Home / Browse projects / Pune, Maharashtra / Godrej Hillside 2
Godrej Hillside 2
By Mahalunge Township Developers LLP
RG-MH-13072 · RERA P52100022153 · Last updated on MahaRERA portal: 31 Jul 2025
Source: official MahaRERA filing
Red flags
- Litigation declared, 5 cases
- 3 complaints at MahaRERA
- Rs 321.00 crore secured on the land, in favour of ICIC Bank Limited
Clear
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Godrej Hillside 2 is a Others project by Mahalunge Township Developers LLP in Pune, Maharashtra, registered with MahaRERA as P52100022153 on 4 Sep 2019. The registration is recorded completed; possession was promised by 30 Oct 2024. 547 of the 550 units on this registration are recorded sold or booked, and 36 of 44 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameGodrej Hillside 2
- TypeOthers
- Location
- MDR Road
- Mahalunge
- Mulshi
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100022153
- ReraGenie IDRG-MH-13072
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 Sep 2019
- Promised completion30 Oct 2024
- Revised completionNone
- Buildings4 building records
- Documents filed117 files
Current status
Figures as on 31 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | NA | 23 | 23 | 180 | 0 | 180 |
| Tower 2 | NA | 23 | 23 | 180 | 0 | 180 |
| Tower 3 | NA | 23 | 23 | 180 | 0 | 180 |
| Tower 4 | NA | 7 | 2 | 0 | 10 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 31 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
36 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
Tower 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower 382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower 482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 31 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2409
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Tower 1 | 400 | 403 | 803 |
| Tower 2 | 400 | 403 | 803 |
| Tower 3 | 400 | 403 | 803 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V K a Architecture |
| Engineer | Bricklane |
| Engineer | Melior Structural Solution Private Limited |
| Engineer | Samartha Constro Consultants LLP |
| Chartered Accountant | M D Deshpande & Co |
| Chartered Accountant | B S R & Co. LLP |
| Partner | Role in project |
|---|---|
| Mahalunge Township Developers LLP | - |
Litigation declared5
| Case | Court | Status |
|---|---|---|
| RCS 1233/2014 | Civil Judge Junior Division | Ongoing |
| RCS 822/2008 | Civil Judge Junior Division | Closed |
| RCA 601/2014 | District Judge and Addl Sessions Judge Pune | Ongoing |
| RCS - 1233/2014/2014 | Pune District & Sessions Court | Ongoing |
| RCS - 170/2021/2021 | Pune District & Sessions Court | Ongoing |
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064772 | BHUSHAN DINKAR RAUT | Godrej properties | 30/10/2020 |
| CC005000000310527 | Sundeep Balkrishna Chetty | Mahalunge Township Developers LLP | 02/05/2024 |
| CC12500355 | Panini Suhas pitake | Mahalunge Township Developers LLP | 01/02/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Jun 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Jan 2025
Documents filed117
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Form 4_Mail from PMRDA_OCs - Hillside 2.pdf | 31 Jul 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Godrej Hillside 2.pdf | 11 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R4_Full_OC.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside 2 _ Form 1 _ Q3 FY25.pdf | 17 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 _ Hillside 2 _ Q3 FY25.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Hillside 2 _ Form 2 _ Q3 FY25.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2 _ Inventory Data _ Q3 FY25.pdf | 13 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Hillside 2.pdf | 16 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 - Hillside 2.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside 2.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside 2.pdf | 12 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hill side 2.pdf | 12 Oct 2024 |
| Form 5 (FY 2023-2024)File: Hill side 2.pdf | 30 Sep 2024 |
| Certificates of CA (Form 3)File: HillSide 2.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240630 - RERA Certificate (Form 1) - R4.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: HS 2_July2024.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Godrej Hill Side 2.pdf | 13 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hillside-2 R4 - Form 2A.pdf | 18 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Godrej Hill Side 2.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahalunge _ Hillside 2.pdf | 17 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahalunge _ HILLSIDE 2.pdf | 17 Apr 2024 |
| Certificates of CA (Form 3)File: Mahalunge _ Hillside 2_Form 3.pdf | 17 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 231231 - RERA Certificate - Hillside 2.pdf | 15 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: HS2 (3).pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Data _ Godej Hill Side 2 _ Q3 FY24_11zon.pdf | 15 Jan 2024 |
| Certificates of CA (Form 3)File: Godrej HillSide 2.pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: HILLSIDE 2.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230930 RERA Certificate R4_Hillside 2.pdf | 17 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: HS2.pdf | 17 Oct 2023 |
| Certificates of CA (Form 3)File: MDD Godrej Hillside 2 -SIGNED.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Godrej Hillside II.pdf | 22 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Certificate_Hillside_02_June23_11zon.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2_11zon.pdf | 20 Jul 2023 |
| Certificates of CA (Form 3)File: Hill Side 2 CA.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 17 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside02_RERA_Engineer_certificate.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Hillside02_Quality_certificate_2023_compressed.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2_compressed.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: CA Hillside 2.pdf | 17 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside 2.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Hillside 2_Engineer's certificate_Dec-22.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: MDD_Hillside 2 RERA-signed.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220630 RERA Certificate R4 (1).pdf | 22 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Revised Certificate_1.pdf | 22 Oct 2022 |
| Certificates of CA (Form 3)File: MDD Hillside 2 RERA CA.pdf | 18 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate GODREJ HILLSIDE 2.pdf | 17 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Godrej Hill side 2 _RERA Eng Certificate.pdf | 17 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2 Inventory.pdf | 17 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Hillside 2.pdf | 30 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside-2 Engineer certificate_compressed.pdf | 11 Jul 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_Mahalunge.pdf | 7 Jul 2022 |
| Certificates of CA (Form 3)File: MDD_Hillside 2 RERA Signed.pdf | 7 Jul 2022 |
| Certificates of CA (Form 3)File: MDD_Hillside 2 RERA-Revised Signed Certificate.pdf | 10 May 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R4 for uploading.pdf | 20 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220405 RERA Certificate R4.pdf | 11 Apr 2022 |
| Certificates of CA (Form 3)File: Signed HillSide 2 Mar 22.pdf | 11 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hill side 2 Engineers Certificate for uploading.pdf | 7 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hillside 2 Quality certificate for uploading.pdf | 7 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Godrej Hillside 2 for uploading.pdf | 7 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Hillside 2 Society Certificate.pdf | 30 Mar 2022 |
| Certificates of CA (Form 3)File: CA Hillside 2 311221 compressed.pdf | 7 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Hillside 2.pdf | 15 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Mahalunge H2.pdf | 2 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside 2 Engineers Certificate 311231.pdf | 31 Jan 2022 |
| Certificates of CA (Form 3)File: R4-30 Sep 2021-Rera Form 3_MDD Draft_Signed.pdf | 15 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Hillside 2 - All Towers.pdf | 26 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R4 Form 2.pdf | 8 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hillside 2 2A_compressed.pdf | 8 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 211001 RERA Arch Certificate Hillside 2_compressed.pdf | 7 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: HILLSIDE 2_FORM 5.pdf | 30 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Hillside 2 - All Towers compressed July.pdf | 19 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30 June 2021 Hillside 2 R4 Engr Certificate.pdf | 27 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Hillside 2 QAQC Jun21.pdf | 27 Jul 2021 |
| Certificates of CA (Form 3)File: R4 30 June 2021Rera Form 3 Signed.pdf | 20 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 210715 RERA Certificate R4 Signed compressed.pdf | 16 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Hillside 2 - All Towers compressed.pdf | 5 Jun 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate- Godrej Hillside 2.pdf | 6 Apr 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Godrej River RoyaleP52100052957 | Mahalunge, Pune | 370 | Oct 2023 | Ongoing | Mar 2029 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 117 filed documents as one ZIP, foldered, with a manifest
Keep Godrej Hillside 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahalunge13,700+ in Pune
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: Mahalunge Township Developers LLP
Mahalunge Township Developers LLP has 2 registrations on MahaRERA, including Godrej Hillside 1 and Godrej Hillside 2. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Godrej Hillside 2 is delayed beyond 30 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Godrej Hillside 2?
The registered promoter entity is Mahalunge Township Developers LLP, an others as per the filing. Its GSTIN 27AAOFG3727E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Godrej Hillside 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Hillside 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Godrej Hillside 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Godrej Hillside 2?
The professionals named in the filing: Architect: V K a Architecture; Engineer: Bricklane; Engineer: Melior Structural Solution Private Limited; Engineer: Samartha Constro Consultants LLP; Chartered Accountant: M D Deshpande & Co; Chartered Accountant: B S R & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Hillside 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.