Home / Browse projects / Pune, Maharashtra / Godrej Green Cove

Registration lapsed Litigation declared Others project

Godrej Green Cove

By Mahalunge Township Developers Private Limited

RG-MH-16790 · RERA P52100026875 · Last updated on MahaRERA portal: 22 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 3 cases
  • 5 complaints at MahaRERA
  • Completion date moved by 15 months
  • 2 extensions taken
  • Rs 321.00 crore secured on the land, in favour of ICICI Bank Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
54 of 66Construction stages doneacross 6 buildings; furthest along: Podiums (if any), 0%
12 of 741Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 129 documents Report an error

Godrej Green Cove is a Others project by Mahalunge Township Developers Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100026875 on 3 Nov 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 15 months from the original filing. 729 of the 741 units on this registration are recorded sold or booked, and 54 of 66 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Green Cove
  • TypeOthers
  • Location
    • MDR Road
    • Mahalunge
    • Mulshi
    • Pune
    • 411045
  • Pincode411045
  • RERA no.P52100026875
  • ReraGenie IDRG-MH-16790

Builder

  • NameMahalunge Township Developers Private Limited
  • Entity typeOthers
  • GSTIN27AAUCM0614K1Z5
  • PartnersGodrej Properties Limited NA, Mahalunge Land Developers LLP NA
  • Other registrations7 more →
  • Completed1 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

4 months past promisethis monthRegisteredNov 2020First promiseMar 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Nov 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Mar 2025)
  • Buildings6 building records
  • Documents filed129 files

Current status

98%729 of 741 units booked
98.2%Work done, per cost certificate

Figures as on 22 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 2NA232317410184
Tower 3NA23231820182
Tower 4NA23231820182
Tower 1NA232317410184
MLCP TowerNA41088
Retail TowerNA22011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Podiums (if any), at 0%.

Tower 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tower 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
MLCP Tower82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Retail Tower82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed3783

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3,783
Closed/Covered3,783

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area17,531 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI Bank Limited
Secured amountRs 321.00 crore
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI48155.83
Proposed, not sanctioned48,156 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThe Address Commercia, Survey No 154, Shop No 118, 119, 120, Mumbai- Bangalore Highway, Wakad, Pune-
Estimated costRs 243.18 cr
Cost incurredRs 238.72 cr
Work done98.17%
BuildingWingEstimatedIncurred
Tower 3NARs 50.72 crRs 49.80 cr
Tower 4NARs 50.50 crRs 49.91 cr
Tower 2NARs 50.38 crRs 49.72 cr
Tower 1NARs 50.38 crRs 48.60 cr
MLCP TowerNARs 29.50 crRs 29.27 cr
-NARs 8.00 crRs 7.97 cr
Retail TowerNARs 3.70 crRs 3.45 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVka
ArchitectAna Consortium Pvt Ltd
EngineerBricklane India
EngineerAnil T Powar
Chartered AccountantMD Deshpande & CO
Chartered AccountantM D Deshpande & Co
Chartered AccountantB S R and Co LLP
PartnerRole in project
Mahalunge Township Developers Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA12082502367Mar 2025 → Dec 2025

Reason as filed by the promoterWe respectfully request an extension of six months, with a revised completion date of 31/12/2025. The Project has been offered for possession to 97% of the allottees and 94% of the allottees have already taken possession. We have already applied for the Occupancy certificate but due to slow processing we are facing delays because of which we are not able to file Form 4.

EA27012619595Mar 2025 → Jun 2026

Reason as filed by the promoterWe respectfully request an extension of six months, with a revised completion date of 30/06/2026. The Project has been offered for possession to 97% of the allottees and 94% of the allottees have already taken possession. We have already applied for the Occupancy certificate but due to slow processing we are facing delays because of which we are not able to file Form 4.

Litigation declared3

CaseCourtStatus
RCS - 170/2021/2021Pune District & Sessions CourtOngoing
RCS - 1233/2014/2014Pune District & Sessions CourtOngoing
RCA - 601/2014/2014Pune District & Sessions CourtOngoing

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000258839Pravin Laxman JadhavMahalungeTownshipDevelopers LLP09/05/2023
CC12603777Mahalunge Township Developers Private LimitedRahul Shukla18/06/2026
CC12603780Mahalunge Township Developers Private LimitedRAHUL SHUKLA18/06/2026
CC12603782Mahalunge Township Developers Private LimitedRAHUL SHUKLA18/06/2026
CC12603783Mahalunge Township Developers Private LimitedRAHUL SHUKLA18/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed129

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 129 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: R-07A_RERA FORM-1_20-04-2026.pdf22 Apr 2026
Withdrawal Update Form 2File: Form 2 R7A.pdf22 Apr 2026
Withdrawal Update Form 3File: R7A.pdf22 Apr 2026
Withdrawal Update Form 1File: R-07A_RERA FORM-1_20-04-2026.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2 R7A.pdf21 Apr 2026
Withdrawal Update Form 3File: R7A.pdf21 Apr 2026
Withdrawal Update Form 1File: Form -1_R-07_A_Q3FY26.pdf27 Jan 2026
Withdrawal Update Form 1File: Form -1_R-07_A_Q3FY26.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2_Godrej Green Cove_Q2u002726.pdf27 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate for Godrej R7a Mahalunge Green Cove_Dec 25 1.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 - Green Cove - Q3FY26.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 - Green Cove - Q3FY26.pdf27 Jan 2026
Withdrawal Update Form 1File: R-07 A_Rera Form-1_21-07-2025.pdf17 Oct 2025
Withdrawal Update Form 1File: R-07_RERA FORM-1_16-10-2025.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2_Q1_FY 26_Green Cove.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2_Godrej Green Cove_Q2u002726.pdf17 Oct 2025
Withdrawal Update Form 3File: Signed_Green Cove RERA 30th June 2025.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3_MDD_Green Cove RERA 30th Sept 2025_Signed.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: Cove.pdf26 Aug 2025
Form 1File: R-07_A_Rera Form-1.pdf11 Aug 2025
Form 2File: Form 2 - GGC.pdf11 Aug 2025
Form 3File: Signed _MDD Green Cove as on 31st Mar 2025.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure_Godrej Green Cove.pdf11 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R-07_A_Rera Form-1.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Green Cove.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed _MDD Green Cove as on 31st Mar 2025.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - GGC.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Disclosure_Godrej Green Cove.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Green Cove _ Form 1 _ Q3 FY25.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _ Green Cove _ Q3 FY25.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Green Cove _ Form 2 _ Q3 FY25.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Godrej Green Cove _ Inventory Data _ Q3 FY25.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cove.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Green Cove.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Green Cove.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Godrej Green Cove.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Green cove.pdf16 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Godrej Green Cove - v1.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Green Cove.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240630 - RERA Certificate (Form 1) - R7A.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R7A-Godrej Greencove.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Godrej Green Cove.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240331 - RERA Certificate- Green Cove.pdf22 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Green Cove R7A - Form 2A.pdf18 Apr 2024
Disclosure of sold/ booked inventoryFile: Godrej Green Cove.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahalunge _ Green Cove.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahalunge _ Green Cove_Form 3.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 231231 - RERA Certificate - R7A - 1_Godrej Green Cove.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA engineer's certificate_R7A Green Cove_Dec-23.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory Data _ Godej Green Cove _ Q3 FY24_11zon.pdf13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Godrej Green Cove.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: GREEN COVE.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Godrej Green Cove_MDD_Signed.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230930- RERA Certificate-R7A_Green cove.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Green Cove.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Green green Cove.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Green Cove.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf13 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certifcate_Greencove_Mahalunge_June23.pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: Godrej Green Cove_11zon.pdf13 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Creencove_RERA_Engineer_Certificate_.pdf17 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Green_Cove_Quality_certificate_2023.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: Godrej Green Cove_compressed (2).pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Green Cove.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Green cove.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Green Cove_Engineer's certificate_Dec-22.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Godrej Green Cove_compressed (1)_compressed.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_ Green Cove RERA-Signed.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD Green Cove RERA CA.pdf18 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate GREEN COVE.pdf17 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Green Cove RERA Engineer certificate 300922.pdf17 Oct 2022
Disclosure of sold/ booked inventoryFile: Godrej Green Cove Inventory.pdf17 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Mahalunge Green Cove.pdf30 Sep 2022
Disclosure of sold/ booked inventoryFile: Godrej Greencove Part 1.pdf15 Jul 2022
Disclosure of sold/ booked inventoryFile: Godre Greencove Part 2.pdf15 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Greencove Engineer certificate_compressed.pdf11 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_Mahalunge.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MDD_ Green Cove RERA-Signed.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Green Cove Mar 22.pdf11 Apr 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
Godrej Hillside 1P52100022099Mahalunge, PuneAug 2019OngoingOct 2024Not delivered

How this compares with Pune

98%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 15 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Green Cove on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahalunge13,700+ in Pune

Builder: Mahalunge Township Developers Private Limited

Mahalunge Township Developers Private Limited has 8 registrations on MahaRERA, including Godrej Green Cove and Godrej Green Vistas. Its filings disclose 8 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Litigation is declared on 8 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Godrej Green Cove shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Godrej Green Cove is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Green Cove?

The registered promoter entity is Mahalunge Township Developers Private Limited, an others as per the filing. Its GSTIN 27AAUCM0614K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Green Cove?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Green Cove?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Green Cove?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Green Cove?

The professionals named in the filing: Architect: Vka; Architect: Ana Consortium Pvt Ltd; Engineer: Bricklane India; Engineer: Anil T Powar; Chartered Accountant: MD Deshpande & CO; Chartered Accountant: M D Deshpande & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Green Cove?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Green Cove. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Green Cove to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.