Registered Litigation declared Others project

Godrej Meadows- Phase 2

By Mahalunge Township Developers Private Limited

RG-MH-22664 · RERA P52100031794 · Last updated on MahaRERA portal: 13 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 48 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 321.00 crore secured on the land, in favour of ICICI Bank Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
19 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 95%
5 of 498Units unsoldnot recorded sold or booked
48Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

Godrej Meadows- Phase 2 is a Others project by Mahalunge Township Developers Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100031794 on 12 Nov 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 493 of the 498 units on this registration are recorded sold or booked, and 19 of 33 construction stages are filed complete. 48 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Meadows- Phase 2
  • TypeOthers
  • Location
    • MDR Road
    • Mahalunge
    • Mulshi
    • Pune
    • 411045
  • Pincode411045
  • RERA no.P52100031794
  • ReraGenie IDRG-MH-22664

Builder

  • NameMahalunge Township Developers Private Limited
  • Entity typeOthers
  • GSTIN27AAUCM0614K1Z5
  • PartnerMahalunge Land Developers Private Limited NA
  • Other registrations7 more →
  • Completed1 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredNov 2021First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Nov 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings3 building records
  • Documents filed106 files

Current status

99%493 of 498 units booked
80.0%Work done, per cost certificate

Figures as on 13 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower- 01NA33322440244
Tower- 02NA33322440244
Commercial BuildingNA4101010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 95%.

Tower- 0188%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises93%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.92%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.88%
Tower- 0285%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks89%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.77%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.79%
Commercial Building80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks86%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes88%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes60%
Street LightingYes75%
Community BuildingsYes65%
Treatment And Disposal Of Sewage And Sullage WaterYes85%
Solid Waste Management And DisposalYes88%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceYes30%
Open ParkingYes80%

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area9,290 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank Limited
Secured amountRs 321.00 crore
CERSAI search filedYes
Declared on28 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI37970.51
Proposed, not sanctioned37,971 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Address Commercia, Survey No 154, Shop No 118,119,120, Mumbai-Bangalore Highway, Wakad, Pune- 41
Estimated costRs 217
Cost incurredRs 173
Work done79.98%
BuildingWingEstimatedIncurred
Tower- 02NARs 104Rs 80
Tower- 01NARs 104Rs 84
-NARs 5Rs 4
Commercial BuildingNARs 4Rs 4

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKA Architecture
ArchitectVK: a architecture
ArchitectANA Consortium Pvt Ltd
EngineerSarika Infratech
EngineerSamartha Constro Consultants LLP
EngineerNavnath Kolekar
Chartered AccountantMD Deshpande and Co
Chartered AccountantM D Deshpande & Co
Chartered AccountantB S R & Co. LLP
Chartered AccountantBSR & Co. LLP
PartnerRole in project
Mahalunge Township Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23122518928Dec 2025 → Dec 2026

Reason as filed by the promoterThe delay in project completion was caused by a combination of factors beyond the reasonable control of the developer, including abnormal variation in material prices and labour wages, supply chain disruptions due to industry strikes, acute labour shortages, and regulatory construction bans imposed due to environmental concerns. These factors collectively disrupted construction activities, affected productivity, and extended project timelines. The developer has acted in good faith and exercised due diligence in managing the project under challenging conditions. All possible steps have been tak

Litigation declared4

CaseCourtStatus
RCS 822/2008Civil Judge Senior DIvisionClosed
RCS 1233/2014Civil Judge Senior DIvisionOngoing
RCA 601/2014District Judge and Addl Sessions Judge PuneOngoing
RCS - 170/2021/2021Pune District & Sessions CourtOngoing

Complaints filed with MahaRERA48

Case no.ComplainantRespondentFiled
CC12400762Babita RaniMahalunge Township Developers LLP13/11/2024
CC12600014Nishant UdavantMahalunge Township Developers Private Limited02/01/2026
CC12600446Anil KumarMahalunge Township Developers Private Limited24/01/2026
CC12600515Jayesh KadamMahalunge Township Developers Private Limited29/01/2026
CC12600977Ajoy Kumar SumanMahalunge Township Developers Private Limited23/02/2026
CC12601197Karuna RautMahalunge Township Developers Private Limited05/03/2026
CC12600985Darshankumar KshirsagarMahalunge Township Developers Private Limited23/02/2026
CC12601005Ishita GuptaMahalunge Township Developers Private Limited24/02/2026
CC12601074Rushikesh JadhavMahalunge Township Developers Private Limited27/02/2026
CC12601077Amiben LakkadMahalunge Township Developers Private Limited27/02/2026
CC12601270Jagdish SawantMahalunge Township Developers Private Limited09/03/2026
CC12601139Suraj HengneMahalunge Township Developers Private Limited02/03/2026
CC12601186Antima TiwariMahalunge Township Developers Private Limited04/03/2026
CC12601187Viraj DavareMahalunge Township Developers Private Limited04/03/2026
CC12601201Kalpesh SalunkeMahalunge Township Developers Private Limited05/03/2026
CC12601293Swapnil Sudhakar MalgaonkarMahalunge Township Developers Private Limited10/03/2026
CC12601324Girish NANDESHWAR MAHAJANMahalunge Township Developers Private Limited11/03/2026
CC12601330Chandralekha RautMahalunge Township Developers Private Limited11/03/2026
CC12601481Vipin SankhwarMahalunge Township Developers Private Limited17/03/2026
CC12601810Sampurna MohantyMahalunge Township Developers Private Limited28/03/2026
CC12601811Sampurna MohantyMahalunge Township Developers Private Limited28/03/2026
CC12601594Bhawna TiwariMahalunge Township Developers Private Limited22/03/2026
CC12601957Aditya WaghMahalunge Township Developers Private Limited02/04/2026
CC12601995Dheeraj KhandareMahalunge Township Developers Private Limited04/04/2026
CC12602020Boni KhatriMahalunge Township Developers Private Limited05/04/2026
CC12602554MAYUR MANOJ SAPATEMahalunge Township Developers Private Limited01/05/2026
CC12602065Sanjeet KhandagaleMahalunge Township Developers Private Limited08/04/2026
CC12602077Saksham BamezaiMahalunge Township Developers Private Limited09/04/2026
CC12602155Jayesh KirangeMahalunge Township Developers Private Limited12/04/2026
CC12602362Pratik DesaiMahalunge Township Developers Private Limited21/04/2026
CC12602474Amey PolMahalunge Township Developers Private Limited27/04/2026
CC12602427preity vyasMahalunge Township Developers Private Limited25/04/2026
CC12602638Dipa TiwariMahalunge Township Developers Private Limited07/05/2026
CC12602767Tarun DubeyMahalunge Township Developers Private Limited12/05/2026
CC12602846Madhuri BhavaleMahalunge Township Developers Private Limited15/05/2026
CC12602845Bhavya ThakkarMahalunge Township Developers Private Limited15/05/2026
CC12602956Shreyas SakorikarMahalunge Township Developers Private Limited19/05/2026
CC12602980Vimalkumar SinghMahalunge Township Developers Private Limited20/05/2026
CC12603086Amol JoshiMahalunge Township Developers Private Limited24/05/2026
CC12603143Dimple BhatMahalunge Township Developers Private Limited26/05/2026
CC12603380Antariksh GainMahalunge Township Developers Private Limited02/06/2026
CC12603545Gananayak SinghMahalunge Township Developers Private Limited08/06/2026
CC12603510Sumit DeshmukhMahalunge Township Developers Private Limited07/06/2026
CC12603793Rakesh KumarMahalunge Township Developers Private Limited19/06/2026
CC12603983Yogesh JadhavMahalunge Township Developers Private Limited27/06/2026
CC12604252ashwin kawduji sawalikarMahalunge Township Developers Private Limited07/07/2026
CC12604377Jaideep ThoratMahalunge Township Developers Private Limited13/07/2026
CC12604372Prachi PatilMahalunge Township Developers Private Limited13/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: R-08 Phase 2_RERA FORM-1_20-04-2026.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2 R8B.pdf13 Jun 2026
Withdrawal Update Form 3File: R8B.pdf13 Jun 2026
Form 2A (FY 2025-2026)File: R8B.pdf13 Jun 2026
Withdrawal Update Form 1File: Form -1_R-08_Phase 2_Q3FY26.pdf19 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate for Godrej R8B Mahalunge Meadows Phase II _Dec 25 1.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3 - Godrej Meadows 2 - Q3FY26.pdf19 Jan 2026
Withdrawal Update Form 1File: Form -1_R-08_Phase 2_Q3FY26.pdf18 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate for Godrej R8B Mahalunge Meadows Phase II _Dec 25 1.pdf18 Jan 2026
Withdrawal Update Form 3File: Meadows 2.pdf18 Jan 2026
Form 1File: R-08_Phase 2_RERA FORM-1_16-10-2025.pdf17 Oct 2025
Form 2File: Form 2_Meadows Phase II _Q2'26.pdf17 Oct 2025
Form 3File: Form 3_Signed_ Godrej Meadow 2 _September 2025.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure_R8B_Q2 FY 26.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: Meadows - 2.pdf26 Aug 2025
Form 1File: R-08 Phase2_Rera Form -1_21-07-2025.pdf22 Jul 2025
Form 2File: Form 2_Q1_FY 26_Meadows 2.pdf22 Jul 2025
Form 3File: Signed_ MDD_ Godrej Meadows 2_June 2025.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure_Q1_FY26_Meadows 2.pdf22 Jul 2025
Form 1File: R-08_B2_Rera Form-1.pdf27 Jun 2025
Form 2File: Form 2 - M2.pdf27 Jun 2025
Form 3File: Signed_MDD_ Godrej Meadows 2_Mar 2025.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure_Godrej Meadows-Phase 2.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R-08B_Rera Form-1_Updated.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R-08_B_Rera Form-1.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Meadows Ph2.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_MDD_ Godrej Meadows 2_Mar 2025.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - M2.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure_Godrej Meadows-Phase 2.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Meadows 2 _ Form 1 _ Q3 F25.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _ Meadows 2 _ Q3 FY25.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Meadows Phase 2 _ Form 2 _ Q3 FY25.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Godrej Meadows-Phase 2 _ Inventory Data _ Q3 FY25.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Meadows 2.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Meadows 2.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Godrej Meadows-Phase 2.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Meadows 2.pdf14 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Meadows 2.pdf14 Oct 2024
Form 5 (FY 2023-2024)File: Meadows 2.pdf29 Sep 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Meadows 2_RERA certificate_Jun'24 (1) - v1.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Meadows 2.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240630 - RERA Certificate (Form 1) - R8B.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Godrej Meadows-Phase 2.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240331 - RERA Certificate - Meadows Phase 2.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Meadows -2 R8B - Form 2A.pdf18 Apr 2024
Disclosure of sold/ booked inventoryFile: Godrej Meadows-Phase 2.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahalunge - Meadows 2.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahalunge _ Meadows 2_Form 3.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 231231 - RERA Certificate - R8B - Phase II - Godrej Meadows _II.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA engineer's certificate_R8B Meadows 2_Dec-23.pdf15 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory Data _ Godej Meadows 2 _ Q3 FY24.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Godrej Meadows Phase 2.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_ Godrej Meadows-II_Sept_2023- Signed.pdf5 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230930 - RERA Certificate - R8B - Phase II_Green Meadows Phase II.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Meadows 2_RERA Engineer's certificate_Sep-23.pdf17 Oct 2023
Disclosure of sold/ booked inventoryFile: MEADOWS PHASE 2.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Godrej Meadows II.pdf22 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate_Meadows_II_Mahalunge_June23.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Godrej Meadows Phase 2_11zon.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Meadows II.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Meadows02_RERA_Engineer_certificate.pdf17 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Meadows02_Quality_certificate_2023.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: Godrej Meadows Phase 2_compressed.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Meadows Phase II.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Meadows Phase II.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Meadows 2_Engineer's certificate_Dec-22.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Godrej Meadows phase 2.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_ Godrej Meadows-II-Signed.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD Godrej Meadows 2 CA.pdf18 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate GODREJ MEADOWS PH 2.pdf17 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Meadows phase 2 RERA Engineer certificate 300922.pdf17 Oct 2022
Disclosure of sold/ booked inventoryFile: Godrej Meadows phase 2 Inventory.pdf17 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Meadows 2.pdf30 Sep 2022
Disclosure of sold/ booked inventoryFile: Godrej Meadows phase 2_compressed.pdf15 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Meadows phase 2 Engineer certificate_compressed.pdf11 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_Mahalunge.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_ Godrej Meadows-II-Signed.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Meadows 2 Mar 22.pdf11 Apr 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Godrej Hillside 1P52100022099Mahalunge, Pune605Aug 2019OngoingOct 2024Not delivered

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Meadows- Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahalunge13,700+ in Pune

Builder: Mahalunge Township Developers Private Limited

Mahalunge Township Developers Private Limited has 8 registrations on MahaRERA, including Godrej Green Cove and Godrej Green Vistas. Its filings disclose 8 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Litigation is declared on 8 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Meadows- Phase 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Meadows- Phase 2?

The registered promoter entity is Mahalunge Township Developers Private Limited, an others as per the filing. Its GSTIN 27AAUCM0614K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Meadows- Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Meadows- Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Meadows- Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Meadows- Phase 2?

The professionals named in the filing: Architect: VKA Architecture; Architect: VK: a architecture; Architect: ANA Consortium Pvt Ltd; Engineer: Sarika Infratech; Engineer: Samartha Constro Consultants LLP; Engineer: Navnath Kolekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Meadows- Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Meadows- Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Meadows- Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.