Green Alley Phase - II
RG-MH-34906 · RERA P52100049768 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Green Alley Phase - II is a Others project by ARYAN DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100049768 on 24 Feb 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 13 of the 15 units on this registration are recorded sold or booked, and 45 of 165 construction stages are filed complete.
At a glance
Project
- NameGreen Alley Phase - II
- TypeOthers
- Location
- VISHAL NAGAR
- PIMPLE NILAKH
- Haveli
- Pune
- 411027
- Pincode411027
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100049768
- ReraGenie IDRG-MH-34906
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Feb 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings15 building records
- Documents filed94 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ROW HOUSE 15 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 14 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOIUSE 11 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 13 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 12 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 10 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 9 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 8 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 7 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 6 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 5 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 4 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 3 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 2 | NA | 3 | 3 | 1 | 0 | 1 |
| ROW HOUSE 1 | NA | 3 | 3 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
45 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is Internal walls, at 95%.
ROW HOUSE 1555%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 1455%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOIUSE 1155%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 1355%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 1255%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 1055%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 955%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 855%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 755%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 655%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 555%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 455%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 355%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 255%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
ROW HOUSE 155%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed75
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| ROW HOUSE 15 | 5 | 5 |
| ROW HOUSE 14 | 5 | 5 |
| ROW HOIUSE 11 | 5 | 5 |
| ROW HOUSE 13 | 5 | 5 |
| ROW HOUSE 12 | 5 | 5 |
| ROW HOUSE 10 | 5 | 5 |
| ROW HOUSE 9 | 5 | 5 |
| ROW HOUSE 8 | 5 | 5 |
| ROW HOUSE 7 | 5 | 5 |
| ROW HOUSE 6 | 5 | 5 |
| ROW HOUSE 5 | 5 | 5 |
| ROW HOUSE 4 | 5 | 5 |
| ROW HOUSE 3 | 5 | 5 |
| ROW HOUSE 2 | 5 | 5 |
| ROW HOUSE 1 | 5 | 5 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 2.00 cr | Rs 51.39 lakh |
| ROW HOUSE 15 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 14 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOIUSE 11 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 13 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 12 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 10 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 9 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 8 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 7 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 6 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
| ROW HOUSE 5 | NA | Rs 58.43 lakh | Rs 56.49 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shrinivas Pandit |
| Engineer | Mayur Belose |
| Chartered Accountant | G N Mantri & Associates |
| Chartered Accountant | Yashkumar Santosh Soni |
| Chartered Accountant | A N J K & CO LLP |
| Chartered Accountant | RV Nevatia & Co |
| Partner | Role in project |
|---|---|
| ARYAN DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe hereby request an extension of the project timeline under RERA due to unforeseen delays caused by a shortage of both skilled labour and essential construction materials. Over the past few months, our project has faced significant disruptions in workforce availability, which has slowed down on-site progress. Additionally, the supply chain for critical raw materials such as cement and steel has been inconsistent, leading to delays in procurement and execution of key construction activities. certain row houses within the project have been sold with specific customization requests from respecti
Reason as filed by the promoterThe construction progress of the project Green Alley Phase - II has been affected due to shortage of skilled labour force and irregular availability of essential raw materials, which resulted in delay in the execution of construction activities. The remaining work shall be completed within the extended timeline requested, and the Completion Certificate / Occupancy Certificate shall be obtained on or before 31.12.2026, i.e. before the expiry of the extension period sought. In view of the above, we humbly request an extension for completion of the project to enable us to complete the pending con
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jan 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Withdrawal Application Form1.PDF | 20 Jul 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.PDF | 20 Jul 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form 1.PDF | 21 Apr 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.PDF | 21 Apr 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.PDF | 21 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate.PDF | 21 Apr 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.PDF | 20 Jan 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.PDF | 20 Jan 2026 |
| Form 5 (FY 2024-2025)File: CA Form 5 FY 2024-25 Green Alley Phase II_Signed.PDF | 4 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Quality Assurance Certificate_Signed.PDF | 30 Oct 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 - Green Alley Phase II.pdf | 25 Oct 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 - Green Alley Phase II.pdf | 25 Oct 2025 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 - Green Alley Phase II.pdf | 25 Oct 2025 |
| Withdrawal Update Form 1File: Form-1_11zon.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: Form-2.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: Form-3.pdf | 24 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - March 2025.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Aryan Developers March 2025 - Signed.pdf | 25 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - March 2025.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Aryan Developers - March 2025.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Dec 2024.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format Signed - Aryan Developers December 2024.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Dec 2024.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Aryan Developers - December 2024.pdf | 18 Jan 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Format A on Separate bank account.pdf | 19 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5 23-24 Green Alley Phase II_ FY 23-24_Signed_11zon.pdf | 26 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 22 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Sept 2024 - Sign.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Sept 2024.PDF | 22 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - ARYAN DEVELOPERS.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - March 2024.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - June 2024.PDF | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - March 2024.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - June 2024.PDF | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance 2023-24.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - March 2024.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - June 2024.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Aryan Developers March 2024.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - June 2024- Sign.pdf | 20 Jul 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Format A on separate bank account.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Oct Nov Dec2022.pdf | 26 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Jan Feb Mar2023.pdf | 26 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Apr May June 2023.pdf | 26 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Oct Nov Dec2022.pdf | 26 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Jan Feb Mar2023.pdf | 26 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Apr May June 2023.pdf | 26 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate - Jan Feb Mar 2023.pdf | 26 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Apr To Sep- 2023.pdf | 26 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ARYAN DEVELOPERS form5.pdf | 23 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ARYAN DEVELOPERS form5.pdf | 23 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Apr May June 2023.pdf | 19 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Jan Feb Mar 2023.pdf | 19 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE - Oct Nov Dec 2022.pdf | 19 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Apr May June 2023.pdf | 19 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Jan Feb Mar 2023.pdf | 19 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE - Oct Nov Dec 2022.pdf | 19 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate - July Aug Sep 2023.pdf | 19 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate - Oct Nov Dec 2022.pdf | 19 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality.pdf | 14 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Aryan Developers June 2023.pdf | 14 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Aryan Developers March 2023.pdf | 14 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2ARCHITECT'S CERTIFICATE.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2ARCHITECT'S CERTIFICATE.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3ARCHITECT'S CERTIFICATE.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4ARCHITECT'S CERTIFICATE.pdf | 13 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1ENGINEER'S CERTIFICATE.pdf | 13 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2ENGINEER'S CERTIFICATE.pdf | 13 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3ENGINEER'S CERTIFICATE.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE REVISED 03102023.pdf | 21 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARYAN DEVELOPERS - ENGINEER'S CERTIFICATE Maha RERA.pdf | 21 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 1.pdf | 21 Nov 2023 |
| Declaration about Commencement CertificateFile: FORMAT D - RERA.PDF | 20 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A - RERA ARYAN DEVELOPERS GREEN ALLEY PH 2.pdf | 15 Feb 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_UPDATED.pdf | 10 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Aryan Developers -GREEN ALLEY PH 2.pdf | 10 Feb 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf | 8 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: RERA - DISCLOSER OF INTEREST.pdf | 3 Feb 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| galaxy | wakad | 225 | Completed | Dec 2023 | Dec 2022 |
| green valley | wakad | 179 | Completed | Dec 2019 | Dec 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Green Alley Phase - II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PIMPLE NILAKH13,700+ in Pune
Filed coordinates, straight-line distance. 201 registered projects within 2 km.
VANTAGE TWENTY ONE
VIVANTA REALTY
SHAKTI GARDENS
Grandwell Properties and Leasing Private L
24K OPULA
KOLTE-PATIL DEVELOPERS LIMITED
Sukhwani Minerva
Sukhwani Ramchandani LLP
MIDORI TOWER PHASE 4
VIKRAM DEVELOPERS AND PROMOTERS
Sai Aura
WJV LANDMARKS LLP
Builder: ARYAN DEVELOPERS
ARYAN DEVELOPERS has 7 registrations on MahaRERA, including Mayuri Gold Leaf and Mayuri Residency. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Green Alley Phase - II is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Green Alley Phase - II?
The registered promoter entity is ARYAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Green Alley Phase - II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Green Alley Phase - II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Green Alley Phase - II?
The professionals named in the filing: Architect: Shrinivas Pandit; Engineer: Mayur Belose; Chartered Accountant: G N Mantri & Associates; Chartered Accountant: Yashkumar Santosh Soni; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: RV Nevatia & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Green Alley Phase - II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.