Completed No litigation declared Residential / Group Housing project

Green Woods

By Goldfinger Ventures

RG-MH-10129 · RERA P52100013183 · Last updated on MahaRERA portal: 6 Apr 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 90 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 35 documents Report an error

Green Woods is a Residential / Group Housing project by Goldfinger Ventures in Pune, Maharashtra, registered with MahaRERA as P52100013183 on 18 Sep 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 90 months from the original filing.

At a glance

Project

  • NameGreen Woods
  • TypeResidential / Group Housing
  • Location
    • Salunke Vihar Road
    • Wanowrie
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411040
  • Pincode411040
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100013183
  • ReraGenie IDRG-MH-10129

Builder

  • NameGoldfinger Ventures
  • Entity typePartnership
  • PartnersBharti Jayesh Sangani, Ines Kumar Gupta, Girdhari Thakumal Chandnani, Goldfinger Realty Investors Pvt Ltd Goldfinger Reality Investors Pvt Ltd
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseDec 2017Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Sep 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2017)
  • Buildings1 building record
  • Documents filed35 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BuildingNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Apr 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

A Building: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Apr 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,657 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch00170 Pune Kasarwadi, Pune-Mumbai RO Nana Chambers, opp Siddharth Motors, Kasarwadi, Pune 411034

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLaxman Thite Architect
PartnerRole in project
Goldfinger Ventures-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011620Dec 2017 → Dec 2024

Reason as filed by the promoterAmenity Space was handed over to Pune Municipal Corporation but till date we have not received the TDR in lieu of the same and consequently we have not been able to obtain further sanction and construct the additional units. Wing A presently is constructed of ground floor - parking and upto 2 Upper Floors. The construction of both Wing A and B, as of now, is complete, as per the plans sanctioned and approved by the Pune Municipal Corporation under No. 1804/10 Dt.06.09.10 & 2758/14 dt. 12.12.14 Occupation Certificate of Wing B has been obtained and the same is ready to use & has already been al

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed35

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - Engineers Certificate.pdf6 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - Engineers Certificate.pdf6 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Qality Assurance.pdf6 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory.pdf6 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 17-18.pdf6 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 18-19.pdf6 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: From 5 FY 19-20.pdf6 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate_compressed (1).pdf25 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf25 Mar 2022
Declaration about Commencement CertificateFile: Form D.pdf25 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf25 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2.pdf25 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Qality Assurance.pdf25 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Qality Assurance.pdf25 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200233155583_For_Asset_Based_Search_23_03_2022_12_15_27_606.pdf25 Mar 2022
Certificates of CA (Form 3)File: Form 3.PDF25 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 -Scanned.pdf25 Mar 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Certificate.pdf31 Oct 2020
Details of encumbrancesFile: Self Decaration.pdf31 Jul 2017
Declaration in FORM BFile: Form B Promoter.pdf31 Jul 2017
Proforma of Allotment letterFile: RERA Draft Agreement and Allotment letter.pdf31 Jul 2017
OtherFile: SNo 86 3 4 A 4.pdf31 Jul 2017
OtherFile: SNo 86 3 4 A 4.pdf31 Jul 2017
OtherFile: SNo 86 3 4A 5.pdf31 Jul 2017
OtherFile: S86.pdf31 Jul 2017
OtherFile: S364aa.pdf31 Jul 2017
OtherFile: S863a.pdf31 Jul 2017
Building plan approvalFile: 1st2nd.pdf30 Jul 2017
Layout approvalFile: Layout.pdf30 Jul 2017
Copy of the legal title reportFile: Title Certificate.PDF30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf30 Jul 2017
Building Plan Approval (IOD)File: 1st2nd.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Vikas SheelSr No 497 Hiss no 29 Hiss na 1 Kasarwadi Pune 411 03442CompletedOct 2013Oct 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 90 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Green Woods on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wanowrie13,700+ in Pune

2 kmGreen WoodsCompleted 3Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Goldfinger Ventures

Goldfinger Ventures has 1 registration on MahaRERA, including Green Woods. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Green Woods is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Green Woods?

The registered promoter entity is Goldfinger Ventures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Green Woods?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Green Woods?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Green Woods?

The professionals named in the filing: Architect: Laxman Thite Architect. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Green Woods?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Green Woods. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Green Woods to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.