Red flags

  • Litigation declared, 4 cases
  • Rs 350.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
4 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 7%
8 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 91 documents Report an error

Golfland V and VI is a Residential / Group Housing project by IMAGE REALTY PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100052531 on 8 Sep 2023. Possession is promised by 31 Dec 2029. 130 of the 138 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.

At a glance

Project

  • NameGolfland V and VI
  • TypeResidential / Group Housing
  • Location
    • Oxford City Township
    • Lavale
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • RERA no.P52100052531
  • ReraGenie IDRG-MH-75963

Builder

  • NameIMAGE REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU68200MH2026PTC465298
  • GSTIN27AAICI6208F1ZM
  • PartnersNirav Bhupendra Dalal, Haresh Jayantilal Shah, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal, Haresh Jayantilal Shah, Nirav Bhupendra Dalal
  • Other registrations9 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2023PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Sep 2023
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed91 files

Current status

94%130 of 138 units booked
36.8%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower- 5NA232361061
Tower- 6NA232377077

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 7%.

Tower- 519%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower- 618%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure1%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed260

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots260
Closed/Covered260
BuildingClosed/CoveredTotal
Tower- 5131131
Tower- 6129129

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,717 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofIDBI TRUSTEE SHIP SERVICES LTD
Secured amountRs 350.00 crore
CERSAI search filedYes
Declared on10 Dec 2025
LandownerVillageDistrict
Knowledge City Education Private LimitedPune (CB)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI25035.46
Proposed, not sanctioned25,035 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRPG Towers- Ground Floor 248- Andheri Kurla Road- JB Nagar- Andheri East- Mumbai-40005
Estimated costRs 170.73 cr
Cost incurredRs 62.89 cr
Work done36.84%
BuildingWingEstimatedIncurred
Tower- 6NARs 73.98 crRs 31.52 cr
Tower- 5NARs 68.49 crRs 29.80 cr
-NARs 28.25 crRs 1.58 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParag Deshpande
EngineerAjit Kulkarni
Chartered AccountantBR Nagda & Co
Chartered AccountantHarshad Doshi & Co.
PartnerRole in project
IMAGE REALTY PRIVATE LIMITED-

Litigation declared4

CaseCourtStatus
700/2014Civil Judge Senior Division PunePending
1796/2006Civil Judge Senior Division PunePending
1074/2007Civil Judge Junior Division PunePending
700/2014Court of Civil Judge Senior DivisionOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed91

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Golfland V and VI Certificate 31 03 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate Golfland V and VI 31 03 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: 20260331 RERA Certificate OCR 1 T5 Golf Land V and VI.pdf20 Apr 2026
Withdrawal Update Form 1File: MahaRERA_Architect Certificate_Golfland V and VI_31 12 2025.pdf29 Jan 2026
Withdrawal Update Form 2File: Golfland V and VI_Eng Cert.pdf29 Jan 2026
Withdrawal Update Form 3File: 20251231 RERA Certificate OCR 1 T5 and T6 Golf Land V and VI.pdf29 Jan 2026
Form 1File: Architect Certificate_OCR 1 T5 and T6.pdf20 Oct 2025
Form 2File: Golfland V and VI.pdf20 Oct 2025
Form 3File: 20250930 RERA Certificate OCR 1 T5_6 Golf Land V & VI - RERA.pdf20 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 OCR 1 T5_T6 Golf Lands V & VI.pdf30 Sep 2025
Form 1File: Architect Certificate Golfland V and VI_01 07 2025.pdf15 Jul 2025
Form 2File: Eng Cert Golfland V and VI_01 07 2025.pdf15 Jul 2025
Form 3File: CA Certificate OCR 1 T5_6 Golf Land V and VI.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf15 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Golfland V and VI_Certificate_31 03 2024.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Golfland V and VI.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MahaRERA_Architect Certificate Golfland V and VI 19 10 2024.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Golfland V and VI.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Golfland V and VI 21 01 2025.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MahaRERA_Architect Certificate_Golfland V and VI 28 03 2025.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate OCR 1 T5_6 Golfland V and VI.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 23 02 2025 RERA Certificate OCR 1 T5_6 Golf Land V and VI - RERA.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20250331 RERA Certificate OCR 1 T5_6 Golf Land V and VI Form 3.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Golfland V and VI_Eng Cert.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Golfland V and VI.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_ Golfland V and VI.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Golfland V and VI.pdf13 May 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 OCR 1 T5 T6 Golf Lands V and VI.pdf10 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20231231 Form 3 Golfland V and VI.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf21 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Golfland V and VI.pdf5 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration for CA Certificate Golfland V and VI.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Golfland V and VI.pdf18 Apr 2024
Other - TechnicalFile: OCR -1_North Orientation.pdf14 Mar 2024
Copy of the legal title reportFile: Addendum RERA Report-1660.pdf17 Feb 2024
Copy of the legal title reportFile: Addendum RERA Report-1177.pdf17 Feb 2024
Proforma of Agreement for saleFile: AFS -Golfland 5 and 6- Post Demerger Amendment RERA Version.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Golfland V and VI.pdf7 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Golfland V and VI_Eng Cert.pdf7 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Declaration_Golfland V and VII.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Declaration_Golfland V and VII.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Units Golfland V and VI.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Declaration V and VI.pdf31 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Declaration V and VI.pdf31 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory Golfland V and VI.pdf31 Oct 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrance_Project 3.pdf27 Sep 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrance_Project 3.pdf27 Sep 2023
Copy of the legal title reportFile: Phase 3 - Declaration.pdf26 Aug 2023
CERSAI detailsFile: Phase 3 CERSAI.pdf26 Aug 2023
Other - FinanceFile: Phase 3 CERSAI.pdf26 Aug 2023
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (49).pdf23 Aug 2023
Details of encumbrances concerned to FinanceFile: All Documents_ Project 3_4-4.pdf23 Aug 2023
Details of encumbrances concerned to FinanceFile: All Documents_ Project 3_5-end.pdf23 Aug 2023
Details of encumbrances concerned to LegalFile: All Documents_ Project 3_4-4.pdf23 Aug 2023
Details of encumbrances concerned to LegalFile: All Documents_ Project 3_5-end.pdf23 Aug 2023
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (49).pdf23 Aug 2023
CERSAI detailsFile: Asset Based Search Report - v vi.pdf23 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: output (2) (3).pdf23 Aug 2023
Proforma of Agreement for saleFile: AFS-Golfland 5 and 6 (1)_SP.pdf23 Aug 2023
Building plan approvalFile: final plan_11zon.pdf8 Aug 2023
Building plan approvalFile: Common.pdf8 Aug 2023
Building plan approvalFile: 47-93.pdf8 Aug 2023
Building plan approvalFile: 48-93.pdf8 Aug 2023
Building plan approvalFile: Part 1.pdf8 Aug 2023
Building plan approvalFile: Part 2.pdf8 Aug 2023
Building plan approvalFile: Part 3.pdf8 Aug 2023
Building plan approvalFile: Part 4.pdf8 Aug 2023
PAN CardFile: 1 PAN Card.pdf8 Aug 2023
Copy of the legal title reportFile: Final 1660 Title_11zon.pdf8 Aug 2023
Copy of the legal title reportFile: Dv14706 Legal Title Report - 1177_11zon.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: final plan_11zon.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Common.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 47-93.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 48-93.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Part 1.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Part 2.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Part 3.pdf8 Aug 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
YAHAVI-TOWER-3-TEAKP52100028033OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI-TOWER-2-PINEP52100028082OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI-TOWER-1-OAKP52100028031OXFORD GOLF COURSE, Pune218Jan 2021CompletedJun 2024Jun 2024
YAHAVI RETAILP52100031784OXFORD GOLF COURSE, Pune19Nov 2021CompletedJun 2024Jun 2024

How this compares with Pune

94%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Golfland V and VI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lavale13,700+ in Pune

Builder: IMAGE REALTY PRIVATE LIMITED

IMAGE REALTY PRIVATE LIMITED has 10 registrations on MahaRERA, including VANAHA SPRINGS T1 WILLOW and VANAHA SPRINGS T2 CEDAR. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Golfland V and VI is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Golfland V and VI?

The registered promoter entity is IMAGE REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U68200MH2026PTC465298 and GSTIN 27AAICI6208F1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Golfland V and VI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Golfland V and VI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Golfland V and VI?

The professionals named in the filing: Architect: Parag Deshpande; Engineer: Ajit Kulkarni; Chartered Accountant: BR Nagda & Co; Chartered Accountant: Harshad Doshi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Golfland V and VI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Golfland V and VI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Golfland V and VI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.