Home / Browse projects / Raigarh, Maharashtra / GOKULDHAM
GOKULDHAM
RG-MH-54738 · RERA P52000009607 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 54 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOKULDHAM is a Others project by SHREEJI DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000009607 on 22 Aug 2017. The registration is recorded completed; possession was promised by 25 Dec 2025. The completion date has moved by 54 months from the original filing.
At a glance
Project
- NameGOKULDHAM
- TypeOthers
- Location
- SHELU
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000009607
- ReraGenie IDRG-MH-54738
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Aug 2017
- Promised completion25 Dec 2025
- Revised completionRevised to 25 Dec 2025 (originally 30 Jun 2021)
- Buildings8 building records
- Documents filed105 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TULIP WING A | NA | 5 | 0 | 0 | 0 | 0 |
| TULIP WING B | NA | 5 | 0 | 0 | 0 | 0 |
| ROSE | NA | 15 | 0 | 0 | 0 | 0 |
| LOTUS WING A | NA | 18 | 0 | 0 | 0 | 0 |
| LOTUS WING B | NA | 18 | 0 | 0 | 0 | 0 |
| LOTUS WING C | NA | 19 | 0 | 0 | 0 | 0 |
| JASMIN WING A | NA | 4 | 0 | 0 | 0 | 0 |
| JASMIN WING B | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
64 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Staircases, at 50%.
TULIP WING A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
TULIP WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ROSE82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LOTUS WING A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LOTUS WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
LOTUS WING C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
JASMIN WING A53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
JASMIN WING B53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 90% |
Parking filed77
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| TULIP WING A | 0 | 7 | 7 |
| TULIP WING B | 1 | 7 | 8 |
| ROSE | 11 | 0 | 11 |
| LOTUS WING A | 14 | 0 | 14 |
| LOTUS WING C | 15 | 0 | 15 |
| JASMIN WING A | 0 | 11 | 11 |
| JASMIN WING B | 0 | 11 | 11 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TRENDS ARCHITECTURE INTERIOR CONSULTANTS |
| Engineer | S R CONSULTANTS |
| Chartered Accountant | M G BARVADIYA AND ASSOCIATES |
| Chartered Accountant | D G PATEL & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHREEJI DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project was delayed on account of various unforeseeable reasons in which one of the major reason was Covid -19. In addition shortage of manpower due to travel bans & quarantine and delay in material delivery in the construction site resulted in delay in completion of the work at the site
Reason as filed by the promoterAs per Request Letter Attached
Reason as filed by the promoterThe Project could be completed on the due date i.e., 31st December 2023, but due to unavoidable circumstances i.e. Occupation Certificate Copy not yet received and it will take time to obtain received Occupation Certificate. Thus, we hereby request you to kindly grant us the extension of 1 year i.e., till 31st December 2024.
Reason as filed by the promoterDue to unavoidable circumstances i.e. Occupation Certificate Copy not yet received and it will take time to obtain Occupation Certificate
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Arct certificate 30-06-2025.pdf | 24 Jun 2026 |
| Form 2File: Form 2 30-6-25.pdf | 24 Jun 2026 |
| Form 3File: FORM 3-Shreeji Developers - Q1.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Booked inventory 30-06-2025.pdf | 24 Jun 2026 |
| Form 1File: Form 1 Arct certificate 30-09-2025.pdf | 24 Jun 2026 |
| Form 2File: Form 2 30-9-25.pdf | 24 Jun 2026 |
| Form 3File: FORM 3-Shreeji Developers - Q2.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Booked inventory 30-09-2025.pdf | 24 Jun 2026 |
| Form 1File: Form 1 Arct certificate 25-12-2025.pdf | 24 Jun 2026 |
| Form 2File: Form 2 25-12-25.pdf | 24 Jun 2026 |
| Form 3File: FORM 3-Shreeji Developers - Q3.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Booked inventory 25-12-2025.pdf | 24 Jun 2026 |
| Occupational CertificateFile: OC Copy.pdf | 24 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5-FY 24-25-Shreeji Developers.pdf | 16 Jan 2026 |
| Certificates of CA (Form 3)File: Q4 Form3.pdf | 3 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture certificate 2025 - converted.pdf | 3 Mar 2025 |
| Certificates of CA (Form 3)File: FORM 3-Shreeji Developers Q3.pdf | 3 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineeers certificate 03MARCH2025.pdf | 3 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A quality assirance certificate (1).pdf | 24 Jan 2025 |
| Declaration in FORM BFile: FORM B.pdf | 17 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance concerned to legal.pdf | 16 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Booked inventory - converted.pdf | 16 Dec 2024 |
| Declaration about Commencement CertificateFile: Declaration about commencement certifica.pdf | 16 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance concerned to legal.pdf | 16 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A lalji ramji bangari.pdf | 16 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 architect certificate march 2024 - converted.pdf | 12 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate june 2024 - converted.pdf | 12 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture certificate December 2024 - converted.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer certificate March 2024.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate september 2024.pdf | 12 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate june 2024.pdf | 12 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3-Shreeji Developers march 24.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3-Shreeji Developers Q1.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: FORM 3-Shreeji Developers Q2.pdf | 30 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-FY 23-24-Shreeji Developers.pdf | 26 Nov 2024 |
| Declaration in FORM BFile: Form B affidavit.pdf | 10 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Booking Inventory.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Booking Inventory.pdf | 23 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - lalji bangari.pdf | 23 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest - bhimji patel.pdf | 23 Dec 2023 |
| Proforma of Allotment letterFile: Letter of Allotment.pdf | 23 Dec 2023 |
| Proforma of Agreement for saleFile: Sale of Agreement.pdf | 23 Dec 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf | 23 Dec 2023 |
| Deviation Report with respect to Allotment letterFile: No Deviation Report.pdf | 23 Dec 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance concerned to legal.pdf | 21 Dec 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance concerned to legal.pdf | 21 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf | 21 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A engineer certificate.pdf | 21 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-FY 22-23-Shreeji Developers.pdf | 28 Nov 2023 |
| CERSAI detailsFile: CERSAI_Search_Report.pdf | 21 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: 5-Details of encumbrances concerned to Finance and Legal.pdf | 20 Jan 2023 |
| Details of encumbrances concerned to LegalFile: 5-Details of encumbrances concerned to Finance and Legal.pdf | 20 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6-ok-Architect Certificate.pdf | 20 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7-ok-Engineer Certificate.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 8.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: 1.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: 12-CA Certificate-Form 3-Final.pdf | 20 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1-ok-Disclosure in Interested Concern.pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-FY 21-22-Shreeji Developers.pdf | 20 Jan 2023 |
| Proforma of Agreement for saleFile: 9-Final RERA Agreement.pdf | 20 Jan 2023 |
| Proforma of Allotment letterFile: 10-ok-Allotment Letter.pdf | 20 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 4-ok-Separate Bank Account.pdf | 20 Jan 2023 |
| Deviation Report with respect to Allotment letterFile: 10-ok-No Deviation Report.pdf | 20 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: 10-ok-No Deviation Report.pdf | 20 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: SHREEJI 18.pdf | 1 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SHREEJI 19.pdf | 1 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SHREEJI 20.pdf | 1 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SHREEJI 21.pdf | 1 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 30 Jun 2021 |
| Declaration about Commencement CertificateFile: Declarataion about CC.pdf | 30 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate.pdf | 30 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate.pdf | 30 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Details.pdf | 30 Jun 2021 |
| Layout approvalFile: FIRST AND THIRD.pdf | 24 Jan 2020 |
| Layout approvalFile: GROUND FLOOR.pdf | 24 Jan 2020 |
| Layout approvalFile: SECOND AND FOURTH.pdf | 24 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: FIRST AND THIRD.pdf | 24 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: GROUND FLOOR.pdf | 24 Jan 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 26 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 105 filed documents as one ZIP, foldered, with a manifest
Keep GOKULDHAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHELU5,900+ in Raigarh
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: SHREEJI DEVELOPERS
SHREEJI DEVELOPERS has 27 registrations on MahaRERA, including SAHAJANAND INTEGRITY and SHREEJI DREAMS. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if GOKULDHAM is delayed beyond 25 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOKULDHAM?
The registered promoter entity is SHREEJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOKULDHAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GOKULDHAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOKULDHAM?
The professionals named in the filing: Architect: TRENDS ARCHITECTURE INTERIOR CONSULTANTS; Engineer: S R CONSULTANTS; Chartered Accountant: M G BARVADIYA AND ASSOCIATES; Chartered Accountant: D G PATEL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOKULDHAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.