Home / Browse projects / Pune, Maharashtra / GULMOHAR VILLAS - X
GULMOHAR VILLAS - X
RG-MH-33101 · RERA P52100080573 · Last updated on MahaRERA portal: 6 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GULMOHAR VILLAS - X is a Plotted project by ARBAAZ VALIMOHAMMED MEMON in Pune, Maharashtra, registered with MahaRERA as P52100080573 on 16 Jun 2025. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameGULMOHAR VILLAS - X
- TypePlotted
- Location
- ROHAN ABHILASHA ROAD
- WAGHOLI
- Haveli
- Pune
- 412207
- Pincode412207
- RERA no.P52100080573
- ReraGenie IDRG-MH-33101
Builder
- NameARBAAZ VALIMOHAMMED MEMON
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Jun 2025
- Promised completion31 Dec 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed29 files
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Progress on shared amenities15
As on 6 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAHADEV BORADE AND ASSOCIATES |
| Engineer | MAHESH GULABRAO GAVHANE |
| Chartered Accountant | RUSHABH M. LODHA |
| Partner | Role in project |
|---|---|
| ARBAAZ VALIMOHAMMED MEMON | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 May 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 May 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 May 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - LegalFile: 7-12 Arbaz X.pdf | 6 Jun 2025 |
| Layout approvalFile: X BP_11zon.pdf | 2 May 2025 |
| Building plan approval or NA orderFile: X BP_11zon.pdf | 2 May 2025 |
| PAN CardFile: PAN.pdf | 2 May 2025 |
| Copy of the legal title reportFile: RERA title X 1933.pdf | 2 May 2025 |
| Details of encumbrances concerned to FinanceFile: Enc Finance.pdf | 2 May 2025 |
| Details of encumbrances concerned to FinanceFile: Enc Legal.pdf | 2 May 2025 |
| Copy of Layout Approval (in case of layout)File: X BP_11zon.pdf | 2 May 2025 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 2 May 2025 |
| Declaration in FORM BFile: Form B.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 2 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: X CC.pdf | 2 May 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: X BP_11zon.pdf | 2 May 2025 |
| Other - LegalFile: Sale Deed.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Details.pdf | 2 May 2025 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 2 May 2025 |
| CERSAI detailsFile: Cersai Reprot.pdf | 2 May 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 2 May 2025 |
| Deviation Report with respect to Allotment letterFile: Dec AL.pdf | 2 May 2025 |
| Details of encumbrances concerned to LegalFile: Enc Finance.pdf | 2 May 2025 |
| Details of encumbrances concerned to LegalFile: Enc Legal.pdf | 2 May 2025 |
| Other - TechnicalFile: Order No 50.pdf | 2 May 2025 |
| Deviation Report with respect to model copy of AgreementFile: Dev AFS.pdf | 2 May 2025 |
| Proforma of Agreement for saleFile: AFS 13062025.pdf | 2 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Other real.pdf | 2 May 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 2 May 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: FINANCE AVAILED.pdf | 2 May 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 29 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GULMOHAR VILLAS - X on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WAGHOLI13,700+ in Pune
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: ARBAAZ VALIMOHAMMED MEMON
ARBAAZ VALIMOHAMMED MEMON has 1 registration on MahaRERA, including GULMOHAR VILLAS - X. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GULMOHAR VILLAS - X is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GULMOHAR VILLAS - X?
The registered promoter entity is ARBAAZ VALIMOHAMMED MEMON, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GULMOHAR VILLAS - X?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GULMOHAR VILLAS - X?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GULMOHAR VILLAS - X?
The professionals named in the filing: Architect: MAHADEV BORADE AND ASSOCIATES; Engineer: MAHESH GULABRAO GAVHANE; Chartered Accountant: RUSHABH M. LODHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GULMOHAR VILLAS - X?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback