingEstimatedIncurred
-NARs 5.00 crRs 4.70 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS PADOLE
EngineerShashikant bhombhe
Chartered AccountantAnjali Divecha
Chartered AccountantSAMEER DIVECHA
PartnerRole in project
SHREE RENUKA INFRA LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04042620556Mar 2026 → Sep 2027

Reason as filed by the promoterTo The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Reason for Extension of Project - GURUKRIPA Bearing RERA No. P50500078365 Respected Sir/Madam, The project is delayed primarily due to non-issuance of Occupation Certificate (OC) by the competent authority despite substantial completion of works. Additionally, the project is further delayed pending approval from Nagpur Improvement Trust (NIT) for our proposal to construct two more floors over the existing floors; the acknowledgment receipt for this NIT permission application is enclosed herewith. These external delays, bey

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: FORM 2A MAR 25.pdf4 Apr 2026
Form 1File: FORM 1 DEC 24.pdf3 Apr 2026
Form 2File: FORM 2 DEC 24.pdf3 Apr 2026
Form 3File: FORM 3 DEC 24.pdf3 Apr 2026
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD DEC 24.pdf3 Apr 2026
Form 1File: FORM 1 MAR 25.pdf3 Apr 2026
Form 2File: FORM 2 MAR 25.pdf3 Apr 2026
Form 3File: FORM 3 MAR 25.pdf3 Apr 2026
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD MAR 25.pdf3 Apr 2026
Withdrawal Update Form 1File: FORM 1 DEC 24.pdf3 Apr 2026
Withdrawal Update Form 1File: FORM 1 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 1File: FORM 1 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 1File: FORM 1 SEP 25_0001.pdf3 Apr 2026
Withdrawal Update Form 1File: FORM 1 DEC 25_0001.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 DEC 24.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 SEP 25_0001.pdf3 Apr 2026
Withdrawal Update Form 2File: FORM 2 DEC 25_0001.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 DEC 24.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 JUNE 25_0001.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 SEP 25_0001.pdf3 Apr 2026
Withdrawal Update Form 3File: FORM 3 DEC 25_0001.pdf3 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5_0001.pdf2 Apr 2026
Other - FinanceFile: owner decalration to retain the flats and shops.pdf3 Dec 2024
Other - FinanceFile: FORMAT A RERA BANK ACCOUNT DECLARATION.pdf3 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: VERIFICATION OF OC CC.pdf23 Nov 2024
Other - FinanceFile: declaration cum undertaking for uploading.pdf23 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: merged decalartion of CA SECURED LOANS.pdf23 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: owner decalartion no requirment of rera ac.pdf19 Nov 2024
Building plan approvalFile: MAP SCAN 1.pdf13 Nov 2024
Layout approvalFile: MAP SCAN 1.pdf13 Nov 2024
PAN CardFile: PAN CARD SHREE RENUKA INFRA LLP.pdf13 Nov 2024
Copy of the legal title reportFile: LEGAL REPORT_compressed.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: Non Encumberance Certificate.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE LEGAL.pdf13 Nov 2024
Copy of Layout Approval (in case of layout)File: MAP SCAN 1.pdf13 Nov 2024
Proforma of Allotment letterFile: AL SEP 24.pdf13 Nov 2024
Declaration in FORM BFile: form B.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MERGED CA CERTIFICATE.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf13 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: NIT PERMIT comencement certificate.pdf13 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: MAP SCAN 1.pdf13 Nov 2024
Declaration about Commencement CertificateFile: Commencemnt Certificate.pdf13 Nov 2024
CERSAI detailsFile: CERSAI gurukripa.pdf13 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declartion of Rera designated Bank account.pdf13 Nov 2024
Deviation Report with respect to Allotment letterFile: DEVIATION FRPM AL.pdf13 Nov 2024
Details of encumbrances concerned to LegalFile: Non Encumberance Certificate.pdf13 Nov 2024
Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE LEGAL.pdf13 Nov 2024
Deviation Report with respect to model copy of AgreementFile: declaration cum undertaking for uploading.pdf13 Nov 2024
Proforma of Agreement for saleFile: AFS SEP 24aa.pdf13 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A .pdf13 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf13 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: SECURED UNSECURED LOAN BY CLIENT.pdf13 Nov 2024

How this compares with Nagpur

6%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 18 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GURUKRIPA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOREWADA2,800+ in Nagpur

2 kmGURUKRIPACompleted 11Lapsed / revoked 1Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: SHREE RENUKA INFRA LLP

SHREE RENUKA INFRA LLP has 1 registration on MahaRERA, including GURUKRIPA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if GURUKRIPA is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GURUKRIPA?

The registered promoter entity is SHREE RENUKA INFRA LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GURUKRIPA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GURUKRIPA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GURUKRIPA?

The professionals named in the filing: Architect: VIKAS PADOLE; Engineer: Shashikant bhombhe; Chartered Accountant: Anjali Divecha; Chartered Accountant: SAMEER DIVECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GURUKRIPA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GURUKRIPA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GURUKRIPA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.