ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Golden Van

Registration lapsed No litigation declared Residential / Group Housing project

Golden Van

By A PLUS DEVELOPERS

RG-MH-03231 · RERA P52000020754 · Last updated on MahaRERA portal: 29 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 8 months past the filed date
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Feb 2026Possession promised8 months past this date
16 of 55Construction stages doneacross 5 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Golden Van is a Residential / Group Housing project by A PLUS DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000020754 on 8 May 2019. Possession was promised by 28 Feb 2026 and is now 8 months past that date. The completion date has moved by 11 months from the original filing.

At a glance

Project

  • NameGolden Van
  • TypeResidential / Group Housing
  • Location
    • Ardhe
    • Karjat
    • Raigarh
    • 410101
  • Pincode410101
  • RERA no.P52000020754
  • ReraGenie IDRG-MH-03231

Builder

  • NameA PLUS DEVELOPERS
  • Entity typePartnership
  • PartnersNarottam Meghajibhai Patel, Hitesh Bhikhabhai Karelia
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live5 lapsed, de-registered or revoked

Key dates

8 months past promisethis monthRegisteredMay 2019First promiseMar 2025Revised toFeb 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 May 2019
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 30 Mar 2025)
  • Buildings5 building records
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A1NA90000
WING A2NA90000
WING A3NA90000
WING A4NA90000
WING A5NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 29 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 0%.

WING A10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING A291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING A327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING A40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING A527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered50
Open Space13
BuildingClosed/CoveredOpen SpaceTotal
WING A112820
WING A212012
WING A312315
WING A412012
WING A5224

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,422 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14595.33
Proposed, not sanctioned14,595 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBADLAPUR EAST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDharmesh V Balani Destination Architecture Interior Designer
EngineerSamarth Agarwal
PartnerRole in project
A PLUS DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000028183Mar 2025 → Feb 2026

Reason as filed by the promoterWe have Applied for Extension of Project until date 28.02.2026; Reason for Delay of the Project was due to unavailability of Construction Material Dumped at the Construction site Premises; due to Road Re-construction work and the narrow road approaching site.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3 March 2025.pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: golden van form 2 A (19-20).pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: golden van form 2A (20-21).pdf29 May 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf29 May 2025
Other - TechnicalFile: PERT Chart.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: golden van form 2A (21-22).pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: golden van form 2A (22-23).pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf29 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: golden van form 2A (23-24).pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf29 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 24-25.pdf29 May 2025
Declaration about Commencement CertificateFile: CC DECLARATION.pdf30 Apr 2025
Proforma of Agreement for saleFile: AGRMNT 1.pdf30 Apr 2025
Proforma of Agreement for saleFile: AGRMNT 2.pdf30 Apr 2025
Proforma of Agreement for saleFile: AGRMNT 3.pdf30 Apr 2025
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE TO LEGAL.pdf29 Apr 2025
CERSAI detailsFile: CERSAI.pdf29 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf29 Apr 2025
Deviation Report with respect to Allotment letterFile: DEVIATION TO ALLOTMENT.pdf29 Apr 2025
Details of encumbrances concerned to LegalFile: ENCUMBRANCE TO LEGAL.pdf29 Apr 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION TP AGREEMENT.pdf29 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE IN OTHER.pdf29 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B BANK.pdf29 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: SECURED UNSECURED.pdf29 Apr 2025
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE F.pdf12 Apr 2025
Declaration in FORM BFile: FORM B.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_GOLDEN VAN.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_F.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: BOOKING DISCLOSURE_F.pdf28 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 GOLDEN VAN.pdf7 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GOLDEN VAN.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE f.pdf7 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architech certificate.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf31 Jan 2024
Certificates of CA (Form 3)File: FORM 3 UPLOADED.pdf31 Jan 2024
Copy of the legal title reportFile: GOLDEN VAN TITLE REPORT.pdf28 May 2019
Layout approvalFile: PLan Layout.pdf3 May 2019
Copy of the legal title reportFile: Title Report.pdf3 May 2019
Details of encumbrancesFile: No Encumbrance Certificate.pdf3 May 2019
Copy of Layout Approval (in case of layout)File: PLan Layout.pdf3 May 2019
Declaration in FORM BFile: Form B.pdf3 May 2019
Certificates of CA (Form 3)File: CA Certificate_compressed.pdf3 May 2019
Proforma of Allotment letterFile: Declaration for sale Agreement.pdf3 May 2019
Building plan approvalFile: Approval _ Goldenvan.pdf26 Apr 2019
PAN CardFile: PAN Card.pdf26 Apr 2019
Building Plan Approval (IOD)File: Approval _ Goldenvan.pdf26 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Approval _ Goldenvan.pdf26 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate PHASE 1.pdf26 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Engineer Certificate Phase 1 GOLDEN VAN.pdf26 Apr 2019

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 11 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Golden Van on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ardhe5,900+ in Raigarh

Builder: A PLUS DEVELOPERS

A PLUS DEVELOPERS has 6 registrations on MahaRERA, including GOLDEN VANN - PHASE 1 and GOLDEN VANN - PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Golden Van shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Golden Van is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Golden Van?

The registered promoter entity is A PLUS DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Golden Van?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Golden Van?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Golden Van?

The professionals named in the filing: Architect: Dharmesh V Balani Destination Architecture Interior Designer; Engineer: Samarth Agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Golden Van?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Golden Van. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Golden Van to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.