Godrej Green Vistas

By Mahalunge Township Developers Private Limited

RG-MH-17203 · RERA P52100028117 · Last updated on MahaRERA portal: 1 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 9 complaints at MahaRERA
  • Completion date moved by 11 months
  • 2 extensions taken
  • Rs 321.00 crore secured on the land, in favour of ICICI Bank Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2026Possession promisedregistration recorded completed
42 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 97%
9 of 784Units unsoldnot recorded sold or booked
9Complaints at MahaRERAon this registration
Jump to the 180 documents Report an error

Godrej Green Vistas is a Others project by Mahalunge Township Developers Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100028117 on 4 Feb 2021. The registration is recorded completed; possession was promised by 30 May 2026. The completion date has moved by 11 months from the original filing. 775 of the 784 units on this registration are recorded sold or booked, and 42 of 55 construction stages are filed complete. 9 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Green Vistas
  • TypeOthers
  • Location
    • MDR Road
    • Mahalunge
    • Mulshi
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028117
  • ReraGenie IDRG-MH-17203

Builder

  • NameMahalunge Township Developers Private Limited
  • Entity typeOthers
  • GSTIN27AAUCM0614K1Z5
  • PartnersGodrej Properties Limited NA, Mahalunge Land Developers Private Limited NA
  • Other registrations7 more →
  • Completed1 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredFeb 2021First promiseJun 2025Revised toMay 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Feb 2021
  • Promised completion30 May 2026
  • Revised completionRevised to 30 May 2026 (originally 30 Jun 2025)
  • Buildings5 building records
  • Documents filed180 files

Current status

99%775 of 784 units booked
94.1%Work done, per cost certificate

Figures as on 1 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA242317510185
Tower 2NA242317910189
Tower 3NA232217110181
Tower 4NA282721810228
Retail TowerNA22011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

42 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 97%.

Tower 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Retail Tower71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed2262

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2,262
Closed/Covered2,262

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area19,152 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank Limited
Secured amountRs 321.00 crore
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI56737.9
Proposed, not sanctioned56,738 sq m
Buildings approved5
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Address Commercia, Survey No 154, Shop No 118, 119, 120, Mumbai Bangalore Highway, Wakad, Pune-
Estimated costRs 235.79 cr
Cost incurredRs 221.94 cr
Work done94.13%
BuildingWingEstimatedIncurred
Tower 4NARs 70.20 crRs 61.91 cr
Tower 2NARs 53.62 crRs 51.45 cr
Tower 1NARs 51.87 crRs 50.87 cr
Tower 3NARs 50.91 crRs 48.65 cr
-NARs 6.96 crRs 6.85 cr
Retail TowerNARs 2.23 crRs 2.21 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVka
ArchitectANA Consortium Pvt Ltd
EngineerBricklane India
EngineerAnil T. Powar
EngineerDeepak Jadhav
Chartered AccountantMD Deshpande & Co
Chartered AccountantM D Deshpande & Co.
Chartered AccountantB S R & Co. LLP
Chartered AccountantBSR & Co. LLP
PartnerRole in project
Mahalunge Township Developers Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20062501691Jun 2025 → Dec 2025

Reason as filed by the promoterThe issuance of the Completion Certificate has been delayed due to technical processing issues at the planning authority. This is expected to be received at the earliest possible. Considering these challenges, we respectfully request an extension of six months, with a revised completion date of 30.12.2025.

EA06042620563Jun 2025 → May 2026

Reason as filed by the promoterRespected Sir, We respectfully submit that the Promoter had earlier applied for closure of the MahaRERA registration of the project upon receipt of the Occupancy Certificate (OC), and the said closure application was under scrutiny before the Authority. While the said closure application was pending scrutiny, the project registration stood lapsed. During the course of such scrutiny, the Authority raised a query indicating that certain details/information furnished in the application require correction/modification. In view of the above circumstances, the Promoter has applied for extension of t

Litigation declared4

CaseCourtStatus
1233/2014/2014Civil Judge Junior DIvisionOngoing
822/2008/2008Civil Judge Junior DIvisionClosed
RCS - 170/2021/2021Pune District & Sessions CourtOngoing
RCA - 601/2014/2014Pune District & Sessions CourtOngoing

Complaints filed with MahaRERA9

Case no.ComplainantRespondentFiled
CC12502761Deepak Ashok PanditaMahalunge Township Developers LLP06/08/2025
CC12503432Abhijeet Balasaheb JadhavMahalunge Township Developers LLP26/09/2025
CC12504160RAHUL DUBEYMahalunge Township Developers LLP25/11/2025
CC12504089Deepali KhatriMahalunge Township Developers LLP20/11/2025
CC12504100Ameya Bhaurao SawantMahalunge Township Developers LLP21/11/2025
CC12504703Abhishek GautamMahalunge Township Developers LLP30/12/2025
CC12600004Sandeep PatwaMahalunge Township Developers LLP01/01/2026
CC12600722Rohit BhatMahalunge Township Developers Private Limited08/02/2026
CC12604333KANJI RAMJIBHAI BERAMahalunge Township Developers Private Limited11/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jan 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed180

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Part OC 1.pdf1 Jun 2026
Occupational CertificateFile: Part OC.pdf1 Jun 2026
Occupational CertificateFile: Final OC.pdf1 Jun 2026
Occupational CertificateFile: OC verification mail from PMRDA to RERA.pdf1 Jun 2026
Layout approvalFile: Retail Tower Godrej Green Vistas_compressed.pdf23 May 2026
Building plan approvalFile: Layout R6 Dec 2025.pdf20 May 2026
Layout approvalFile: T1 2nd and Typical Dec 2024.pdf20 May 2026
Layout approvalFile: T1 Dec 2024.pdf20 May 2026
Layout approvalFile: T1 Sec and Elev Dec 2024.pdf20 May 2026
Layout approvalFile: T2 sec and Elev Dec 2024.pdf20 May 2026
Layout approvalFile: T2 Typical Dec 2024.pdf20 May 2026
Layout approvalFile: T2 LG Dec 2024.pdf20 May 2026
Layout approvalFile: T3 Grnd Floor.pdf20 May 2026
Layout approvalFile: T3 Sec and Elev.pdf20 May 2026
Layout approvalFile: T3 2nd Floor plan.pdf20 May 2026
Layout approvalFile: T4 sec and Elev.pdf20 May 2026
Layout approvalFile: T4 terrace.pdf20 May 2026
Layout approvalFile: T4 2nd Floor.pdf20 May 2026
Layout approvalFile: R6-9.pdf20 May 2026
Layout approvalFile: MLCP First Floor.pdf20 May 2026
Layout approvalFile: MLCP terrace.pdf20 May 2026
Layout approvalFile: MLCP Section and Elevation.pdf20 May 2026
Layout approvalFile: MLCP 4th Floor Dec 2025.pdf20 May 2026
Layout approvalFile: MLCP 5th Floor Dec 2025.pdf20 May 2026
Layout approvalFile: MLCP 3rd Floor Dec 2025.pdf20 May 2026
Layout approvalFile: MLCP 2nd Floor DEc 2025.pdf20 May 2026
Layout approvalFile: R6-8.pdf20 May 2026
Withdrawal Update Form 1File: R-06_RERA FORM-1_20-04-2026.pdf19 May 2026
Withdrawal Update Form 2File: Form 2 R6.pdf19 May 2026
Withdrawal Update Form 3File: R6.pdf19 May 2026
Building plan approvalFile: R6-1.pdf12 May 2026
Layout approvalFile: R6-2.pdf12 May 2026
Layout approvalFile: R6-3.pdf12 May 2026
Layout approvalFile: R6-4.pdf12 May 2026
Layout approvalFile: R6-5.pdf12 May 2026
Layout approvalFile: R6-6.pdf12 May 2026
Layout approvalFile: R6-7_compressed.pdf12 May 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf12 May 2026
Form 5 (FY 2025-2026)File: Form 5.pdf12 May 2026
Withdrawal Update Form 1File: R-06_RERA FORM-1_20-04-2026.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 R6.pdf4 May 2026
Withdrawal Update Form 3File: R6.pdf4 May 2026
Withdrawal Update Form 1File: R-06_Phase 2_RERA FORM-1_16-10-2025.pdf23 Feb 2026
Withdrawal Update Form 1File: Form -1_R-06_Q3FY26.pdf23 Feb 2026
Withdrawal Update Form 2File: Form 2_Godrej Green Vistas_Q2u002726.pdf23 Feb 2026
Withdrawal Update Form 2File: Engineers Certificate for Godrej R6 Mahalunge Green Vistas_Dec 25 1.pdf23 Feb 2026
Withdrawal Update Form 3File: Form 3_MDD_Green Vistas_30th September-25_Signed.pdf23 Feb 2026
Withdrawal Update Form 3File: Form 3 - Green Vistas - Q3FY26.pdf23 Feb 2026
Withdrawal Update Form 1File: R-06_Rera Form-1_21-07-2025.pdf17 Oct 2025
Withdrawal Update Form 1File: R-06_Phase 2_RERA FORM-1_16-10-2025.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Vistas.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2_Godrej Green Vistas_Q2u002726.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3_MDD_Green Vistas_30th September-25_Signed.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3_MDD_Green Vistas_30th September-25_Signed.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: Vistas.pdf26 Aug 2025
Withdrawal Update Form 1File: R-06_Rera Form-1_21-07-2025.pdf23 Jul 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Vistas.pdf23 Jul 2025
Withdrawal Update Form 3File: Signed_MDD_Green Vistas_30th June-25.pdf23 Jul 2025
Withdrawal Update Form 1File: R-06_Rera Form-1_21-07-2025.pdf22 Jul 2025
Withdrawal Update Form 1File: R-06_Rera Form-1_21-07-2025.pdf22 Jul 2025
Withdrawal Update Form 1File: R-06_Rera Form-1_21-07-2025.pdf22 Jul 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Vistas.pdf22 Jul 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Vistas.pdf22 Jul 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Vistas.pdf22 Jul 2025
Withdrawal Update Form 3File: Signed_MDD_Green Vistas_30th June-25.pdf22 Jul 2025
Withdrawal Update Form 3File: Signed_MDD_Green Vistas_30th June-25.pdf22 Jul 2025
Withdrawal Update Form 3File: Signed_MDD_Green Vistas_30th June-25.pdf22 Jul 2025
Form 1File: R-06_Rera Form-1.pdf20 Jun 2025
Form 2File: Form 2 - GGV.pdf20 Jun 2025
Form 3File: Signed_MDD_Green Vistas_31st Mar-25.pdf20 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure_Godrej Green Vistas.pdf20 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R-06_Rera Form-1.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Green Vistas.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_MDD_Green Vistas_31st Mar-25.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - GGV.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure_Godrej Green Vistas.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert _Godrej Green Vistas-1 Apr 2021.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Godrej Green Vistas-1 Apr 2021.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Godrej Green Vistas-1 Apr 2021.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Green Vistas _ Form 1 _ Q3 FY25.pdf17 Jan 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Godrej Hillside 1P52100022099Mahalunge, Pune605Aug 2019OngoingOct 2024Not delivered

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 11 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Green Vistas on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahalunge13,700+ in Pune

2 kmGodrej Green VistasCompleted 90Lapsed / revoked 35Other 121Dot size: filed unitsN

Filed coordinates, straight-line distance. 246 registered projects within 2 km.

Builder: Mahalunge Township Developers Private Limited

Mahalunge Township Developers Private Limited has 8 registrations on MahaRERA, including Godrej Green Cove and Godrej Green Vistas. Its filings disclose 8 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Litigation is declared on 8 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Green Vistas is delayed beyond 30 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Green Vistas?

The registered promoter entity is Mahalunge Township Developers Private Limited, an others as per the filing. Its GSTIN 27AAUCM0614K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Green Vistas?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Green Vistas?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Green Vistas?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Green Vistas?

The professionals named in the filing: Architect: Vka; Architect: ANA Consortium Pvt Ltd; Engineer: Bricklane India; Engineer: Anil T. Powar; Engineer: Deepak Jadhav; Chartered Accountant: MD Deshpande & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Green Vistas?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Green Vistas. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Green Vistas to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.