Home / Browse projects / Pune, Maharashtra / Eternia Phase 2

Registered Litigation declared Residential / Group Housing project

Eternia Phase 2

By VENTURESPRO PROJECTS LLP

RG-MH-13024 · RERA P52100021956 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 60.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 75%
40 of 202Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 287 documents Report an error

Eternia Phase 2 is a Residential / Group Housing project by VENTURESPRO PROJECTS LLP in Pune, Maharashtra, registered with MahaRERA as P52100021956 on 25 Aug 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 162 of the 202 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameEternia Phase 2
  • TypeResidential / Group Housing
  • Location
    • B.T Kawade Road
    • Ghorpodi
    • Ghorpadi
    • Haveli
    • Pune
    • 411001
  • Pincode411001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021956
  • ReraGenie IDRG-MH-13024

Builder

  • NameVENTURESPRO PROJECTS LLP
  • Entity typePartnership
  • GSTIN27AAMFK9255F1ZX
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersRajesh Shriram Dhawan, Dhanesh Dilip Mehta, Ashish Bhawarlal Jain, Bhawarlal Kundanmal Jain, Sunil Puranchand Grover, Manish Dilip Mehta, Dinesh Dilip Mehta
  • Other registrations3 more →
  • Completed1 of 4
  • Past their filed date1
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2019First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Aug 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2025)
  • Buildings2 building records
  • Documents filed287 files

Current status

80%162 of 202 units booked
45.7%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower B upto 1st floorNA51808
Tower B from 2nd floor till 27th floorNA15151940194

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 75%.

Tower B upto 1st floor69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.9%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.9%
Tower B from 2nd floor till 27th floor69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.9%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.9%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes92%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes27%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area13,169 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 60.00 crore
CERSAI search filedYes
Declared on25 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI42557.0
Proposed, not sanctioned24,113 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSOMSHANKAR CHAMBERS,SURVEY NO 46, PLOT - 1, KAKA HALWAI ESTATE, OPP CITY PRIDE, PUNE - SATARA ROAD,PUNE - 411009 MAHARASHTRA 411009
Estimated costRs 125.00 cr
Cost incurredRs 57.11 cr
Work done45.69%
BuildingWingEstimatedIncurred
Tower B from 2nd floor till 27th floorNARs 102.31 crRs 51.69 cr
-NARs 18.75 crRs 3.43 cr
Tower B upto 1st floorNARs 3.94 crRs 1.99 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJay Aeram
ArchitectNM ARCHITECT & INTERIORS
EngineerSatyaprakash Mashalkar
EngineerRavindra Patil
Chartered AccountantPatel and Sharma
Chartered AccountantSBH and Co
Chartered AccountantASAK AND CO
Chartered AccountantAgarwal Sarawgi and associates
PartnerRole in project
VENTURESPRO PROJECTS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25072502195Dec 2025 → Dec 2026

Reason as filed by the promoterSupply chain disruptions and increased lead times for the delivery of essential construction materials, such as cement, steel, and other building components, have caused delays in the construction schedule. The scarcity of these materials in the local market and price volatility have further compounded the problem, leading to intermittent halts in construction activities.

Litigation declared1

CaseCourtStatus
RCS No 3603/2012 PREVIOUSLY SCS NO 288/1998/2013Civil Judge Senior Division PuneFor filling Evidence Affidavit by the plaintitff

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601605Bhavik ShahVENTURESPRO PROJECTS LLP22/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed287

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 287 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf30 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Sign.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 march 26.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 March 26.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 - Eternia Phase 2 Signed.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Eternia Phase 2.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2_Eternia.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 _ Signed.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf7 Nov 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf7 Nov 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf7 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf31 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf31 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf31 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf31 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf31 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf31 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf30 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf30 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf30 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf30 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf30 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf30 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf30 Oct 2025
Withdrawal Update Form 2File: Eternia Phase 2 - Form 2.pdf30 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf30 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf30 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf30 Oct 2025
Withdrawal Update Form 3File: new-Eternia Phse 2 - Form 3 _organized.pdf30 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 1File: 01 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf28 Oct 2025
Form 2File: 02 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf28 Oct 2025
Form 3File: 03 Certificates of CA (Form 3).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Form 2A (FY 2019-2020)File: Form 2A-2019-2020.pdf4 Oct 2025
Form 2A (FY 2025-2026)File: Eternia Phase 2 - Form 2A-2024-25.pdf4 Oct 2025
Form 5 (FY 2024-2025)File: Form 05- Eternia Phae II -Final.pdf1 Oct 2025
Form 2A (FY 2024-2025)File: Eternia Phase 2 - Form 2A.pdf5 Aug 2025
Form 1File: Form 1 - Eternia Phase 2 -.pdf23 Jul 2025
Form 2File: Eternia Phase 2 - Form 2.pdf23 Jul 2025
Form 3File: Eternia Phase 2 - Form 3 -.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Eternia Phase 2 - Sold - Unsold -.pdf23 Jul 2025
Form 1File: 16 Certificates of Architect (Form 1).pdf23 Jul 2025
Form 2File: 02 Form 2 Eternia Phase 2 - March 2024.pdf23 Jul 2025
Form 3File: Form 3 - Eternia Phase 2 Signed.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold - Unsold - Eternia Phase 2.pdf23 Jul 2025
Form 3File: Form 3 ready.pdf23 Jul 2025
Form 2File: Eternia Phase 2 Form 2 - 31-12-2024.pdf23 Jul 2025
Form 1File: Form 01.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Dis closure of sold unsold.pdf23 Jul 2025
Form 1File: 02 Jun 21.pdf23 Jul 2025
Form 2File: 01 Sept 21.pdf23 Jul 2025
Form 3File: 01 Jun 21.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: 00 Jun 21.pdf23 Jul 2025
Form 1File: 03 sept 21.pdf23 Jul 2025
Form 2File: 01 Sept 21.pdf23 Jul 2025

How this compares with Pune

80%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Eternia Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghorpodi13,700+ in Pune

2 kmEternia Phase 2Completed 21Lapsed / revoked 8Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: VENTURESPRO PROJECTS LLP

VENTURESPRO PROJECTS LLP has 4 registrations on MahaRERA, including Eternia Phase 1 and Eternia Phase 2. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Eternia Phase 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Eternia Phase 2?

The registered promoter entity is VENTURESPRO PROJECTS LLP, a partnership as per the filing. Its GSTIN 27AAMFK9255F1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Eternia Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Eternia Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Eternia Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Eternia Phase 2?

The professionals named in the filing: Architect: Jay Aeram; Architect: NM ARCHITECT & INTERIORS; Engineer: Satyaprakash Mashalkar; Engineer: Ravindra Patil; Chartered Accountant: Patel and Sharma; Chartered Accountant: SBH and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Eternia Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Eternia Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Eternia Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.