ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Godrej Infinity

Completed No litigation declared Others project

Godrej Infinity

By OXFORD REALTY LLP

RG-MH-10814 · RERA P52100003129 · Last updated on MahaRERA portal: 13 Jul 2022

Source: official MahaRERA filing

Red flags

  • 29 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2020Possession promisedregistration recorded completed
60 of 66Construction stages doneacross 7 buildings; furthest along: Stilt Floor, 0%
29Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

Godrej Infinity is a Others project by OXFORD REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100003129 on 4 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2020. 29 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Infinity
  • TypeOthers
  • Location
    • KESHAVNAGAR
    • MUNDWA
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003129
  • ReraGenie IDRG-MH-10814

Builder

  • NameOXFORD REALTY LLP
  • Entity typeOthers
  • Named personsOXFORD SHELTERS PVT LTD, GODREJ PROPERTIES LIMITED, ASHOK KOTHARI, PARAG SHAH, ASHOK MOHANANI, VIVEK MOHANANI, ANIRUDHA SEOLEKAR, Ekta Housing Private Limited, EKTA WORLD PRIVATE LIMITED
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017PromisedSep 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion30 Sep 2020
  • Revised completionNone
  • Buildings7 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER T1NA300000
TOWER T2NA260000
TOWER T3NA260000
TOWER T4NA270000
TOWER T5NA270000
TOWER T6NA190000
Town Square RetailNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 13 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

60 of 66 construction stages are filed complete across 7 buildings. The stage furthest along is Stilt Floor, at 0%.

TOWER T191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER T291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER T391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER T491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER T591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER T691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Town Square RetailNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities16

As on 13 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Others Underground water tankYes100%

Parking filed1182

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,182
Closed/Covered933
Open Space249
BuildingClosed/CoveredOpen SpaceTotal
TOWER T110314117
TOWER T217319192
TOWER T317545220
TOWER T4140148288
TOWER T521119230
TOWER T61314135

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area51,906 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Hritik Technologies & Realty Pvt LtdAndheriMumbai Suburban
Oxford Shelters Pvt LtdPune (M Corp.)Pune
Godrej Properties Limited (as Development Manager)KurlaMumbai Suburban

Approvals and building plan

Permissible FSI119123.0
Proposed, not sanctioned119,123 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANEKJI WADIA BLDG GROUND FLOOR NANIK MOTWANI MARGFORTMUMBAI - 400001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectURBAN ARCHITECTURE WORKS
EngineerJW CONSULTANTS LLP
Chartered AccountantM D Deshpande & Co.
PartnerRole in project
OXFORD REALTY LLP-

Litigation declared13

CaseCourtStatus
SCS 396/2009Civil Court Senior DivisionPending
SCS 2677/2010Civil Court Senior DivisionPending
SCS 663/2006Civil Court Senior DivisionPending
RCS 622/2012Civil Court Junior DivisionPending
SCS 662/2006Civil Court Senior DivisionPending
SCS 49/2015Civil Court Senior DivisionCase Disposed
SCS 1378/2018Civil Court Senior DivisionPending
SCS 125/2019Civil Court Senior DivisionPending
SCS 1367/2018Civil Court Senior DivisionPending
CC005000000022952/2019RERA MUMBAIDisposed Of
CC005000000022973/2019RERA MUMBAIDisposed Of
SCS 472/2015Joint CJSD AND Additional CJM PunePending
RCS 121/2019Joint CJSD AND Additional CJM PunePending

Complaints filed with MahaRERA29

Case no.ComplainantRespondentFiled
CC005000000010392SHRIDHAR SHIRDHONEGodrej Properties Limited13/10/2017
CC005000000022952Sajay & JayaOXFORD REALTY LLP / GODREJ INFINITY25/04/2019
CC005000000022973SAURABH POREDI AND SAYALI RAMESH KAKADEOXFORD REALTY LLP29/04/2019
CC005000000023218Mohit SewakOxford reality LLP07/07/2019
CC005000000064875Mohit SewakOxford Realty LLP01/12/2020
CC005000000023221Abhishek KhattiOxford Realty LLP09/07/2019
CC005000000064877Abhishek KhattiOxford Realty LLP01/12/2020
CC005000000023222MAHARSHKUMAR SHARADKUMAR KAPADIAOxford Realty LLP10/07/2019
CC005000000053990ROSHNI LULLA AND RENU LULLAOXFORD REALTY LLP29/01/2020
CC005000000054042AMRITA BASU AND SUDIPTA BASUOXFORD REALTY LLP15/02/2020
CC005000000054082AMIT KALEOXFORD REALTY LLP28/02/2020
CC005000000064922Govind BhatOxford Realty and Godrej Realty11/12/2020
CC005000000075182Krishna BhandariRitesh Singla06/02/2021
CC005000000085520Shrirang Madhukar LonkarOxford Realty LLP01/05/2021
CC005000000085575Amit Madhukar BarveGodrej Properties Limited22/05/2021
CC005000000095851YOGESH JAGDISH BALANKE AND ADITI YOGESH BALANKEOXFORD REALTY LLP05/08/2021
CC005000000095852RASHMIN GANDHOKOXFORD REALTY LLP05/08/2021
CC005000000095853MEGHANA PRESHIT RASAL AND PRESHIT CHARUDATT RASALOXFORD REALTY LLP05/08/2021
CC005000000095928Shravan Kumar Singh and Anuyama KumariOxford Reality LLP01/09/2021
CC005000000095935Rishi Raj Vaidhya and Jyoti jainOxford Reality LLP01/09/2021
CC005000000095938Vipin Jain and Sonal JainOxford Reality LLP02/09/2021
CC005000000095939Vishal Arya and Shipra AryaOxford Reality LLP02/09/2021
CC005000000095940Dhiren Chauhan and Hetal ChauhanOxford Reality LLP04/09/2021
CC005000000095941Nimish Nair ,Neeti Thade and Vilasini NairOxford Reality LLP08/09/2021
CC005000000095944Avinash Nigam and Shristi RajOxford Reality LLP27/10/2021
CC005000000096125Sateesh Kallaoxford reality LLP19/10/2021
CC005000000106735Mrs Anjuman Farooque Shaikhoxford realty LLP throgh its partners07/03/2022
CC005000000167628Krishna Jagat BhandariOxford Realty LLP25/09/2022
CC12502422SAJAY REUBEN ABRAHAMOXFORD REALTY LLP16/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Apr 2021

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf13 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf14 Apr 2022
Disclosure of sold/ booked inventoryFile: Inventory Disclosure Infinity 311221K.pdf11 Feb 2022
Disclosure of sold/ booked inventoryFile: Infinity Sep 21.pdf26 Oct 2021
Disclosure of sold/ booked inventoryFile: Infinity compressed.pdf15 Jul 2021
Disclosure of sold/ booked inventoryFile: Infinity Towers 1 to 6 FINAL 250521 compressed.pdf27 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate - Godrej Infinity.pdf22 Apr 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: REGISTRATION CERTIFICATE.PDF22 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 Godrej Infinity.pdf1 Oct 2020
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 _Infinity.pdf11 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Infinity Architect's Certificate-30th June 2019.pdf8 Nov 2019
Certificates of CA (Form 5)File: Godrej Infinity Form 5 .pdf30 Sep 2019
Layout approvalFile: Layout-min copy.pdf30 Aug 2019
Copy of Layout Approval (in case of layout)File: Layout-min copy.pdf30 Aug 2019
Certificates of CA (Form 5)File: oxford realty-infinity-ilovepdf-compressed (1).pdf30 Sep 2018
Proforma of Allotment letterFile: Docs Infinity .pdf5 Jun 2018
Proforma of Allotment letterFile: Docs Infinity .pdf31 May 2018
Proforma of Allotment letterFile: Infinity -27-3-2018.pdf27 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: MX-1810U_20180314_152223.pdf14 Mar 2018
Proforma of Allotment letterFile: Infinity updated L.pdf6 Mar 2018
Proforma of Allotment letterFile: Infinity RERA - AFS.pdf14 Nov 2017
Building plan approvalFile: REVISED NA ORDER.pdf27 Jul 2017
Layout approvalFile: Infinity_Sanctioned,Proposed,fSI-compressed.pdf27 Jul 2017
PAN CardFile: ORLLP_PAN CARD.pdf27 Jul 2017
Copy of the legal title reportFile: Infinity Title_ certificate-compressed.pdf27 Jul 2017
Copy of the legal title reportFile: Infinity_Supplemental Title certificate.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrance-Infinity.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Infinity_Sanctioned,Proposed,fSI-compressed.pdf27 Jul 2017
Building Plan Approval (IOD)File: REVISED NA ORDER.pdf27 Jul 2017
Declaration in FORM BFile: Form B_ORLLP (2).pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Infinity_Architect's Certificate-compressed.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinity_Engineer's Certificate-compressed.pdf27 Jul 2017
Certificates of CA (Form 3)File: Infinity_CA Certificate-compressed.pdf27 Jul 2017
Proforma of Allotment letterFile: Proforma allotment and AFS_Infinity-compressed.pdf27 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Infinity on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUNDWA13,700+ in Pune

2 kmGodrej InfinityCompleted 55Lapsed / revoked 15Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 116 registered projects within 2 km.

Builder: OXFORD REALTY LLP

OXFORD REALTY LLP has 3 registrations on MahaRERA, including Godrej Infinity and Godrej Rejuve. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Infinity is delayed beyond 30 Sep 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Infinity?

The registered promoter entity is OXFORD REALTY LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Infinity?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Infinity?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Infinity?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Infinity?

The professionals named in the filing: Architect: URBAN ARCHITECTURE WORKS; Engineer: JW CONSULTANTS LLP; Chartered Accountant: M D Deshpande & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Infinity?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Infinity. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Infinity to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.