Registration lapsed No litigation declared Residential / Group Housing project

Gold Valley Central Park Phase 1 Part 2

By POONA REALTORS PVT LTD

RG-MH-28907 · RERA P52800027231 · Last updated on MahaRERA portal: 3 Jun 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
70 of 99Construction stages doneacross 9 buildings; furthest along: Sanitary Fittings within the flats /..., 80%
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

Gold Valley Central Park Phase 1 Part 2 is a Residential / Group Housing project by POONA REALTORS PVT LTD in Ratnagiri, Maharashtra, registered with MahaRERA as P52800027231 on 25 Nov 2020. Possession was promised by 30 Jun 2023 and is now 40 months past that date.

At a glance

Project

  • NameGold Valley Central Park Phase 1 Part 2
  • TypeResidential / Group Housing
  • Location
    • Shri Krushna nagar Road
    • NR DEVI TEMPLE
    • Jalgaon
    • Dapoli
    • Ratnagiri
    • 415712
  • Pincode415712
  • RERA no.P52800027231
  • ReraGenie IDRG-MH-28907

Builder

  • NamePOONA REALTORS PVT LTD
  • Entity typeCompany
  • Managing DirectorPRAKASH VASANT KANE
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

40 months past promisethis monthRegisteredNov 2020PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Nov 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings9 building records
  • Documents filed55 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
N 1NA10000
N 2NA10000
O 1NA10000
O 2NA10000
O 3NA10000
O 4NA10000
M 1NA10000
M 2NA10000
F 1NA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 3 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

70 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

N 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
N 278%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O 40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
M 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
M 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Open Space8
BuildingOpen SpaceTotal
N 111
N 211
O 111
O 211
O 311
O 411
M 111
M 211

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area652 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI652.03
Proposed, not sanctioned652 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDAPOLI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Raje
EngineerDhananjay Sakharekar
Chartered AccountantNeeta Sulakhe
PartnerRole in project
POONA REALTORS PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Jun 2023

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE Gold Valley Dapoli.pdf3 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sanctioned Layout F,M,N Buildings Gold Valley Dapoli.pdf3 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sanctioned Layout F,M,N Buildings Gold Valley Dapoli.pdf3 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf1 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf1 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD-PHASE II- F1.pdf20 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD-PHASE II- F2.pdf20 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase I Part 2.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_FY 2021-22_Part 2.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_FY 2021-22_Part 2.pdf20 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD-P2- F1.pdf2 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD-P2- F2.pdf2 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GVD-P2- COMPLETION.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD PHASE II-F1 JUNE 2022.pdf26 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD PHASE III F2 JUNE 2022.pdf26 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD- PH1 - Part 2 - June 2022.pdf24 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD P2 FORM 1 MARCH 22.pdf21 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD P2 FORM 2 MARCH 22.pdf21 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD P2 FORM 3 MARCH 22.pdf21 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD P2-F1-DEC21.pdf29 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD-P2-F2-DEC 21.pdf29 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD P2-F3-DEC21.pdf29 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD P2-Form 1 SEPT 21.pdf13 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD P2-Form 2 SEPT 21.pdf13 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD P2- Form 3 SEPT 21.pdf13 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Part 2.pdf2 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: gvd phase 1 part 2 form 1.pdf27 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: gvd phase 1 part 2 form 2.pdf27 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: gvd P1 P2 Form 3.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2B part 2.pdf20 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2B part 2.pdf14 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A part 2.pdf12 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD PART 2 FORM 3.pdf12 Jul 2021
Declaration about Commencement CertificateFile: declaration part 2.pdf8 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD PHASE I PART 2 FORM 2.pdf8 Jul 2021
Disclosure of sold/ booked inventoryFile: disclosure part 2.pdf8 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD PART 2 FORM 3.pdf8 Jul 2021
Declaration about Commencement CertificateFile: Commencement and NA Certificate.pdf6 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GVD PHASE I PART 2 FORM 1.pdf6 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GVD PHASE I PART 2 FORM 2.pdf6 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GVD PART 2 FORM 3.pdf6 Jul 2021
Details of encumbrancesFile: Affidevit and Declaration.pdf20 Nov 2020
Declaration in FORM BFile: Affidevit and Declaration.pdf20 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - PRPL GVD.pdf20 Nov 2020
Proforma of Allotment letterFile: ATS GVD RERA.pdf20 Nov 2020
Layout approvalFile: Sanctioned Layout.pdf19 Nov 2020
Building plan approvalFile: Proposed Bldg M, N,O.pdf19 Nov 2020
Building plan approvalFile: Proposed Bldg F1.pdf19 Nov 2020
PAN CardFile: PAN PRPL RERA.pdf19 Nov 2020
Copy of the legal title reportFile: TITLE REPORT GVD RERA.pdf19 Nov 2020
Copy of Layout Approval (in case of layout)File: Sanctioned Layout.pdf19 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Proposed Bldg M, N,O.pdf19 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: Proposed Bldg F1.pdf19 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement and NA Certificate.pdf19 Nov 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GOLD VALLEY CENTRAL PARK DAPOLI PH1 PART 1S No 174 Jalgaon Tal Dapoli Dist Ratnagiri108CompletedJul 2017Jul 2017

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep Gold Valley Central Park Phase 1 Part 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NR DEVI TEMPLE1,100+ in Ratnagiri

Builder: POONA REALTORS PVT LTD

POONA REALTORS PVT LTD has 3 registrations on MahaRERA, including GOLD VALLEY CENTRAL PARK PHASE 1 PART1 and Gold Valley Central Park Phase 1 Part 2. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What does it mean that Gold Valley Central Park Phase 1 Part 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Gold Valley Central Park Phase 1 Part 2 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gold Valley Central Park Phase 1 Part 2?

The registered promoter entity is POONA REALTORS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gold Valley Central Park Phase 1 Part 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Gold Valley Central Park Phase 1 Part 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gold Valley Central Park Phase 1 Part 2?

The professionals named in the filing: Architect: Rajesh Raje; Engineer: Dhananjay Sakharekar; Chartered Accountant: Neeta Sulakhe. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gold Valley Central Park Phase 1 Part 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gold Valley Central Park Phase 1 Part 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gold Valley Central Park Phase 1 Part 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.