GRAND EIGHT

By SNEHA SHIRISH GADIYA

RG-MH-08826 · RERA P51500022348 · Last updated on MahaRERA portal: 18 Feb 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 48 months past the filed date
  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Oct 2022Possession promised48 months past this date
0 of 66Construction stages doneacross 6 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

GRAND EIGHT is a Residential / Group Housing project by SNEHA SHIRISH GADIYA in Aurangabad, Maharashtra, registered with MahaRERA as P51500022348 on 16 Sep 2019. Possession was promised by 31 Oct 2022 and is now 48 months past that date. The completion date has moved by 7 months from the original filing.

At a glance

Project

  • NameGRAND EIGHT
  • TypeResidential / Group Housing
  • Location
    • PAITHAN ROAD
    • GOLWADI
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • RERA no.P51500022348
  • ReraGenie IDRG-MH-08826

Builder

  • NameSNEHA SHIRISH GADIYA
  • Entity typeIndividual

Key dates

48 months past promisethis monthRegisteredSep 2019First promiseMar 2022Revised toOct 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Sep 2019
  • Promised completion31 Oct 2022
  • Revised completionRevised to 31 Oct 2022 (originally 30 Mar 2022)
  • Buildings6 building records
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW 01NA20000
BUNGALOW02NA20000
BUNGALWO 03NA20000
BUNGALOW 04NA20000
BUNGALOW 0506NA20000
BUNGALOW 0708NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 18 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Excavation, at 0%.

BUNGALOW 010%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW020%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALWO 030%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 040%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 05060%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW 07080%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Open Space6
BuildingOpen SpaceTotal
BUNGALOW 0111
BUNGALOW0211
BUNGALWO 0311
BUNGALOW 0411
BUNGALOW 050611
BUNGALOW 070811

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,670 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1670.0
Proposed, not sanctioned1,245 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNDLIKNAGAR, AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUNIL M BHALE
Engineeryouraj shrimandale
Chartered AccountantCHANDAN BORA
PartnerRole in project
SNEHA SHIRISH GADIYA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500012448Mar 2022 → Oct 2022

Reason as filed by the promoterMost of bunglows are ready to move. For Buglow number 1, some alterations are suggested by the customer, Hence this extension is requires.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Feb 2023

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_Certificate_Grand_Eight.pdf18 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Grand_8_2020-21.pdf18 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Grand_Eight_2021-22.pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form_2A_Grand_Eight_2020-21.pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A_Grand_Eight_2021-22.pdf18 Feb 2023
Disclosure of sold/ booked inventoryFile: BOOKED UNITS.pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_Grand_Eight_2020-21.pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_Grand_Eight_2021-22.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5_Grand_8_2020-21.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_Grand_8_2021-22.pdf18 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part_Occupancy_Certificate_Grand_Eight.pdf18 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Grand_Eight_Society_Registration.pdf18 Feb 2023
Building plan approvalFile: 1.pdf10 Sep 2019
Building plan approvalFile: 2.pdf10 Sep 2019
Building plan approvalFile: 3.pdf10 Sep 2019
Building plan approvalFile: 4.pdf10 Sep 2019
Layout approvalFile: 1.pdf10 Sep 2019
PAN CardFile: Sneha_Gadiya_-_PAN.pdf10 Sep 2019
Copy of the legal title reportFile: TITLE-REPORT.pdf10 Sep 2019
Copy of the legal title reportFile: Court Permission 1 (2).pdf10 Sep 2019
Details of encumbrancesFile: Declaration_No ENCUM.pdf10 Sep 2019
Copy of Layout Approval (in case of layout)File: 1.pdf10 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf10 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf10 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf10 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf10 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: Cidco Letter Permission.pdf10 Sep 2019
Declaration in FORM BFile: Form_no_B.pdf10 Sep 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf10 Sep 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf10 Sep 2019
Proforma of Allotment letterFile: Agreement To Sale (1).pdf10 Sep 2019
Proforma of Allotment letterFile: Agreement To Sale (2).pdf10 Sep 2019
Proforma of Allotment letterFile: Agreement To Sale (3).pdf10 Sep 2019
Proforma of Allotment letterFile: Allotment Letter.pdf10 Sep 2019
OtherFile: Court Permission 1 (2).pdf10 Sep 2019
OtherFile: P Deed (1).pdf10 Sep 2019
OtherFile: P Deed (2).pdf10 Sep 2019

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 7 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep GRAND EIGHT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOLWADI1,400+ in Aurangabad

Builder: SNEHA SHIRISH GADIYA

SNEHA SHIRISH GADIYA has 1 registration on MahaRERA, including GRAND EIGHT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that GRAND EIGHT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GRAND EIGHT is delayed beyond 31 Oct 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GRAND EIGHT?

The registered promoter entity is SNEHA SHIRISH GADIYA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GRAND EIGHT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GRAND EIGHT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GRAND EIGHT?

The professionals named in the filing: Architect: SUNIL M BHALE; Engineer: youraj shrimandale; Chartered Accountant: CHANDAN BORA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GRAND EIGHT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GRAND EIGHT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GRAND EIGHT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.