Red flags

  • Litigation declared, 5 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 6 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2026Possession promisedregistration recorded completed
7 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 98%
0Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

GANGA DHAM TOWER B.. is a Residential / Group Housing project by GOEL GANGA INDIA PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100000212 on 10 Jul 2017. The registration is recorded completed; possession was promised by 30 Apr 2026.

At a glance

Project

  • NameGANGA DHAM TOWER B..
  • TypeResidential / Group Housing
  • Location
    • MARKET YARD GANGA DHAM ROAD
    • BIBVEWADI
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411001
  • Pincode411001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000212
  • ReraGenie IDRG-MH-02347

Builder

  • NameGOEL GANGA INDIA PVT LTD
  • Entity typeCompany
  • DirectorsJAIPRAKASH SITARAM GOEL, Amit Jaiprakash Goel
  • Other registrations23 more →
  • Completed6 of 24
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredJul 2017PromisedApr 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Jul 2017
  • Promised completion30 Apr 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed123 files

Current status

89.7%Work done, per cost certificate

Figures as on 8 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B 1-20 FLOORSNA250000
B 21-27 FLOORSNA70000
B 28-31 FLOORSNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 8 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 98%.

B 1-20 FLOORS96%
ActivityProgress
Excavation100%
Basement (if any)97%
Podiums (if any)98%
Plinth97%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises89%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.81%
B 21-27 FLOORS47%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises87%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.79%
B 28-31 FLOORS37%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.81%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.79%

Progress on shared amenities15

As on 8 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes63%
Water SupplyYes63%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes62%
Landscaping & Tree PlantingYes13%
Street LightingYes37%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes56%
Electrical meter room, sub-station, receiving stationYes48%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed282

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots282
Closed/Covered282
BuildingClosed/CoveredTotal
B 1-20 FLOORS177177
B 21-27 FLOORS6161
B 28-31 FLOORS4444

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,050 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI14234.69
Proposed, not sanctioned10,377 sq m
Buildings approved3
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCAMP PUNE
Estimated costRs 61.35 cr
Cost incurredRs 55.02 cr
Work done89.67%
BuildingWingEstimatedIncurred
B 1-20 FLOORSNARs 39.42 crRs 38.27 cr
B 21-27 FLOORSNARs 10.88 crRs 9.70 cr
B 28-31 FLOORSNARs 8.11 crRs 5.98 cr
-NARs 2.94 crRs 1.07 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpace Designers Syndicate
ArchitectDIRECTIONNEXT DESIGNSTUDIO
EngineerG. A. Bhillare
EngineerIM PATEL
Chartered AccountantA R TATIYA
PartnerRole in project
Legends County Landmark Pvt Ltd-

Litigation declared5

CaseCourtStatus
828/2013CIVIL COURT PUNEPENDING
837/2013HIGH COURT BOMBAYPENDING
911/2018CIVIL MISC APPLICATIONPENDING
710/2019HIGH COURT MUMBAIDISPOSED OFF
32/2020NGTDisposed off

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Feb 2025

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Clarification letter-GDT B.pdf8 Sep 2025
Certificates of CA (Form 3)File: GDT B-March 2025.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B Arch.pdf7 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B -Engg.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B -Quality.pdf3 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B.pdf20 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: GDT-Building B.pdf7 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GDT OC.pdf7 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B -Arch-Dec 2024.pdf3 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B -Engg-Dec 2024.pdf3 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B -Quality-Dec 2024.pdf3 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B -Arch-Sept 202B.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B-Engg-Sept 2024.pdf8 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B-Quality-Sept 2024.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B -Arch-Sept 202B.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B-Engg-Sept 2024.pdf8 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B-Quality-Sept 2024.pdf8 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_march 2024.pdf2 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_June 2024.pdf2 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_march 2024.pdf2 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_June 2024.pdf2 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B_QUALITY_march 2024.pdf2 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B_QUALITY_June 2024.pdf2 Jul 2024
Certificates of CA (Form 3)File: GDT B_form 3 2024.pdf2 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: GDT B_form 5 2024.pdf2 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_June 2024.pdf1 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_June 2024.pdf1 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GDT B_QUALITY_June 2024.pdf1 Jul 2024
Certificates of CA (Form 3)File: GDT B_form 3 2023.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GDT B_FORM 5_2023.pdf1 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GDT B_FORM 5_2023.pdf7 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_30-12-23.pdf30 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_30-12-23.pdf30 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GDT B_QUALITY_30-12-23.pdf30 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_30-9-23.pdf20 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_30-9-23.pdf20 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GDT B_QUALITY_30-9-23.pdf20 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GDT B_QUALITY_30-9-23.pdf20 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_ARCH_30-6-23.pdf19 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_ENGG_30-6-23.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GDT B_QUALITY_30-6-23.pdf19 Jul 2023
Building plan approvalFile: GDT BUILDING PLAN 31 FLOORS_compressed (1).pdf12 Apr 2023
Building Plan Approval (IOD)File: GDT BUILDING PLAN 31 FLOORS_compressed (1).pdf12 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: GDT CC 31 FLOORS.pdf12 Apr 2023
Certificates of CA (Form 3)File: GDT B_FORM 3_2020.pdf6 Apr 2023
Certificates of CA (Form 3)File: GDT B_FORM 3_2021.pdf6 Apr 2023
Certificates of CA (Form 3)File: GDT B_FORM 3_2022.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GDT C_FORM 5_2020.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GDT B_FORM 5_2020.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GDT C_FORM 5_2021.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GDT B_FORM 5_2021.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: GDT B_FORM 5_2022.pdf6 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B_Architect march 2023.pdf4 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B ARCH.pdf4 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B_Engineer march 2023.pdf4 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B ENGG.pdf4 Apr 2023
Form 2AFile: GDT B QUALITY.pdf4 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: GDT B_quality march 2023.pdf4 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B Arch.pdf5 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B ARCH.pdf5 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B ARCH.pdf5 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B ENGG.pdf5 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B ENGG.pdf5 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GDT B ENGG.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GDT B- 2A.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: GDT B 2A.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: GDT B 2A.pdf5 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2019- MARCH ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2019- SEP ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2020- MARCH ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2020- JUNE ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2020- SEP ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2020- DEC ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2021- MARCH ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B 2021- JUNE ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B - FORM 1 SEP 2021 ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B- Form 1 Dec 2021 ARCH.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT A Form 1 -MARCH 2022.pdf22 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GDT B- Architect Certificate 30-06-2022.pdf22 Jan 2023

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
GANGA LEGEND A2 AND B4P52100021020BAVDHAN, Pune272May 2019CompletedDec 2023Dec 2023
GANGA GLITZSurvey No 16 P AND Survey No 17 P Village Undri Taluka Haveli District Pune 411 060192-CompletedApr 2018Apr 2017
GANGA ARCADIASR NO 22 Hissa No 2 Village Kharadi Taluka Haveli District Pune 41101428-CompletedJun 2017Jun 2017
GANGA ARCADIASurvey No. 22 Hissa No 2 situated at Village Kharadi Taluka Haveli District Pune 411 014120-CompletedDec 2015Oct 2015
GANGA SPARSHSurvey No 16Pand 17 P Village Undri Taluka Haveli District Pune154-CompletedApr 2014Nov 2013
AMRUTGANGAVADGAON BK PUNE611-CompletedDec 2013Oct 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGA DHAM TOWER B.. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BIBVEWADI13,700+ in Pune

2 kmGANGA DHAM TOWER B..Completed 36Lapsed / revoked 26Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: GOEL GANGA INDIA PVT LTD

GOEL GANGA INDIA PVT LTD has 24 registrations on MahaRERA, including GANGA GLITZ F. BLDG and GANGA LEGEND A4 AND B1... Its filings disclose 8 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 11 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANGA DHAM TOWER B.. is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGA DHAM TOWER B..?

The registered promoter entity is GOEL GANGA INDIA PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGA DHAM TOWER B..?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANGA DHAM TOWER B..?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGA DHAM TOWER B..?

The professionals named in the filing: Architect: Space Designers Syndicate; Architect: DIRECTIONNEXT DESIGNSTUDIO; Engineer: G. A. Bhillare; Engineer: IM PATEL; Chartered Accountant: A R TATIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGA DHAM TOWER B..?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGA DHAM TOWER B... Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGA DHAM TOWER B.. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.