Red flags

  • 9 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
50 of 55Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 0%
9Complaints at MahaRERAon this registration
Jump to the 107 documents Report an error

Godrej Rejuve is a Others project by OXFORD REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100018720 on 28 Nov 2018. The registration is recorded completed; possession was promised by 30 Mar 2024. 9 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Rejuve
  • TypeOthers
  • Location
    • Mundhwa Road
    • Keshavnagar
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018720
  • ReraGenie IDRG-MH-56771

Builder

  • NameOXFORD REALTY LLP
  • Entity typeOthers
  • Named personsOXFORD SHELTERS PVT LTD, GODREJ PROPERTIES LIMITED, ASHOK KOTHARI, PARAG SHAH, ASHOK MOHANANI, VIVEK MOHANANI, ANIRUDHA SEOLEKAR, Ekta Housing Private Limited, EKTA WORLD PRIVATE LIMITED
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2018PromisedMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Nov 2018
  • Promised completion30 Mar 2024
  • Revised completionNone
  • Buildings5 building records
  • Documents filed107 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
T7 - EspritNA230000
T8 - VerveNA230000
T9 - LifeNA220000
T10 - ZestNA220000
T11 - ZingNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 29 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 0%.

T7 - Esprit91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T8 - Verve91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T9 - Life91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T10 - Zest91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T11 - Zing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 29 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Parking Open and coveredYes0%

Parking filed760

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots760
Closed/Covered604
Open Space156
BuildingClosed/CoveredOpen SpaceTotal
T7 - Esprit13886224
T8 - Verve80080
T9 - Life13220152
T10 - Zest12230152
T11 - Zing13220152

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area38,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
OXFORD REALTY LLPKurlaMumbai Suburban
Hritik Technologies & Realty Pvt LtdAndheriMumbai Suburban
Oxford Shelters Private LimitedPune (M Corp.)Pune
Godrej Properties Limited (As Development Manager)KurlaMumbai Suburban

Approvals and building plan

Permissible FSI60284.7
Proposed, not sanctioned60,285 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Jehangir Building, M G Road, Fort, Mumbai 400 001, Maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapadia Associates Design LLP
EngineerJW CONSULTANTS LLP
PartnerRole in project
OXFORD REALTY LLP-

Litigation declared11

CaseCourtStatus
SCS 663/2006Civil Court Senior DivisionPending
SCS 622/2012Civil Court Junior DivisionPending
SCS 662/2006Civil Court Senior DivisionPending
SCS 49/2015Civil Court Senior DivisionCase Disposed
SCS 396/2009Civil Court Senior DivisionPending
SCS 2677/2010Civil Court Senior DivisionPending
SCS 1378/2018Civil Court Senior DivisionPending
SCS 125/2019Civil Court Senior DivisionPending
SCS 1367/2018Civil Court Senior DivisionPending
SCS 472/2015Joint CJSD AND Additional CJM PunePending
RCS 121/2019Joint CJSD AND Additional CJM PunePending

Complaints filed with MahaRERA9

Case no.ComplainantRespondentFiled
CC005000000117057Aarushi ParasharGodrej Properties14/05/2022
CC005000000259253MAHESH KHARATMOLOxford Realty LLP03/08/2023
CC12502005Shyam Bhujang MohiteOXFORD REALTY LLP19/06/2025
CC12602482Naveen MauryaOXFORD REALTY LLP28/04/2026
CC12504063AMAR SINGH KAITWAROXFORD REALTY LLP18/11/2025
CC12601492OXFORD REALTY LLPANTHONY POULOSE18/03/2026
CC12601497OXFORD REALTY LLPKAILASH ARVIND PALANDURKAR18/03/2026
CC12601498OXFORD REALTY LLPIQBALJAVEED18/03/2026
CC12601499OXFORD REALTY LLPSHIVANI SHIVRAJ KASAW18/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Nov 2024

Documents filed107

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf29 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rejuve OC.pdf29 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: Rejuve Inventory (Sold-Unsold).pdf28 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf16 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf16 Jan 2024
Certificates of CA (Form 3)File: CA certificate.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rejuve Architect Certificate_Jul'23 to Sep'23.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rejuve Engineers Certificate_Jul'23 to Sep'23.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Rejuve CC Data_Jul'23 to Sep'23.pdf20 Oct 2023
Certificates of CA (Form 3)File: Rejuve CA Certificate_Jul'23 to Sep'23.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Oxford - Godrej Rejuve signed.pdf21 Sep 2023
Certificates of CA (Form 3)File: Rejuve_CA certificate_compressed.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rejuve - Architect's Certificate.pdf10 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate GODREJ REJUVE for Phase-II - BRICKLANE - (June- 2023).pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: Rejuve - Inventory Details_compressed.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Rejuve - Quality Assurance Certificate.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Rejuve - Inventory Details_11zon.pdf20 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rejuve - Architect Certificate.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rejuve - Engineer Certificate.pdf19 Apr 2023
Certificates of CA (Form 3)File: Rejuve - CA Certificate_11zon.pdf19 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rejuve _ OC.pdf19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20190401_GPL Rejuve Ar Certificate 1.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20230103_GPL Rejuve Ar certificate_31st Dec 21.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20230103_GPL Rejuve Ar certificate_31st March 22.pdf15 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ REJUVE ENGINEERS CERTIFICATE MARCH 2019.pdf15 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer sept 2020.pdf15 Feb 2023
Certificates of CA (Form 3)File: MDD_Mar'19 RERA Certificate Godrej Rejuve .pdf15 Feb 2023
Certificates of CA (Form 3)File: CA Certificate_Mar'20_Rejuve.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Godrej Rejuve for Phase - II - KAPL - A.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Godrej Rejuve.pdf18 Jan 2023
Disclosure of sold/ booked inventoryFile: Rejuve Inventory (Sold-Unsold)-F.pdf18 Jan 2023
Certificates of CA (Form 3)File: MDD_RERA Certificate Rejuve (ORLLP)_Signed-E.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20221010_GPL Rejuve Ar certificate.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Godrej Rejuve.pdf20 Oct 2022
Disclosure of sold/ booked inventoryFile: Rejuve Inventory (Sold-Unsold)_compressed-G.pdf20 Oct 2022
Certificates of CA (Form 3)File: MDD_RERA Certificate Rejuve (ORLLP)-Signed.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Oxford Rejueve Form 5.pdf30 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GPL Rejuve Ar certificate.pdf15 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Godrej Rejuve.pdf15 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf15 Jul 2022
Certificates of CA (Form 3)File: CA Certificate MDD RERA certificate Rejuve.pdf15 Jul 2022
CERSAI detailsFile: CERSAI Search Report.pdf11 Jul 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate-Rejuve.pdf7 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf30 Jun 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf29 Jun 2022
Layout approvalFile: Copy of layout plan.pdf6 Jun 2022
Building plan approvalFile: Building plan approval.pdf6 Jun 2022
Copy of Layout Approval (in case of layout)File: Copy of layout plan.pdf6 Jun 2022
Building Plan Approval (IOD)File: Building plan approval.pdf6 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf6 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (Form 1).pdf14 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (Form 2).pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate (Form 2 A).pdf14 Apr 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf14 Apr 2022
Certificates of CA (Form 3)File: CA Certificate (Form 3).pdf13 Apr 2022
Certificates of CA (Form 3)File: MDD_ Rejuve (ORLLP)_Signed - CA CertificateC.pdf15 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Rejuve 311221B.pdf11 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Rejuve 311221D compressed2.pdf11 Feb 2022
Disclosure of sold/ booked inventoryFile: Inventory Disclosure Rejuve 311221L.pdf11 Feb 2022
Certificates of CA (Form 3)File: Rejuve Sep 21_ Draft_Signed.pdf15 Nov 2021
Disclosure of sold/ booked inventoryFile: Rejuve Sep 21.pdf26 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20211011 GPL Rejuve Ar Certificate.pdf11 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 081021 Engineer's Certificate GODREJ REJUVE Sept 2021.pdf8 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 211007 FORM 2A Quality Assurance cert Godrej Rejuve Sept 21.pdf8 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Godrej Rejuve_RERA certificate FY 20-21-1-7.pdf30 Sep 2021
Certificates of CA (Form 3)File: Rejuve June 21 Final.pdf21 Jul 2021
Disclosure of sold/ booked inventoryFile: Rejuve compressed.pdf15 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20210707 GPL Rejuve Ar Certificate.pdf11 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate GODREJ REJUVE for Phase-II (June - 2021).pdf11 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 210630 RERA Rejuve QC certificate compressed.pdf11 Jul 2021
Disclosure of sold/ booked inventoryFile: Rejuve Towers 7 to 11 FINAL 250221 compressed.pdf26 May 2021
Certificates of CA (Form 3)File: Rejuve mar 21 draft.pdf25 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20210109 GPL Rejuve Ar Certificate.pdf12 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20210408 GPL Rejuve Ar Certificate.pdf12 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Godrej Rejuve Dec 2020compressed.pdf12 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate GODREJ REJUVE March 2021 compressed.pdf12 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Rejuve QC.pdf12 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Godrej Rejuve FORM 2A-Quality Assurance cert for March 21.pdf12 May 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Rejuve on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Keshavnagar13,700+ in Pune

2 kmGodrej RejuveCompleted 57Lapsed / revoked 15Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: OXFORD REALTY LLP

OXFORD REALTY LLP has 3 registrations on MahaRERA, including Godrej Infinity and Godrej Rejuve. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Rejuve is delayed beyond 30 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Rejuve?

The registered promoter entity is OXFORD REALTY LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Rejuve?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Rejuve?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Rejuve?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Rejuve?

The professionals named in the filing: Architect: Kapadia Associates Design LLP; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Rejuve?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Rejuve. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Rejuve to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.