Registration lapsed Litigation declared Residential / Group Housing project

Godrej Parkridge

By Manjari Housing Projects LLP

RG-MH-17241 · RERA P52100028310 · Last updated on MahaRERA portal: 17 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Litigation declared, 3 cases
  • 15 complaints at MahaRERA
  • Rs 230.00 crore secured on the land, in favour of ICICI Bank Ltd

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
20 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 95%
4 of 674Units unsoldnot recorded sold or booked
15Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

Godrej Parkridge is a Residential / Group Housing project by Manjari Housing Projects LLP in Pune, Maharashtra, registered with MahaRERA as P52100028310 on 18 Feb 2021. Possession was promised by 30 Sep 2025 and is now 13 months past that date. 670 of the 674 units on this registration are recorded sold or booked, and 20 of 33 construction stages are filed complete. 15 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Parkridge
  • TypeResidential / Group Housing
  • Location
    • Off Awhalwadi Road
    • Manjari Kh
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028310
  • ReraGenie IDRG-MH-17241

Builder

  • NameManjari Housing Projects LLP
  • Entity typeOthers
  • GSTIN27AARFG0014F1ZP
  • Named personsGodrej Properties Limited, Ashdan Developers Private Limited
  • Other registrations8 more →
  • Completed1 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

13 months past promisethis monthRegisteredFeb 2021PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Feb 2021
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed131 files

Current status

99%670 of 674 units booked
94.5%Work done, per cost certificate

Figures as on 17 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA28272160216
Tower 2NA18172020202
Tower 3NA34322560256

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 17 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

Tower 173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 368%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises82%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%

Progress on shared amenities15

As on 17 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed541

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots541
Closed/Covered541
BuildingClosed/CoveredTotal
Tower 1207207
Tower 28989
Tower 3245245

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area15,830 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank Ltd
Secured amountRs 230.00 crore
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI40341.12
Proposed, not sanctioned40,341 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Address Commercia, Wakad,Pune-411057
Estimated costRs 209.05 cr
Cost incurredRs 197.56 cr
Work done94.5%
BuildingWingEstimatedIncurred
Tower 3NARs 88.79 crRs 85.17 cr
Tower 1NARs 77.43 crRs 72.60 cr
Tower 2NARs 32.46 crRs 32.46 cr
-NARs 10.36 crRs 7.31 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK:a architecture
ArchitectANA Consortium Pvt Ltd
EngineerCBRE South Asia Pvt. Ltd.
EngineerMangesh Avinash Lawand
Chartered AccountantMD Deshpande & Co
Chartered AccountantB S R & Co. LLP
PartnerRole in project
Manjari Housing Projects LLP-

Litigation declared3

CaseCourtStatus
494/2008Civil Judge Senior DivisionOngoing
479/2008Bombay High CourtOngoing
1170/2014Civil Judge Junior DivisionOngoing

Complaints filed with MahaRERA15

Case no.ComplainantRespondentFiled
CC005000000096102Pawan SardaGodrej Properties Limited05/10/2021
CC005000000371033JEETEN RAJANIGodrej Properties Limited01/06/2024
CC12504108Manish Nandkishor AvinasheManjari Housing Projects LLP22/11/2025
CC12503351Sawant Kumar TiwariManjari Housing Projects LLP19/09/2025
CC12503741Prabal JainManjari Housing Projects LLP24/10/2025
CC12504336ASHUTOSH SHASHIKANT MAKHAREManjari Housing Projects LLP07/12/2025
CC12602576Saurabh Rajesh MantalaManjari Housing Projects LLP03/05/2026
CC12600467SUBHASH CHANDRAN NAMBIAR NINKILERI THAZHILLATHManjari Housing Projects LLP26/01/2026
CC12601724Saurabh KunnawarManjari Housing Projects LLP25/03/2026
CC12603713SNEHAL SUBHASH MULEManjari Housing Projects LLP16/06/2026
CC12604265Pawan SardaManjari Housing Projects LLP07/07/2026
CC12604267JALAJ KARANDIKARManjari Housing Projects LLP07/07/2026
CC12604266Jitin HuriaManjari Housing Projects LLP07/07/2026
CC12604127Anup Prashant GandhiManjari Housing Projects LLP02/07/2026
CC12604275Pramod JamkarManjari Housing Projects LLP08/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: R5A - Parkridge.pdf17 Oct 2025
Withdrawal Update Form 2File: R5A Godrej Parkridge.pdf17 Oct 2025
Withdrawal Update Form 3File: MDD_2 Park Ridge September-2025_Signed.pdf17 Oct 2025
Withdrawal Update Form 1File: Parkridge.pdf7 Oct 2025
Withdrawal Update Form 2File: R5A Godrej Parkridge.pdf7 Oct 2025
Withdrawal Update Form 3File: Park Ridge.pdf7 Oct 2025
Form 5 (FY 2024-2025)File: Park ridge 24-25.pdf2 Sep 2025
Form 1File: Parkridge.pdf21 Jul 2025
Form 2File: R5A Godrej Parkridge.pdf21 Jul 2025
Form 3File: Park Ridge.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: Parkridge.pdf21 Jul 2025
OthersFile: R5A Parkridge - Quality assurance certificate - Q1 - June 2025.pdf21 Jul 2025
Form 1File: Parkridge_Form 1.pdf24 Jun 2025
Form 2File: R5A Godrej Parkridge.pdf24 Jun 2025
Form 3File: Form 3-Park Ridge.pdf24 Jun 2025
Disclosure of Sold and Booked InventoryFile: Parkridge.pdf24 Jun 2025
Self-declaration of Quarterly ProgressFile: R5A- Quality Assurance Certificate - Q4 - March 2025.pdf24 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: R5A- Quality Assurance Certificate - Q4 - March 2025.pdf29 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Park Ridge.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Parkridge_Form 1.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R5A Godrej Parkridge.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Parkridge.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Godrej Parkridge_Form 1.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park ridge_Form 3.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R5A Godrej Parkridge_Form 2.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Parkridge_Disclosure sold unsold.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Parkridge_Architect Certificate.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: parkridge_CA Certificate.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R5A Godrej Parkridge_Engineer Certificate.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Parkridge_Disclosure Sold Unsold.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Park Ridge.pdf11 Oct 2024
Form 5 (FY 2023-2024)30 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Godrej PArkridge.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Godrej Parkridge.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park ridge_compressed.pdf13 Jul 2024
Disclosure of sold/ booked inventoryFile: Parkridge.pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate - R5A.pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parkridge certificate signed.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE R5A.pdf9 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE - R5A.pdf9 Apr 2024
Disclosure of sold/ booked inventoryFile: Parkridge.pdf4 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R5A Parkridge_RERA Certificate.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE R5A_Godrej Parkridge.pdf15 Jan 2024
Disclosure of sold/ booked inventoryFile: Parkridge.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Godrej Park Ridge.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: park ridge.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Parkridge_11zon.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Park ridge.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park ridge_11zon.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Manjari - Park Ridge SIGNED.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parkridge_CA.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Parkridge_Architect Certificate.pdf12 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Parkridge (R5A) Engineers certificate - Q1 June2023-compressed.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: Parkridge-compressed.pdf10 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate R5A_compressed.pdf17 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance R5A.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: Godrej Parkridge_compressed.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parkridge_ Form-3_compressed.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Park Ridge Architect Certificate.pdf19 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Park ridge_compressed.pdf19 Jan 2023
Disclosure of sold/ booked inventoryFile: GODREJ PARKRIDGE.PDF19 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park Ridge Form 3_compressed.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R5A Engineers Certificate_compressed.pdf17 Oct 2022
Disclosure of sold/ booked inventoryFile: Sold unsold-Parkridge.pdf17 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Parkridge.pdf17 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Manjari - Park Ridge.pdf30 Sep 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Parkridge Society Cerficate .pdf14 Sep 2022
Building plan approvalFile: Building plan_PARKRIDGE.pdf28 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: Building plan_PARKRIDGE.pdf28 Jul 2022
Declaration about Commencement CertificateFile: Draft - Declaration of Commencement Certificate.pdf21 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Building CC revised_compressed.pdf15 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Parrdige (R5A) -Engineers Certificate Jun-22_compressed.pdf7 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Goderj Parkridge (R5A) - Quality Assurance Certificate - Jun-22.pdf7 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_Manjri1.pdf7 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200241688908_Manjri2.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: Parkridge 1 -Inventory.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: Parkridge -Inventory2.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_2 Park Ridge-signed.pdf7 Jul 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Godrej Sky Greens Phase 2P52100032794Manjari Khurd, Pune320Jan 2022OngoingMar 2026Not delivered

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Parkridge on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Manjari Kh13,700+ in Pune

2 kmGodrej ParkridgeCompleted 12Lapsed / revoked 3Other 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: Manjari Housing Projects LLP

Manjari Housing Projects LLP has 9 registrations on MahaRERA, including GODREJ BOULEVARD and Godrej Park Springs. Its filings disclose 7 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Godrej Parkridge shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Godrej Parkridge is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Parkridge?

The registered promoter entity is Manjari Housing Projects LLP, an others as per the filing. Its GSTIN 27AARFG0014F1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Parkridge?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Parkridge?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Parkridge?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Parkridge?

The professionals named in the filing: Architect: VK:a architecture; Architect: ANA Consortium Pvt Ltd; Engineer: CBRE South Asia Pvt. Ltd.; Engineer: Mangesh Avinash Lawand; Chartered Accountant: MD Deshpande & Co; Chartered Accountant: B S R & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Parkridge?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Parkridge. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Parkridge to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.