Garden Enclave
RG-MH-20096 · RERA P52100006194 · Last updated on MahaRERA portal: 3 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Completion date moved by 102 months
- 1 extension taken
Clear
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Garden Enclave is a Residential / Group Housing project by REMONESA ENTERPRISES LLP in Pune, Maharashtra, registered with MahaRERA as P52100006194 on 14 Aug 2017. Possession is promised by 30 Jun 2028. The completion date has moved by 102 months from the original filing. 1 of the 44 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameGarden Enclave
- TypeResidential / Group Housing
- Location
- -
- kondhwa khurd
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006194
- ReraGenie IDRG-MH-20096
Builder
- NameREMONESA ENTERPRISES LLP
- Entity typePartnership
- GSTIN27AARFR8423M1ZE
- PartnersSagar Mohan Agarwal, Renuka Mohan Agarwal
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Aug 2017
- Promised completion30 Jun 2028
- Revised completionRevised to 30 Jun 2028 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed30 files
Current status
Figures as on 3 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| H | NA | 12 | 11 | 44 | 0 | 44 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
H: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 5% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed57
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A Desigh Studio |
| Architect | CUBIX ARCHITECTS ASSOCIATES |
| Engineer | JW Consultants LLP |
| Engineer | Imran Khan |
| Chartered Accountant | Bhandari SAAJ & Associates |
| Chartered Accountant | Nandkishor Gudle & Associates |
| Chartered Accountant | Kailash Agarwal & Associates |
| Chartered Accountant | Vinod N Nikam & Co |
| Chartered Accountant | VAMU & ASSOCIATES |
| Partner | Role in project |
|---|---|
| REMONESA ENTERPRISES LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The project stands at 75% completion. 2. The consent of 100% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- a. The delay in completion of the project is primarily due to unforeseen legal complications arising after the project was acquired from M/s. D. S. Kulkarni Developers Limited under a Development Agreement dated 31/03/2017. The project, comprising 44 flats, was subsequently registered with MahaRERA under Registrat
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 857/2018 | CJSD | Awaiting Summons |
| 23/2018 | DISTRICT JUDGE AND ADDL SESSIONS JUDGE PUNE | Closed |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2028
Documents filed30
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Garden Enclave Form 1 Architect Certificate Q1 June 2019.pdf | 3 Jun 2026 |
| Form 2File: Garden Enclave Form 2 Engineer Certificate Q1 June 2019.pdf | 3 Jun 2026 |
| Form 3File: Garden Enclave Form 3 CA Certificate Q1 June 2019.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Green Enclave Disclosure of sold unsold inventory Q1 June 2019.pdf | 3 Jun 2026 |
| Form 1File: Garden Enclave Form 1 Architect Certificate Q2 September 2019.pdf | 3 Jun 2026 |
| Form 2File: Garden Enclave Form 2 Engineer Certificate Q2 September 2019.pdf | 3 Jun 2026 |
| Form 3File: Garden Enclave Form 3 CA Certificate Q2 September 2019.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Green Enclave Disclosure of sold unsold inventory Q2 September 2019.pdf | 3 Jun 2026 |
| Form 1File: Garden Enclave Form 1 Architect Certificate Q3 December 2019.pdf | 3 Jun 2026 |
| Form 2File: Garden Enclave Form 2 Engineer Certificate Q3 December 2019.pdf | 3 Jun 2026 |
| Form 3File: Garden Enclave Form 3 CA Certificate Q3 December 2019.pdf | 3 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Green Enclave Disclosure of sold unsold inventory Q3 December 2019.pdf | 3 Jun 2026 |
| Form 2A (FY 2019-2020)File: Garden Enclave Form 2A Engineer Quality Assurance Certificate FY 2019-2020.pdf | 3 Jun 2026 |
| Form 5 (FY 2019-2020)File: CA Form 5 March 20.pdf | 3 Jun 2026 |
| OtherFile: Letter for Extension.pdf | 8 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Audit_Signed.pdf | 11 Nov 2019 |
| Certificates of CA (Form 5)File: Form 5_Remonesa Enterprises LLP_FY 2017-18.pdf | 15 Oct 2018 |
| Proforma of Allotment letterFile: Garden Enclave Final Agreement 300717.pdf | 30 Jul 2017 |
| Layout approvalFile: DSK Building Plan.pdf | 29 Jul 2017 |
| Building plan approvalFile: DSK Building Plan.pdf | 29 Jul 2017 |
| PAN CardFile: Remonesa Enterprises LLP PAN.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: DSK Title Report.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: DSK Building Plan.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: DSK Building Plan.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: Form B Final_Compressed.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3 Remonesa.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 30 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Garden Enclave on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -13,700+ in Pune
Filed coordinates, straight-line distance. 170 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: REMONESA ENTERPRISES LLP
REMONESA ENTERPRISES LLP has 1 registration on MahaRERA, including Garden Enclave. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Garden Enclave is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Garden Enclave?
The registered promoter entity is REMONESA ENTERPRISES LLP, a partnership as per the filing. Its GSTIN 27AARFR8423M1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Garden Enclave?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Garden Enclave?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Garden Enclave?
The professionals named in the filing: Architect: A Desigh Studio; Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: JW Consultants LLP; Engineer: Imran Khan; Chartered Accountant: Bhandari SAAJ & Associates; Chartered Accountant: Nandkishor Gudle & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Garden Enclave?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback