Home / Browse projects / Mumbai City, Maharashtra / GULMOHAR TERRACE

Registered No litigation declared Residential / Group Housing project

GULMOHAR TERRACE

By SHINING SUN CONSTRUCTIONS

RG-MH-52512 · RERA P51900013547 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 96 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 96 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
58 of 102Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

GULMOHAR TERRACE is a Residential / Group Housing project by SHINING SUN CONSTRUCTIONS in Mumbai City, Maharashtra, registered with MahaRERA as P51900013547 on 9 Oct 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 96 months from the original filing. 44 of the 102 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGULMOHAR TERRACE
  • TypeResidential / Group Housing
  • Location
    • C.S NO.1101 AND 1102
    • MUMBAI
    • Mumbai City
    • 400008
  • Pincode400008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900013547
  • ReraGenie IDRG-MH-52512

Builder

  • NameSHINING SUN CONSTRUCTIONS
  • Entity typePartnership
  • PartnersADNAN NASIR JAMAL SHAIKH, NASIR JAMAL SHAIKH, ZAHEDA ABU ASIM AZMI
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredOct 2017First promiseDec 2019Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Oct 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed62 files

Current status

43%44 of 102 units booked
95.0%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GULMOHAR TERRACENA27271020102

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

GULMOHAR TERRACE: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes10%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered70

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area948 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMuncipal Corporation of Greater Mumbai
Permissible FSI1947.0
Proposed, not sanctioned1,947 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFORT, MUMBAI 400001
Estimated costRs 34.72 cr
Cost incurredRs 32.98 cr
Work done95.0%
BuildingWingEstimatedIncurred
GULMOHAR TERRACENARs 34.72 crRs 32.98 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP R DHARIA AND ASSOCIATES
EngineerSTRUCON CONSULTING ENGINEERS
EngineerKOMAL PAWAR
Chartered AccountantManish K Ramawati And Company
Chartered AccountantK Hemant & Co.
PartnerRole in project
SHINING SUN CONSTRUCTIONS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900011430Dec 2019 → Dec 2024

Reason as filed by the promoterBECAUSE OF COVID 19 PANDAMIC WE COULD NOT COMPLETE OUR PROJECT .SO WE REQUIRE EXTENSION TO OUR PROJECT.

EXT51900006072Dec 2019 → Dec 2020

Reason as filed by the promoterWE REQUEST YOU TO EXTEND OUR PROJECT COMPLETION DATE TO 30TH DEC 2020 AS PROJECT GET DELAYED DUE TO COVID 19 DISEASE.

EA10112518291Dec 2019 → Dec 2027

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000171787Shabbir Qutub AliShaikh Nasir Jamal18/12/2019
CC006000000195866Ebrahim Alihusain RajaSHINING SUN CONSTRUCTIONS03/02/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 30-06-2026 Sign.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2 30-06-2026 Sign.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 30-06-2026 Sign.pdf18 Jul 2026
Withdrawal Update Form 1File: Form 1 31-03-2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 31-03-2026.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM_3 Shining sun 31-03-2026 Sign .pdf20 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERT.pdf24 Feb 2026
Withdrawal Update Form 1File: ARCHITECT CERT.pdf24 Feb 2026
Withdrawal Update Form 2File: ENG CERTIFICATE.pdf24 Feb 2026
Withdrawal Update Form 2File: ENG CERTIFICATE.pdf24 Feb 2026
Withdrawal Update Form 3File: CA CERT.pdf24 Feb 2026
Withdrawal Update Form 3File: CA CERT.pdf24 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A System G 24-25.pdf4 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 Shining Sun 24-25.pdf29 Nov 2025
Form 1File: Form 1 Shining Sun 30-06-25.pdf1 Sep 2025
Form 2File: Form 2 Shining sun 30-06-25.pdf1 Sep 2025
Form 3File: Form 3 Shining sun 30-06-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold Shining Sun 30-06-25.pdf1 Sep 2025
Form 1File: Form 1 shining sun 31-03-25.pdf1 Sep 2025
Form 2File: Form 2 Shining sun 31-03-25.pdf1 Sep 2025
Form 3File: Form 3 Shining sun 31-03-25.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Shining Sun 31-03-2025.pdf1 Sep 2025
Form 1File: Form 1 Shining Sun 31-12-24.pdf1 Sep 2025
Form 2File: Form 2 Shining sun 31-12-24.pdf1 Sep 2025
Form 3File: Form 3 Shining Sun 31-12-24.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Shining Sun 31-12-2024.pdf1 Sep 2025
Form 1File: Form 1 Shining sun 30-09-24.pdf1 Sep 2025
Form 2File: Form 2 Shining sun 30-09-24.pdf1 Sep 2025
Form 3File: Form 3 Shining sun 30-09-24.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Shining Sun 30-09-2024.pdf1 Sep 2025
Form 1File: Form 1 shining sun 30-06-24.pdf1 Sep 2025
Form 2File: Form 2 shining sun 30-06-24.pdf1 Sep 2025
Form 3File: Form 3 shining sun 30-06-24.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Shining Sun 30-06-2024.pdf1 Sep 2025
Form 2A (FY 2021-2022)File: Form 2 A 31.03.22.pdf1 Sep 2025
Form 2A (FY 2022-2023)File: Form 2 A 31.03.23.pdf1 Sep 2025
Form 2A (FY 2023-2024)File: Form 2 A 31.03.24.pdf1 Sep 2025
Form 5 (FY 2021-2022)File: Form 5 System G 21-22.pdf28 Aug 2025
Form 5 (FY 2022-2023)File: Form 5 System G 22-23.pdf28 Aug 2025
Form 5 (FY 2023-2024)File: Form 5 System G 23-24.pdf28 Aug 2025
Declaration about Commencement CertificateFile: cc declaration.pdf8 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A 2020.pdf8 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2021.pdf8 Feb 2022
CERSAI detailsFile: CERSAI Search Report.pdf8 Feb 2022
Disclosure of sold/ booked inventoryFile: sold unsold.pdf8 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 17-18.pdf8 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf8 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf8 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf8 Feb 2022
Certificates of CA (Form 3)File: CA CERT.pdf29 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE.pdf28 Sep 2017
Proforma of Allotment letterFile: agreement for sale letter.pdf27 Sep 2017
Declaration in FORM BFile: form b.pdf21 Sep 2017
Building plan approvalFile: plan (1).pdf19 Sep 2017
Layout approvalFile: plan (1).pdf19 Sep 2017
PAN CardFile: pan card.pdf19 Sep 2017
Copy of the legal title reportFile: title cert.pdf19 Sep 2017
Details of encumbrancesFile: ENCUMBRANCE.pdf19 Sep 2017
Copy of Layout Approval (in case of layout)File: plan (1).pdf19 Sep 2017
Building Plan Approval (IOD)File: plan (1).pdf19 Sep 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf19 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERT.pdf19 Sep 2017

How this compares with Mumbai City

43%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 96 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GULMOHAR TERRACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI780+ in Mumbai City

2 kmGULMOHAR TERRACECompleted 26Lapsed / revoked 33Other 92Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: SHINING SUN CONSTRUCTIONS

SHINING SUN CONSTRUCTIONS has 2 registrations on MahaRERA, including MARBLE ARCH and GULMOHAR TERRACE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if GULMOHAR TERRACE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GULMOHAR TERRACE?

The registered promoter entity is SHINING SUN CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GULMOHAR TERRACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GULMOHAR TERRACE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GULMOHAR TERRACE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GULMOHAR TERRACE?

The professionals named in the filing: Architect: P R DHARIA AND ASSOCIATES; Engineer: STRUCON CONSULTING ENGINEERS; Engineer: KOMAL PAWAR; Chartered Accountant: Manish K Ramawati And Company; Chartered Accountant: K Hemant & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GULMOHAR TERRACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GULMOHAR TERRACE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GULMOHAR TERRACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.