Home / Browse projects / Thane, Maharashtra / Gold Crest
Gold Crest
RG-MH-30678 · RERA P51700031489 · Last updated on MahaRERA portal: 20 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gold Crest is a Others project by Jay Ganesh Developers in Thane, Maharashtra, registered with MahaRERA as P51700031489 on 25 Oct 2021. Possession is promised by 31 May 2027. The completion date has moved by 24 months from the original filing. 102 of the 196 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.
At a glance
Project
- NameGold Crest
- TypeOthers
- Location
- Ayre Road
- Ayre Goan
- DOMBIVLI
- Kalyan
- Thane
- 421201
- Pincode421201
- RERA no.P51700031489
- ReraGenie IDRG-MH-30678
Builder
- NameJay Ganesh Developers
- Entity typePartnership
- GSTIN27AALFJ2953N2ZQ
- PartnersManisha S Patil, Ravindra Dasharth Patil, Harishchandra Waman Kene, Bharti Dipak More
- Other registrations5 more →
- Completed1 of 6
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Oct 2021
- Promised completion31 May 2027
- Revised completionRevised to 31 May 2027 (originally 31 May 2025)
- Buildings2 building records
- Documents filed60 files
Current status
Figures as on 20 Apr 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 26 | 24 | 132 | 8 | 140 |
| Wing B | NA | 11 | 11 | 56 | 0 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.
Wing A76%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Wing B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 60% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 1 | 1 |
| Wing B | 1 | 1 |
Land and ownership10
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Ravindra Shantaram Patail | DOMBIVLI | Thane |
| Subhash Shantaram Patil | DOMBIVLI | Thane |
| Pandurang Shantaram Patil | DOMBIVLI | Thane |
| Vishwanath Shantaram Patil | DOMBIVLI | Thane |
| Sandeep Shantaram Patil | DOMBIVLI | Thane |
| Sudhakar Shantaram Mhatre | DOMBIVLI | Thane |
| Kalpana Sudhakar Mhatre | DOMBIVLI | Thane |
| Prathamesh Sudhakar Mhatre | DOMBIVLI | Thane |
| Anant Undrya Bhoir | DOMBIVLI | Thane |
| Adinath Undrya Bhoir | DOMBIVLI | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ankru Shetye |
| Engineer | Sandeep Khnadode |
| Chartered Accountant | Pooja Jain |
| Partner | Role in project |
|---|---|
| Jay Ganesh Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExtension requested under section 7 (3) with consent due to increase in scope of work of increasing floors (Correction is also made with consent currently at Desk 2)
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Aug 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 May 2027
Documents filed60
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Gold Crest Mar 25.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Gold Crest Mar 25.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Gold Crest Mar 25.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: jay ganesh architect certificate.pdf | 6 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: jay ganesh CA certificate Q-3.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: jay ganesh engineers certificate.pdf | 6 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Gold Crest 24.pdf | 6 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24 Gold crest.pdf | 6 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate (1)_rotated.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate (1).pdf | 13 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 with sign.pdf | 13 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gold Crest Architect Certificate (1).pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Gold Crest Engineer Certificate.pdf | 5 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Gold Crest Mar 23.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gold Crest CA Cartificate.pdf | 5 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 gold Crest 22-23.pdf | 5 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Gold Crest.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Gold Crest.pdf | 11 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Gold Crest (1) (1).pdf | 11 Oct 2023 |
| Layout approvalFile: PLAN 24 REVISED 01.pdf | 28 Aug 2023 |
| Layout approvalFile: PLAN 24 REVISED 02.pdf | 28 Aug 2023 |
| Layout approvalFile: PLAN 24 REVISED 03.pdf | 28 Aug 2023 |
| Building plan approvalFile: PLAN 24 REVISED 01.pdf | 28 Aug 2023 |
| Building plan approvalFile: PLAN 24 REVISED 02.pdf | 28 Aug 2023 |
| Building plan approvalFile: PLAN 24 REVISED 03.pdf | 28 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN 24 REVISED 01.pdf | 28 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN 24 REVISED 02.pdf | 28 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: PLAN 24 REVISED 03.pdf | 28 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN 24 REVISED 01.pdf | 28 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN 24 REVISED 02.pdf | 28 Aug 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN 24 REVISED 03.pdf | 28 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: REVIED CC 24 FLOOR.pdf | 28 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 JG June 23_rotated.pdf | 28 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 JG June 23_rotated.pdf | 28 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Gold Crest Mar 22_rotated.pdf | 28 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Gold Crest_rotated.pdf | 28 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JG June 23_rotated.pdf | 28 Aug 2023 |
| Proforma of Agreement for saleFile: Agreement For Sale.pdf | 7 Apr 2023 |
| Layout approvalFile: Jay Ganesh New Plan.pdf | 12 Jan 2023 |
| Copy of Layout Approval (in case of layout)File: Jay Ganesh New Plan.pdf | 12 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf | 12 Jan 2023 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 21 Oct 2021 |
| Copy of the legal title reportFile: TITLE CERTIFICATE JAY GANESH.pdf | 12 Oct 2021 |
| Copy of the legal title reportFile: Jay Ganesh Title Certificate 1.pdf | 23 Sep 2021 |
| Copy of the legal title reportFile: Jay Ganesh Title Certificate.pdf | 23 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAY_GANESH__FORM_3.pdf | 23 Sep 2021 |
| Proforma of Allotment letterFile: Agreement For Sale.pdf | 23 Sep 2021 |
| Layout approvalFile: PLAN 1.pdf | 22 Sep 2021 |
| Layout approvalFile: PLAN 2.pdf | 22 Sep 2021 |
| Layout approvalFile: PLAN 3.pdf | 22 Sep 2021 |
| Building plan approvalFile: JAY GANESH NA.pdf | 22 Sep 2021 |
| Details of encumbrancesFile: Details of encumbrances.pdf | 22 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: PLAN 1.pdf | 22 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: PLAN 2.pdf | 22 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: PLAN 3.pdf | 22 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: JAY GANESH NA.pdf | 22 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: JAY GANESH CC.pdf | 22 Sep 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf | 22 Sep 2021 |
| Declaration in FORM BFile: Form B Promoter.pdf | 22 Sep 2021 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 22 Sep 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations, which the RERA portal never shows together
- All 60 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Gold Crest on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ayre Goan7,600+ in Thane
MY CITY PHASE II CLUSTER 5 PART II
HORIZON PROJECTS PVT LTD
MY CITY PHASE II CLUSTER 5 PART III
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 3 Bldg No 27-28
Runwal Residency Private Limited
Runwal Gardens Phase 4 Bldg No. 35-36
Runwal Residency Private Limited
VASTU LUXURIA
LAUKIK DEVELOPMENT CORPORATION
KAPLESHWARA RESIDENCY
KAPLESHWARA HOMES LLP
See every Thane project, with the district possession charts
Builder: Jay Ganesh Developers
JAY GANESH DEVELOPERS has 6 registrations on MahaRERA, including OMSHREE and JAY GANESH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Gold Crest is delayed beyond 31 May 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gold Crest?
The registered promoter entity is Jay Ganesh Developers, a partnership as per the filing. Its GSTIN 27AALFJ2953N2ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gold Crest?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Gold Crest?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gold Crest?
The professionals named in the filing: Architect: Ankru Shetye; Engineer: Sandeep Khnadode; Chartered Accountant: Pooja Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gold Crest?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.