Home / Browse projects / Pune, Maharashtra / BOULEVARD TOWER A2

Registered No litigation declared Commercial project

BOULEVARD TOWER A2

By Bramhacorp Limited

RG-MH-59145 · RERA P52100051975 · Last updated on MahaRERA portal: 20 Jan 2026

Source: official MahaRERA filing

Red flags

  • Rs 275.00 crore secured on the land, in favour of INDUSIND BANK LTD

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 98%
150 of 237Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

BOULEVARD TOWER A2 is a Commercial project by Bramhacorp Limited in Pune, Maharashtra, registered with MahaRERA as P52100051975 on 13 Jul 2023. Possession is promised by 31 Dec 2026. 87 of the 237 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameBOULEVARD TOWER A2
  • TypeCommercial
  • Location
    • CONNOUGHT ROAD
    • PUNE STATION
    • Ghorpadi
    • Haveli
    • Pune
    • 411001
  • Pincode411001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051975
  • ReraGenie IDRG-MH-59145

Builder

  • NameBramhacorp Limited
  • Entity typeCompany
  • CINU70101PN2012PLC142705
  • GSTIN27AAFCB0273N1ZI
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Other registrations25 more →
  • Completed8 of 26
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Jul 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed113 files

Current status

37%87 of 237 units booked
58.9%Work done, per cost certificate

Figures as on 20 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A2NA22170237237

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 98%.

TOWER A2: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed237

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots237
Closed/Covered237

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,543 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofINDUSIND BANK LTD
Secured amountRs 275.00 crore
CERSAI search filedYes
Declared on28 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI19555.0
Proposed, not sanctioned10,907 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE
Estimated costRs 59.31 cr
Cost incurredRs 34.92 cr
Work done58.88%
BuildingWingEstimatedIncurred
TOWER A2NARs 55.94 crRs 32.14 cr
-NARs 3.37 crRs 2.78 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPadmakar Kole
ArchitectImran Shaikh
ArchitectSACHIN SHAH
EngineerDattatray Gaikwad
EngineerPANKAJKUMAR A SOMVANSHI
Chartered AccountantF A A & ASSOCIATES LLP
Chartered AccountantS D Kharadkar & Associates
PartnerRole in project
Bramhacorp Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Dec 25_ Boulevard A2.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2_Dec 25_ Boulevard A2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3_Dec 25_ Boulevard A2.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1_Sep 25_Boulevard A2.pdf24 Oct 2025
Withdrawal Update Form 2File: Form 2_Sep 25_Boulevard A2.pdf24 Oct 2025
Withdrawal Update Form 3File: Form 3_Sep 25_Boulevard A2.pdf24 Oct 2025
Form 5 (FY 2024-2025)File: Form 5_FY 2024-25_Boulevard A2.pdf30 Sep 2025
Withdrawal Update Form 1File: Form 1_June 25_Boulevard A2.pdf26 Aug 2025
Withdrawal Update Form 1File: Form 1_June 25_Boulevard A2.pdf26 Aug 2025
Withdrawal Update Form 2File: Form 2_June 25_Boulevard A2.pdf26 Aug 2025
Withdrawal Update Form 2File: Form 2_June 25_Boulevard A2.pdf26 Aug 2025
Withdrawal Update Form 3File: Form 3_June 25_Boulevard A2.pdf26 Aug 2025
Withdrawal Update Form 3File: Form 3_June 25_Boulevard A2.pdf26 Aug 2025
Form 2A (FY 2024-2025)File: Boulevard Tower A2.pdf30 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Mar 25_Boulevard A2.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold_Mar 25_Boulevard A2.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Mar 25_Boulevard A2.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Mar 25_Boulevard A2.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 24_Boulevard A2.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Boulevard A2.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 24_Boulevard A2.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dec 24_Boulevard A2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Boulevard A2.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Boulevard A2.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 24_Boulevard A2.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Sep 24_Boulevard A2.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_2023-24_Boulevard A2.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 24_B Tower A2.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Jun 24_Boulevard Tower A2.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: BOULEVARD TOWER A2.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Jun 24_Boulevard Tower A2.pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Jun 24_B Tower A2.pdf13 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Mar 24_Tower A2.pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: Boulevard Tower A2.pdf27 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Mar 24_Tower A2.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Mar 24_Tower A2.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1_Mar 24_Tower A2.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Mar 24_Tower A2.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dec 23_Boulevard A2_.pdf31 Jan 2024
Building plan approvalFile: Sheet 18 - 14_15th Refuge Floor Plan_compressed.pdf23 Jan 2024
Building plan approvalFile: Sheet 19 - 18_19th Floor Plan_compressed.pdf23 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet 18 - 14_15th Refuge Floor Plan_compressed.pdf23 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet 19 - 18_19th Floor Plan_compressed.pdf23 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: BOULEVARD TOWER A2_.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 23_Boulevard A2.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 23_Boulevard A2.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1_Dec 23_Boulevard A2.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Dec 23_Boulevard A2.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: BOULEVARD TOWER A2 (2).pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Boulevard Tower A2_Sep 23.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1_Boulevard Tower A2_Sep 23.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Boulevard Tower A2_Sep 23.pdf18 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Boulevard Tower A2_Sep 23.pdf18 Oct 2023
Other - TechnicalFile: Clarification of Built Up Area.pdf24 Jun 2023
Layout approvalFile: Sheet - 1.pdf22 Jun 2023
Layout approvalFile: Sheet 2 - Basement.pdf22 Jun 2023
Layout approvalFile: Sheet 3 - Basement.pdf22 Jun 2023
Layout approvalFile: Sheet 4 - Lower Ground Parking.pdf22 Jun 2023
Layout approvalFile: Sheet 5 - Lower 2nd Parking.pdf22 Jun 2023
Layout approvalFile: Sheet 6 - Section and Elevation.pdf22 Jun 2023
Layout approvalFile: Sheet 7 - Section and Elevation.pdf22 Jun 2023
Building plan approvalFile: Sheet - 1.pdf22 Jun 2023
Building plan approvalFile: Sheet - 3.pdf22 Jun 2023
Building plan approvalFile: Sheet - 5.pdf22 Jun 2023
Building plan approvalFile: Sheet - 7.pdf22 Jun 2023
Building plan approvalFile: Sheet - 8.pdf22 Jun 2023
Building plan approvalFile: Sheet - 12.pdf22 Jun 2023
Building plan approvalFile: Sheet - 13.pdf22 Jun 2023
Building plan approvalFile: Sheet - 14.pdf22 Jun 2023
Building plan approvalFile: Sheet - 15.pdf22 Jun 2023
Building plan approvalFile: Sheet - 16.pdf22 Jun 2023
Building plan approvalFile: Sheet - 17.pdf22 Jun 2023
Building plan approvalFile: Sheet - 18.pdf22 Jun 2023
Building plan approvalFile: Sheet-23.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Sheet - 1.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Sheet 2 - Basement.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Sheet 3 - Basement.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Sheet 4 - Lower Ground Parking.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Sheet 5 - Lower 2nd Parking.pdf22 Jun 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Bramha Exuberance CP52100001076KONDHWA, Pune-Jul 2017CompletedDec 2021Jan 2019
Bramha Vantage A / BSurvey No 6 Hissa No 10 1B Bavdhan Khurd Taluka Mulshi District Pune51-CompletedAug 2017Apr 2017
Bramha BaugSurvey No 55B Hissa No 1A 2B at Village Ghorpadi Taluka Haveli District Pune8-CompletedJan 2017Late, Feb 2017
Bramha Suncity PlatinumS No 7 Hissa No 1 to 5 S No 8 Hissa No 1 1 2 S No 38A Hissa No 1B 1 S No 38A Hissa No 1A S No 38B Village Wadgaon Sheri Pune134-CompletedSep 2014Sep 2014

How this compares with Pune

37%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BOULEVARD TOWER A2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE STATION13,700+ in Pune

2 kmBOULEVARD TOWER A2Completed 16Lapsed / revoked 31Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 91 registered projects within 2 km.

Builder: Bramhacorp Limited

Bramhacorp Limited has 26 registrations on MahaRERA, including Bramha Exuberance C and F RESIDENCES T5 T6 and T7. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if BOULEVARD TOWER A2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BOULEVARD TOWER A2?

The registered promoter entity is Bramhacorp Limited, a company as per the filing. Its CIN U70101PN2012PLC142705 and GSTIN 27AAFCB0273N1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BOULEVARD TOWER A2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BOULEVARD TOWER A2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BOULEVARD TOWER A2?

The professionals named in the filing: Architect: Padmakar Kole; Architect: Imran Shaikh; Architect: SACHIN SHAH; Engineer: Dattatray Gaikwad; Engineer: PANKAJKUMAR A SOMVANSHI; Chartered Accountant: F A A & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BOULEVARD TOWER A2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BOULEVARD TOWER A2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BOULEVARD TOWER A2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.