ReraGenieLog inGet a buyer report

Home / Browse projects / Satara, Maharashtra / Golden Leaf

Registered No litigation declared Plotted project

Golden Leaf

By Irfan Ahmed Younus Shaikh

RG-MH-22302 · RERA P52700030953 · Last updated on MahaRERA portal: 22 Sep 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedno revision filed
60 of 60Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Golden Leaf is a Plotted project by Irfan Ahmed Younus Shaikh in Satara, Maharashtra, registered with MahaRERA as P52700030953 on 29 Sep 2021. Possession is promised by 30 Oct 2027. 0 of the 60 units on this registration are recorded sold or booked.

At a glance

Project

  • NameGolden Leaf
  • TypePlotted
  • Location
    • Gat No 152/1152/2 Mouje Palashi Tal Khandala Dist Satara
    • Khandala
    • Palashi
    • Satara
    • 415540
  • Pincode415540
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700030953
  • ReraGenie IDRG-MH-22302

Builder

  • NameIrfan Ahmed Younus Shaikh
  • Entity typeIndividual

Key dates

this monthRegisteredSep 2021PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Sep 2021
  • Promised completion30 Oct 2027
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed77 files

Current status

0%0 of 60 units booked

Figures as on 22 Sep 2021, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 22 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,300 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI17214.75
Proposed, not sanctioned17,215 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch218 Vishvasta Bhavan Pratapganj Peth Veer Sawarkar Marg Satara 415002

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Chandrashekhar V Pawar
EngineerVidya M Khole
Chartered AccountantMr Prafull S Shaha
PartnerRole in project
Irfan Ahmed Younus Shaikh-

Litigation declared3

CaseCourtStatus
129/2013Khandala CourtCase Dismissed
81/2020Khandala CourtCase Withdrawal Application
111/2020Satara CourtAppeal Withdrawal Application

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Copy of the legal title reportFile: Advocate RERA Search.pdf22 Sep 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf6 Sep 2021
Declaration in FORM BFile: zppd_Form_B.pdf6 Sep 2021
Proforma of Allotment letterFile: Sale Deed Pdf.pdf6 Sep 2021
OtherFile: 1_001.pdf6 Sep 2021
OtherFile: 2_001.pdf6 Sep 2021
OtherFile: 3_001.pdf6 Sep 2021
OtherFile: 4_001.pdf6 Sep 2021
OtherFile: 5_001.pdf6 Sep 2021
OtherFile: 6_001.pdf6 Sep 2021
OtherFile: 7_001.pdf6 Sep 2021
OtherFile: 8_001.pdf6 Sep 2021
OtherFile: 9_001.pdf6 Sep 2021
OtherFile: 10_001.pdf6 Sep 2021
OtherFile: 11_001.pdf6 Sep 2021
OtherFile: 12_001.pdf6 Sep 2021
OtherFile: 13_001.pdf6 Sep 2021
OtherFile: 14_001.pdf6 Sep 2021
OtherFile: 15_001.pdf6 Sep 2021
OtherFile: 16_001.pdf6 Sep 2021
OtherFile: 17_001.pdf6 Sep 2021
OtherFile: 18_001.pdf6 Sep 2021
OtherFile: 19_001.pdf6 Sep 2021
OtherFile: 20_001.pdf6 Sep 2021
OtherFile: 21_001.pdf6 Sep 2021
OtherFile: 22_001.pdf6 Sep 2021
OtherFile: 23_001.pdf6 Sep 2021
OtherFile: 24_001.pdf6 Sep 2021
OtherFile: 25_001.pdf6 Sep 2021
OtherFile: 26_001.pdf6 Sep 2021
OtherFile: 27_001.pdf6 Sep 2021
OtherFile: 28_001.pdf6 Sep 2021
OtherFile: 29_001.pdf6 Sep 2021
OtherFile: 30_001.pdf6 Sep 2021
OtherFile: 31_001.pdf6 Sep 2021
OtherFile: 32_001.pdf6 Sep 2021
OtherFile: 33_001.pdf6 Sep 2021
OtherFile: 34_001.pdf6 Sep 2021
OtherFile: 35_001.pdf6 Sep 2021
OtherFile: 36_001.pdf6 Sep 2021
OtherFile: 37_001.pdf6 Sep 2021
OtherFile: 38_001.pdf6 Sep 2021
OtherFile: 39_001.pdf6 Sep 2021
OtherFile: 40_001.pdf6 Sep 2021
OtherFile: 41_001.pdf6 Sep 2021
OtherFile: 42_001.pdf6 Sep 2021
OtherFile: 43_001.pdf6 Sep 2021
OtherFile: 44_001.pdf6 Sep 2021
OtherFile: 45_001.pdf6 Sep 2021
OtherFile: 46_001.pdf6 Sep 2021
OtherFile: 47_001.pdf6 Sep 2021
OtherFile: 48_001.pdf6 Sep 2021
OtherFile: 49_001.pdf6 Sep 2021
OtherFile: 50_001.pdf6 Sep 2021
OtherFile: 51_001.pdf6 Sep 2021
OtherFile: 52_001.pdf6 Sep 2021
OtherFile: 53_001.pdf6 Sep 2021
OtherFile: 54_001.pdf6 Sep 2021
OtherFile: 55_001.pdf6 Sep 2021
OtherFile: 56_001.pdf6 Sep 2021
OtherFile: 57_001.pdf6 Sep 2021
OtherFile: 59_001.pdf6 Sep 2021
OtherFile: 60_001.pdf6 Sep 2021
OtherFile: 61_001.pdf6 Sep 2021
Layout approvalFile: Layout.pdf4 Sep 2021
Building plan approval or NA orderFile: NA_order.pdf4 Sep 2021
PAN CardFile: Pan Card.pdf4 Sep 2021
Copy of the legal title reportFile: zppd_Title_Search.pdf4 Sep 2021
Details of encumbrancesFile: Declaration of Encumbrance Certificate.pdf4 Sep 2021
Copy of Layout Approval (in case of layout)File: Layout.pdf4 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: NA_order.pdf4 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: NA_order.pdf4 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf4 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf4 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf4 Sep 2021
OtherFile: Sale Deed 152-1.pdf4 Sep 2021
OtherFile: Sale Deed 152-2.pdf4 Sep 2021

How this compares with Satara

0%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one has not
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep Golden Leaf on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khandala1,100+ in Satara

2 kmGolden LeafLapsed / revoked 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Irfan Ahmed Younus Shaikh

Irfan Ahmed Younus Shaikh has 1 registration on MahaRERA, including Golden Leaf. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if Golden Leaf is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Golden Leaf?

The registered promoter entity is Irfan Ahmed Younus Shaikh, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Golden Leaf?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Golden Leaf?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Golden Leaf?

The professionals named in the filing: Architect: Mr Chandrashekhar V Pawar; Engineer: Vidya M Khole; Chartered Accountant: Mr Prafull S Shaha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Golden Leaf?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Golden Leaf. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Golden Leaf to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.