Home / Browse projects / Aurangabad, Maharashtra / GREEN WOODS

Registered No litigation declared Residential / Group Housing project

GREEN WOODS

By CHINTAMANI INFRASTRUCTURE

RG-MH-08791 · RERA P51500022372 · Last updated on MahaRERA portal: 10 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 33 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 33 months from the original
218 of 561Construction stages doneacross 51 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

GREEN WOODS is a Residential / Group Housing project by CHINTAMANI INFRASTRUCTURE in Aurangabad, Maharashtra, registered with MahaRERA as P51500022372 on 16 Sep 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 33 months from the original filing.

At a glance

Project

  • NameGREEN WOODS
  • TypeResidential / Group Housing
  • Location
    • GOLWADI
    • Aurangabad
    • 431005
  • Pincode431005
  • RERA no.P51500022372
  • ReraGenie IDRG-MH-08791

Builder

  • NameCHINTAMANI INFRASTRUCTURE
  • Entity typePartnership
  • PartnersSATISH BHAGCHAND SETHI, PUSHPALATA SATYANARAYAN KALANI, NILESH RAJKUMAR KASLIWAL, INDERCHAND LAKHMICHAND SETHI

Key dates

this monthRegisteredSep 2019First promiseMar 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Sep 2019
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Mar 2025)
  • Buildings51 building records
  • Documents filed104 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING-ANA80000
BUILDING-BNA80000
BUILDING-CNA80000
BUILDING-DNA80000
RH-01NA20000
RH-02NA20000
RH-03NA20000
RH-04NA20000
RH-05NA20000
RH-06NA20000
RH-07NA20000
RH-08NA20000
RH-09NA20000
RH-10NA20000
RH-11NA20000
RH-12NA20000
RH-13NA20000
RH-14NA20000
RH-15NA20000
RH-16NA20000
RH-17NA20000
RH-18NA20000
RH-19NA20000
RH-20NA20000
RH-21NA20000
RH-22NA20000
RH-23NA20000
RH-24NA20000
RH-25NA20000
RH-26NA20000
RH-27NA20000
RH-28NA20000
RH-29NA20000
RH-30NA20000
RH-31NA20000
RH-32NA20000
RH-33NA20000
RH-34NA20000
RH-35NA20000
RH-36NA20000
RH-37NA20000
RH-38NA20000
RH-39NA20000
RH-40NA20000
RH-41NA20000
RH-42NA20000
RH-43NA20000
RH-44NA20000
RH-45NA20000
RH-46NA20000
RH-47NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 10 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 51 buildings; the table lists the first 20.

218 of 561 construction stages are filed complete across 51 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

BUILDING-A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING-B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING-C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING-D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RH-0191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH-0291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH-0386%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH-0475%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
RH-0575%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
RH-0691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH-0775%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
RH-0875%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
RH-0972%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1072%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1172%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1272%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1372%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1472%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1572%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
RH-1662%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 10 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered5
Open Space32
BuildingClosed/CoveredOpen SpaceTotal
BUILDING-A189
BUILDING-B189
BUILDING-C189
BUILDING-D189
RH-18101

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DIAMOND INFRASTRUCTURE-Aurangabad

Approvals and building plan

Permissible FSI12612.28
Proposed, not sanctioned12,612 sq m
Buildings approved51
Buildings sanctioned51

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCIDCO, AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYASHODHAN PATHAK
EngineerAMOL KALANI
Chartered AccountantN R BHATTAD & ASSOCIATES
PartnerRole in project
CHINTAMANI INFRASTRUCTURE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500028373Mar 2025 → Dec 2027

Reason as filed by the promoterTechical Reason

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 1 Form-1 June 25 (O).pdf10 Mar 2026
Form 2File: 2 Form-2 June 25.pdf10 Mar 2026
Form 3File: 3 Form-3 Jun 25.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: 4 Sold June 25.pdf10 Mar 2026
Form 1File: 1 Form-1 June 25 (O).pdf10 Mar 2026
Form 2File: 2 Form-2 June 25.pdf10 Mar 2026
Form 3File: 3 Form-3 Jun 25.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: 4 Sold June 25.pdf10 Mar 2026
Declaration in FORM BFile: Form B.pdf28 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 June 25_compressed.pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Green Form 3 Dec 22 (Final).pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Green Form 3 Mar 24 (Final).pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Green Form-3 Dec 24 (Final).pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form-3 Jun 25.pdf28 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form-2 June 25.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: 1 Sold Dec 24.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: 1 Sold Mar 25.pdf28 Jul 2025
Disclosure of sold/ booked inventoryFile: 1 Sold Jun 25.pdf28 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Form-1 March 20_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 Dec 19_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 22 Form-1 March 25_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 21 Form-1 Dec 24_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20 Form-1 Sep 24_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 19 Form-1 June 24_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 18 Form-1 March 24_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17 Form-1 Dec 23_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 16 Form-1 Sep 23_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 Form-1 June 23_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 Form-1 March 23_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 Form-1 Dec 22_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Form-1 June 22_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Form-1 March 22_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Form-1 Dec 21_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Form-1 Sep 21_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Form-1 June 21_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Form-1 March 21_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Form-1 Dec 20_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Form-1 Sep 20_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form-1 June 20_11zon.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 Form-1 Sep 22_11zon.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 Form-3 Sep 22 (FS).pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Green Form 3 Dec 22_11zon.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 Form-3 March 23.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 15 Form-3 June 23.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 16 Form-3 Sep 23.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 Form-3 Dec 23.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Green Form 3 Mar 24_11zon.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 19 Form-3 June 24.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20 Form-3 Sep 24.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Green Form-3 Dec 24_11zon.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 22 Form-3 March 25.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Form-3 March 22.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 Form-3 Dec 21.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Form-3 Sep 21.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Form-3 June 21.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Form-3 March 21.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Form-3 Dec 20.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form-3 Sep 20.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form-3 June 20.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form-3 March 20.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form-3 Dec 19.pdf20 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 Form-3 June 22.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 Form-2 Dec 22.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 Form-2 Dec 21.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 Form-2 March 23.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 15 Form-2 June 23.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 16 Form-2 Sep 23.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 17 Form-2 Dec 23.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 18 Form-2 March 24.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 19 Form-2 June 24.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20 Form-2 Sep 24.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 21 Form-2 Dec 24.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 22 Form-2 March 25.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Form-2 Sep 22.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Form-2 June 22.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form-2 March 22.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 Form-2 Sep 21.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Form-2 June 21.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 Form-2 March 21.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Form-2 Dec 20.pdf20 Jun 2025

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 33 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep GREEN WOODS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOLWADI1,400+ in Aurangabad

Builder: CHINTAMANI INFRASTRUCTURE

CHINTAMANI INFRASTRUCTURE has 1 registration on MahaRERA, including GREEN WOODS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if GREEN WOODS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GREEN WOODS?

The registered promoter entity is CHINTAMANI INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GREEN WOODS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GREEN WOODS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GREEN WOODS?

The professionals named in the filing: Architect: YASHODHAN PATHAK; Engineer: AMOL KALANI; Chartered Accountant: N R BHATTAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN WOODS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN WOODS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN WOODS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.