Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GAVANKAR RESIDENCY is a Residential / Group Housing project by DATTATRAY SHIVRAM GAVANKAR in Ratnagiri, Maharashtra, registered with MahaRERA as P52800010430 on 24 Aug 2017. Possession is promised by 30 Oct 2027. 0 of the 60 units on this registration are recorded sold or booked, and 10 of 33 construction stages are filed complete.
At a glance
Project
- NameGAVANKAR RESIDENCY
- TypeResidential / Group Housing
- Location
- 1051
- village Walope
- Walope
- Chiplun
- Ratnagiri
- 415605
- Pincode415605
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800010430
- ReraGenie IDRG-MH-56506
Builder
- NameDATTATRAY SHIVRAM GAVANKAR
- Entity typeIndividual
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Aug 2017
- Promised completion30 Oct 2027
- Revised completionNone
- Buildings3 building records
- Documents filed62 files
Current status
Figures as on 13 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GAVANKAR RESIDENCY A WING | NA | 4 | 3 | 24 | 0 | 24 |
| GAVANKAR RESIDENCY B WING | NA | 4 | 3 | 18 | 0 | 18 |
| GAVANKAR RESIDENCY C WING | NA | 4 | 3 | 18 | 0 | 18 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.
GAVANKAR RESIDENCY A WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GAVANKAR RESIDENCY B WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
GAVANKAR RESIDENCY C WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed84
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GAVANKAR RESIDENCY A WING | NA | Rs 3.92 cr | - |
| GAVANKAR RESIDENCY B WING | NA | Rs 1.96 cr | Rs 1.96 cr |
| - | NA | Rs 35.27 lakh | Rs 35.27 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR BHALEKAR |
| Engineer | Ravindra M Patil |
| Engineer | Precise Consultants |
| Chartered Accountant | S GANESH & Associates |
| Partner | Role in project |
|---|---|
| Gavankar Builders & Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2027
Documents filed62
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Archt Certificate Q I FY 26 27.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Engineer Certificate Q I FY 26 27.pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 full Q I 26-27.pdf | 13 Jul 2026 |
| Form 2A (FY 2026-2027)File: Form 2A Q I 26-27.pdf | 13 Jul 2026 |
| Form 5 (FY 2025-2026)File: Form 5 Q I 26-27.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Architect - June 25-compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Architect - Sep 25-compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Architect - Dec 25_compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 2File: Engineer - Jun 25-compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Sep 25_compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Dec 25_compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 3File: CA Certificate Q I April 25 to June 25.pdf | 12 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Jul - Sep 25.pdf | 12 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Oct - Dec 25.pdf | 12 Jun 2026 |
| Form 2A (FY 2017-2018)File: Form 2A 17-22_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2018-2019)File: Form 2A 17-22_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2019-2020)File: Form 2A 17-22_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2020-2021)File: Form 2A 17-22_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 2026_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2021-2022)File: Form 2A 2026_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2023-2024)File: Form 2A Mar 524_compressed.pdf | 12 Jun 2026 |
| Form 2A (FY 2024-2025)File: Form 2A Mar 25_compressed.pdf | 12 Jun 2026 |
| Withdrawal Update Form 1File: Annexure A Architect Certificate.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: Annexure B Form 2 Engineers Certificate.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form 3 Chartered Accountants Certificate.pdf | 29 May 2026 |
| Form 3File: Form 3 CACertificate Aprl- June 2025.pdf | 7 Mar 2026 |
| Form 2File: Form - 2_ APRIL - JUNE 5-7-2025.pdf | 7 Mar 2026 |
| Form 1File: Form 1 april JUNE.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Financial liabilities.pdf | 7 Mar 2026 |
| Form 1File: Form 1 uly to sept.pdf | 7 Mar 2026 |
| Form 2File: Form - 2_ JULY - SEP 2025 - 6-10-2025.pdf | 7 Mar 2026 |
| Form 3File: Form 3 CA Certificate 02-27-2026 - July-sep 2025.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Bank Certificate FY 18-20.pdf | 7 Mar 2026 |
| Form 1File: Form 1 oct to dec.pdf | 7 Mar 2026 |
| Form 2File: Form - 2_OCT - DEC 2025 - 4-1-2026.pdf | 7 Mar 2026 |
| Form 3File: Form 3 CA Certificate 02-27-2026 -Oct - Dec 2025.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Bank Certificate FY 18-20.pdf | 7 Mar 2026 |
| OthersFile: Respose to RERA - 09 01 2026.pdf | 7 Mar 2026 |
| Form 1File: Form 1 april JUNE.pdf | 7 Mar 2026 |
| Form 2File: Form - 2_ APRIL - JUNE 5-7-2025.pdf | 7 Mar 2026 |
| Form 3File: Form 3 CACertificate Aprl- June 2025.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Bank Certificate FY 18-20.pdf | 7 Mar 2026 |
| Form 1File: Form 1 oct to dec.pdf | 7 Mar 2026 |
| Form 2File: Form - 2_OCT - DEC 2025 - 4-1-2026.pdf | 7 Mar 2026 |
| Form 3File: Form 3 CA Certificate 02-27-2026 -Oct - Dec 2025.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Bank Certificate FY 18-20.pdf | 7 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 oct to dec.pdf | 7 Mar 2026 |
| Withdrawal Update Form 2File: Form - 2_OCT - DEC 2025 - 4-1-2026.pdf | 7 Mar 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 7 Mar 2026 |
| Layout approvalFile: Plan 310717.pdf | 31 Jul 2017 |
| Building plan approvalFile: IOD CC.pdf | 31 Jul 2017 |
| PAN CardFile: PAN Card.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate 310717.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Plan 310717.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: IOD CC.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: IOD CC.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Affidivit Form B.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 310717.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate 310717.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate 310717.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Agreement 310717.pdf | 31 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Heramb Apartments | Plot No B12 Sector 20 Nerul GES Navi Mumbai | 4 | Completed | Mar 2015 | Mar 2015 |
| SINDOORVARAD | Plot No 46 Turbhe GES Navi Mumbai | 7 | Completed | Mar 2010 | Mar 2010 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 62 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GAVANKAR RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near village Walope1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 89 registered projects within 2 km.
Horizon View Exotic
Nasir Abdul Rehaman Khot
ATRIA
Sushant Suresh Chiplunkar
Gold Tower
Salim Haji yusuf Memon
Modern Heights
Modern Construction
FATIMA HEIGHTS
ROZI CONSTRUCTION AND DEVELOPERS
MANNAT TOWER
SHARIF HASAN JAHANGIR DALWAI
See every Ratnagiri project, with the district possession charts
Builder: DATTATRAY SHIVRAM GAVANKAR
DATTATRAY SHIVRAM GAVANKAR has 1 registration on MahaRERA, including GAVANKAR RESIDENCY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if GAVANKAR RESIDENCY is delayed beyond 30 Oct 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GAVANKAR RESIDENCY?
The registered promoter entity is DATTATRAY SHIVRAM GAVANKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GAVANKAR RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GAVANKAR RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GAVANKAR RESIDENCY?
The professionals named in the filing: Architect: MR BHALEKAR; Engineer: Ravindra M Patil; Engineer: Precise Consultants; Chartered Accountant: S GANESH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GAVANKAR RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback