Home / Browse projects / Pune, Maharashtra / Guardian Eastern Meadows - Phase 1
Guardian Eastern Meadows - Phase 1
By Guardian Promoters & Developers Private Limited
RG-MH-09805 · RERA P52100007435 · Last updated on MahaRERA portal: 24 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 26 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Guardian Eastern Meadows - Phase 1 is a Residential / Group Housing project by Guardian Promoters & Developers Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100007435 on 17 Aug 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 24 months from the original filing. 26 complaints are on record with the regulator.
At a glance
Project
- NameGuardian Eastern Meadows - Phase 1
- TypeResidential / Group Housing
- Location
- Grant Road
- Off Nagar Road
- WAGHOLI
- Haveli
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100007435
- ReraGenie IDRG-MH-09805
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 30 Jun 2021)
- Buildings5 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | NA | 13 | 0 | 0 | 0 | 0 |
| B1 | NA | 13 | 0 | 0 | 0 | 0 |
| C1 | NA | 13 | 0 | 0 | 0 | 0 |
| B4 | NA | 15 | 0 | 0 | 0 | 0 |
| A8 | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
36 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.
A179%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 83% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
B179%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 91% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
C189%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 92% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
B489%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
A889%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 96% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | Yes | 75% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 75% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed278
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A1 | 34 | 34 |
| B1 | 42 | 42 |
| C1 | 96 | 96 |
| B4 | 54 | 54 |
| A8 | 52 | 52 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Yashwant Sakhare & Usha Sakhare | WAGHOLI | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vikas Achalkar |
| Engineer | Spectrum Consultants |
| Partner | Role in project |
|---|---|
| Guardian Promoters & Developers Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to corona-virus and lockdown
Complaints filed with MahaRERA26
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022738 | Sunil Sasidharan Pillai | Manish Sabade | 03/03/2019 |
| CC005000000022745 | Madhuri Gupta | Guardian Promoters and Developers Private Limited | 04/03/2019 |
| CC005000000022823 | Deepanshu Chopra | Manish Sabde | 24/04/2019 |
| CC005000000023117 | Sainath Kotgire | Manish Sabade | 16/11/2019 |
| CC005000000023198 | DEVENDER SINGH GARHA | MANISH SABADE | 03/07/2019 |
| CC005000000064841 | DATTA TUKARAM MANDALE | Manish Murlidhar Sabade | 01/02/2023 |
| CC005000000269545 | Tejashree NIranjan Rane | M/s Guardian Promoters and Developers Pvt. ltd. | 17/10/2023 |
| CC005000000269547 | Lalit Joshi | Guardian Promoters & Developers Private Limited | 17/10/2023 |
| CC005000000269551 | Gurpreet Pannu | M/S Guardian Promoters and Developers Pvt. Ltd. | 17/10/2023 |
| CC005000000269557 | Chintan Shah | M/S Guardian Promoters and Developers Pvt. Ltd | 17/10/2023 |
| CC005000000269552 | Sreekumer Nair | M/S Guardian Promoters and Developers Pvt.Ltd. | 17/10/2023 |
| CC005000000269583 | Usha Padmale | M/S Guardian Developers and Promoters Pvt Ltd | 17/10/2023 |
| CC005000000269598 | Rohit Gupta | M/S Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269588 | Rupesh Sharma | M/S Guardian Promoters and Developers Pvt Ltd | 17/10/2023 |
| CC005000000269607 | Arun Singh | M/S Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269601 | Kaushal Sharma | M/s Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269597 | Viren Kawade | M/S Guardian Promoters and Developers Prv Ltd | 17/10/2023 |
| CC005000000269600 | Nilesh Kumar | M/S Guardian Promoters & Develoers Pvt Ltd | 17/10/2023 |
| CC005000000269599 | Nilesh More | M/S Guardia Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269606 | Aparna Dubey | M/S Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269605 | Atul Nandgavali | M/S Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000269602 | Darbesh Yadav | M/S Guardian Promoters & Developers PVT LTD | 17/10/2023 |
| CC005000000269603 | Avdhut Dalavi | M/S Guardian Promoters & Developers Pvt Ltd | 17/10/2023 |
| CC005000000471442 | Sonal Ramkumar Varma | M/s Guardian Promoter & Developers Pvt.LTD | 06/08/2024 |
| CC005000000471443 | Vinod Tukaram Manerajure | M/s Guardian Promoters & Developers Pvt Ltd | 06/08/2024 |
| CC12501294 | KEDARNATH BALAJI PILAJI | Guardian Promoters & Developers Private Limited | 19/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Ph1 Form 3 CA Certificate sept 23.pdf | 24 Jan 2025 |
| Certificates of CA (Form 3)File: Ph1 Form 3 CA Certificate dec 23.pdf | 24 Jan 2025 |
| Certificates of CA (Form 3)File: Ph1 Form 3 CA Certificate mar 24.pdf | 24 Jan 2025 |
| Certificates of CA (Form 3)File: Ph1 CA Certificate June 24.pdf | 24 Jan 2025 |
| Certificates of CA (Form 3)File: Ph1 Form 3 CA Certificate sept 24.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Ph 1 Dec 23.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Ph 1 Mar 24.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Ph 1 June 24.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Ph 1 Sept 24.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 0323.pdf | 2 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 0923.pdf | 2 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GEM Phase 1 Form V FY 92.pdf | 13 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GEM Phase 1 Form V FY 92.pdf | 13 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: GEM Ph-1-Sold Disclosure_c.pdf | 4 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM-Architect-Ph-1.pdf | 3 Aug 2021 |
| Form 2AFile: GEM-Ph-1 Quality-Jun-21.pdf | 3 Aug 2021 |
| Form 2AFile: GEM-Quality Certificate-Ph-1-Dec-20.pdf | 3 Aug 2021 |
| Form 2AFile: GEM-Quality Certificate-Ph-1 Mar-20.pdf | 3 Aug 2021 |
| Declaration about Commencement CertificateFile: GEM-Commencement Declaration.pdf | 2 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM-Ph-1 Engineer-Jun-21.pdf | 2 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GEM-Quality-Ph-1-Dec-20.pdf | 27 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM-Architect.pdf | 19 Sep 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM-Engineer Certificate-Ph-1 Mar-20.pdf | 19 Sep 2020 |
| Form 2AFile: GEM-Quality Certificate-Ph-1 Mar-20.pdf | 19 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM-Arch-Ph-1.pdf | 17 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM-EN-Ph-1.pdf | 17 Jan 2020 |
| Form 2AFile: GEM-QA-Ph-1.pdf | 17 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: GEM PH-1 RERA-ANUAL RETUE 17-18.PDF | 16 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM-1 Architect Certificate-Sept 19.pdf | 5 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM-1 Engineer Certificate-Sept 19.pdf | 2 Oct 2019 |
| Form 2AFile: GEM-1 Quality Assurance-Sept 19.pdf | 2 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM- Archi Ph-1.pdf | 12 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM Ph-1 -Engg.pdf | 12 Jul 2019 |
| Form 2AFile: GEM_Phase-1 QA.pdf | 1 Jun 2019 |
| Certificates of CA (Form 5)File: CA Certificate.pdf | 31 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM ph1.pdf | 12 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM PH1 EN.pdf | 12 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GEM Ph-1 Architech certificate Dec 2018.pdf | 14 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GEM ph1 Engineer certificate Dec 2018.pdf | 14 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Eastern Meadows Phase 1 Architect 050218.pdf | 13 Feb 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Eastern Meadows Ph 1 Engineer 250118.pdf | 13 Feb 2018 |
| Certificates of CA (Form 3)File: Eastern Meadows Ph1 CA Certificate 311017.pdf | 19 Dec 2017 |
| Declaration in FORM BFile: Eastern Meadows phase 1 promoter Form B Revised.pdf | 24 Nov 2017 |
| Details of encumbrancesFile: Letter of Encumbrances Eastern Meadows R1 1 Nov 17.PDF | 21 Nov 2017 |
| Details of encumbrancesFile: Letter of Encumbrances 1 Nov 17.PDF | 1 Nov 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Eastern Meadows Ph1 Architect 311017.pdf | 1 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Eastern Meadows Ph1 Engineer 311017.pdf | 31 Oct 2017 |
| Certificates of CA (Form 3)File: 1 Eastern Meadows Phase 1 CA 1.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: 1 Eastern Meadows Phase 1 CA Annexure 1.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Eastern Meadows Phase 1 Engineer 1.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Eastern Meadows Phase 1 Architect Final.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: GEM Phase 1 Agreement Draft.pdf | 27 Jul 2017 |
| Declaration in FORM BFile: Eastern Meadows phase 1 promoter Form B.pdf | 25 Jul 2017 |
| Proforma of Allotment letterFile: Allotment_Letter_ Draft OK.pdf | 24 Jul 2017 |
| Building plan approvalFile: GEM Layout.pdf | 17 Jul 2017 |
| Layout approvalFile: GEM Layout.pdf | 17 Jul 2017 |
| PAN CardFile: PAN Card GPDPL.pdf | 17 Jul 2017 |
| Copy of the legal title reportFile: Title Report.pdf | 17 Jul 2017 |
| Details of encumbrancesFile: Letter of Encumbrance_Eastern Meadows.pdf | 17 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: GEM Layout.pdf | 17 Jul 2017 |
| Building Plan Approval (IOD)File: GEM Layout.pdf | 17 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commmencmet GEM.pdf | 17 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Kanchangauri | Kanchan Lane Near Krishna Dining Hall Law college Road Pune-411004 | 19 | Completed | Apr 2014 | Late, Nov 2014 |
| Gaurishankar | Mayur Colony Kothrud Pune-411038 | 10 | Completed | Mar 2014 | Late, May 2014 |
| Aaditya | Shriram Society Warje Pune-411052 | 12 | Completed | Mar 2014 | Late, Jun 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Guardian Eastern Meadows - Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Off Nagar Road13,700+ in Pune
Filed coordinates, straight-line distance. 48 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: Guardian Promoters & Developers Private Limited
Guardian Promoters & Developers Private Limited has 5 registrations on MahaRERA, including Hill Shire Phase-2 and Guardian Anantam. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Guardian Eastern Meadows - Phase 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Guardian Eastern Meadows - Phase 1 is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Guardian Eastern Meadows - Phase 1?
The registered promoter entity is Guardian Promoters & Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Guardian Eastern Meadows - Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Guardian Eastern Meadows - Phase 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Guardian Eastern Meadows - Phase 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Guardian Eastern Meadows - Phase 1?
The professionals named in the filing: Architect: Vikas Achalkar; Engineer: Spectrum Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Guardian Eastern Meadows - Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback