Home / Browse projects / Satara, Maharashtra / PRADHAN MANTRI AWAS YOJANA SATARA PHASE I
PRADHAN MANTRI AWAS YOJANA SATARA PHASE I
By SATARA MUNICIPAL COUNCIL SATARA
RG-MH-22139 · RERA P52700031022 · Last updated on MahaRERA portal: 13 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 43 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PRADHAN MANTRI AWAS YOJANA SATARA PHASE I is a Residential / Group Housing project by SATARA MUNICIPAL COUNCIL SATARA in Satara, Maharashtra, registered with MahaRERA as P52700031022 on 29 Sep 2021. Possession is promised by 31 Mar 2029. The completion date has moved by 43 months from the original filing. 76 of the 1,092 units on this registration are recorded sold or booked, and 20 of 154 construction stages are filed complete.
At a glance
Project
- NamePRADHAN MANTRI AWAS YOJANA SATARA PHASE I
- TypeResidential / Group Housing
- Location
- SATARA MEDHA ROAD
- KARANJE TARF SATARA
- Karanje Tarf Satara (CT)
- Satara
- 415001
- Pincode415001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700031022
- ReraGenie IDRG-MH-22139
Builder
- NameSATARA MUNICIPAL COUNCIL SATARA
- Entity typePublic Authority
- ChairpersonABHIJEET SATISH BAPAT
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Sep 2021
- Promised completion31 Mar 2029
- Revised completionRevised to 31 Mar 2029 (originally 31 Aug 2025)
- Buildings14 building records
- Documents filed80 files
Current status
Figures as on 13 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 3 | NA | 9 | 7 | 133 | 0 | 133 |
| BUILDING NO 4 | NA | 8 | 7 | 154 | 0 | 154 |
| BUILDING NO 5 | NA | 9 | 7 | 154 | 0 | 154 |
| BUILDING NO 6 | NA | 9 | 7 | 175 | 0 | 175 |
| BUILDING NO 7 | NA | 9 | 7 | 175 | 0 | 175 |
| BUILDING NO 12-R | NA | 9 | 7 | 77 | 0 | 77 |
| BUILDING NO 13 | NA | 9 | 7 | 133 | 0 | 133 |
| BUILDING NO 14 | NA | 9 | 7 | 91 | 0 | 91 |
| BUILDING 1 | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING 2 | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING 8 | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING 9 | NA | 9 | 0 | 0 | 0 | 0 |
| BUILDING 10 | NA | 8 | 0 | 0 | 0 | 0 |
| BUILDING 11 | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building14
As on 13 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Staircases, at 90%.
BUILDING NO 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 12-R79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 8% |
BUILDING NO 1354%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 15% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1490%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
BUILDING 10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING 110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 25% |
| Water Supply | Yes | 11% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 15% |
| Storm Water Drains | Yes | 14% |
| Landscaping & Tree Planting | Yes | 26% |
| Street Lighting | Yes | 25% |
| Community Buildings | Yes | 35% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 11% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 12% |
| Electrical meter room, sub-station, receiving station | Yes | 11% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1435
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING NO 3 | 171 | 171 |
| BUILDING NO 4 | 198 | 198 |
| BUILDING NO 5 | 198 | 198 |
| BUILDING NO 6 | 231 | 231 |
| BUILDING NO 7 | 231 | 231 |
| BUILDING NO 12-R | 113 | 113 |
| BUILDING NO 13 | 171 | 171 |
| BUILDING NO 14 | 117 | 117 |
| BUILDING 1 | 1 | 1 |
| BUILDING 2 | 1 | 1 |
| BUILDING 8 | 1 | 1 |
| BUILDING 9 | 1 | 1 |
| BUILDING 11 | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 6 | NA | Rs 15.98 cr | - |
| BUILDING NO 7 | NA | Rs 15.98 cr | - |
| BUILDING NO 4 | NA | Rs 14.23 cr | - |
| BUILDING NO 5 | NA | Rs 14.23 cr | - |
| BUILDING 1 | NA | Rs 14.23 cr | - |
| BUILDING 11 | NA | Rs 14.23 cr | - |
| BUILDING 2 | NA | Rs 13.59 cr | - |
| BUILDING NO 3 | NA | Rs 12.14 cr | - |
| BUILDING NO 13 | NA | Rs 12.14 cr | Rs 2.03 cr |
| BUILDING 8 | NA | Rs 12.14 cr | - |
| BUILDING 9 | NA | Rs 12.14 cr | - |
| - | NA | Rs 8.79 cr | - |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | BHARAT PATIL |
| Engineer | DILIP SOPAN CHIDRE |
| Chartered Accountant | PURUSHOTTAM OZARDE |
| Partner | Role in project |
|---|---|
| SATARA MUNICIPAL COUNCIL SATARA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPMAY SCHEME I GOT OFFICIAL EXTENTION TILL 31-3-2029 SO WE WOULD LIKE THIS PROJECT EXTENTION
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Sep 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Sep 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2029
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2023-2024)File: FORM -2A 23-24.PDF | 13 Aug 2026 |
| Form 2A (FY 2024-2025)File: FORM -2A 24-25.PDF | 13 Aug 2026 |
| Form 2A (FY 2025-2026)File: FORM -2A 25-26.PDF | 13 Aug 2026 |
| Form 5 (FY 2025-2026)File: FORM NO 5-25-26.PDF | 13 Aug 2026 |
| Form 5 (FY 2024-2025)File: FORM NO 5-24-25.PDF | 29 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 june 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 SEPT 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 DEC 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 june 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 SEPT 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 DEC 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 june 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 SEPT 25.PDF | 10 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 DEC 25.PDF | 10 Apr 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DEC 24.PDF | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA TILL JUNE 2023.PDF | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA TILL SEPT 2023.PDF | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA TILL DEC 2023.PDF | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA TILL MARCH 2024.PDF | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA JUNE 24.pdf | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SEPT 24.pdf | 5 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC 24.PDF | 5 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG DEC 24.PDF | 5 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 for 2023-24.PDF | 5 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH 23.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SEPT 21.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC 21.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA MARCH 22.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA JUNE 22.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SEPT 22.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC 22.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA MARCH 23.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG 30 SEPT 2024.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG 30 JUNE 2024.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG March 2024.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG Dec 2023.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG Sept 2023.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG June 2023.PDF | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG MARCH 23.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG DEC 22.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG SEPT 22.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG JUNE 22.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG MARCH 22.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG SEPT 21.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31 March 2024.PDF | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DEC 2023.PDF | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH MAR 2024.PDF | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ARCH DEC 2023.PDF | 20 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.PDF | 20 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: rewise order.pdf | 17 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2 21.pdf | 17 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22.pdf | 17 Apr 2023 |
| Copy of the legal title reportFile: SEARCH F.pdf | 14 Sep 2021 |
| Details of encumbrancesFile: encuu F.pdf | 14 Sep 2021 |
| Layout approvalFile: layout.pdf | 5 Sep 2021 |
| Building plan approvalFile: building 3.pdf | 5 Sep 2021 |
| Building plan approvalFile: building 4-5.pdf | 5 Sep 2021 |
| Building plan approvalFile: building6-7 ele.pdf | 5 Sep 2021 |
| Building plan approvalFile: building6-7 plan.pdf | 5 Sep 2021 |
| Building plan approvalFile: building 12.pdf | 5 Sep 2021 |
| Building plan approvalFile: building 13.pdf | 5 Sep 2021 |
| Building plan approvalFile: building 14.pdf | 5 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building 3.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building 4-5.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building6-7 ele.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building6-7 plan.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building 12.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building 13.pdf | 5 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: building 14.pdf | 5 Sep 2021 |
| Declaration about Commencement CertificateFile: DECLARATION.pdf | 5 Sep 2021 |
| Declaration in FORM BFile: sch b 5.pdf | 5 Sep 2021 |
| Proforma of Allotment letterFile: Final Draft.pdf | 5 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER.pdf | 6 Aug 2021 |
| PAN CardFile: Municipal PAN Card.pdf | 5 Aug 2021 |
| Copy of the legal title reportFile: SERCH OFFICE.pdf | 5 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commece certificate 1.pdf | 5 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf | 5 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 5 Aug 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PRADHAN MANTRI AWAS YOJANA SATARA PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KARANJE TARF SATARA1,100+ in Satara
Filed coordinates, straight-line distance. 39 registered projects within 2 km.
LANDMARK TOWERS
KANGRALKAR INFRASTRUCTURE
Bhuvi Commercia
LAXMI NARAYAN INDUSTRIES
SAMARVEER SKYLINE
SHRI MANGALMURTI BUILDERS
Mathura
Balkrishna Pandurang Jadhav
BAJIRAO EMPIRE
SHREE SHESHACHAL DEVELOPERS
LIFESTYLE
GURU INFFRASTRUCTURE
See every Satara project, with the district possession charts
Builder: SATARA MUNICIPAL COUNCIL SATARA
SATARA MUNICIPAL COUNCIL SATARA has 1 registration on MahaRERA, including PRADHAN MANTRI AWAS YOJANA SATARA PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if PRADHAN MANTRI AWAS YOJANA SATARA PHASE I is delayed beyond 31 Mar 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PRADHAN MANTRI AWAS YOJANA SATARA PHASE I?
The registered promoter entity is SATARA MUNICIPAL COUNCIL SATARA, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PRADHAN MANTRI AWAS YOJANA SATARA PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PRADHAN MANTRI AWAS YOJANA SATARA PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PRADHAN MANTRI AWAS YOJANA SATARA PHASE I?
The professionals named in the filing: Architect: BHARAT PATIL; Engineer: DILIP SOPAN CHIDRE; Chartered Accountant: PURUSHOTTAM OZARDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PRADHAN MANTRI AWAS YOJANA SATARA PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.