GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.
RG-MH-73600 · RERA P52100053857 · Last updated on MahaRERA portal: 21 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD. is a Others project by D & T PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100053857 on 5 Dec 2023. Possession is promised by 31 Dec 2027.
At a glance
Project
- NameGANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.
- TypeOthers
- Location
- BADHAI SWEET
- KOTHRUD
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100053857
- ReraGenie IDRG-MH-73600
Builder
- NameD & T PROPERTIES
- Entity typePartnership
- PartnersANSHU NANAKCHAND WADHWANI, ABHISHEK PRASAD DESHPANDE, PRASAD GIRIDHAR DESHPANDE, KARAN DEEPAK TAMBE, VINAYKUMAR SUDHAKAR DESHPANDE
- Other registrations7 more →
- Completed2 of 8
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Dec 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed96 files
Current status
Figures as on 21 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD: 29% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 33% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. | Kothrud | Pune |
| SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD. | Kothrud | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD | NA | Rs 52.02 cr | Rs 20.78 cr |
| - | NA | Rs 19.25 cr | Rs 5.53 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR RUPESH JAMKHINDIKAR Kishor Jamkhindikar |
| Engineer | AJAY BHILARY AND ASSOCIATES |
| Engineer | Karan Dipak Tambe |
| Chartered Accountant | MGSP |
| Partner | Role in project |
|---|---|
| D & T PROPERTIES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Jun 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Ganeshbaug 31122025.pdf | 21 May 2026 |
| Withdrawal Update Form 2File: GB Form 2 - 31122025.pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 30092025 GB.PDF | 21 May 2026 |
| Withdrawal Update Form 1File: Ganeshbaug Form 1.PDF | 15 Jan 2026 |
| Withdrawal Update Form 1File: Ganeshbaug Form 1.PDF | 15 Jan 2026 |
| Withdrawal Update Form 1File: GB Form 1 30092025.PDF | 15 Jan 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 15 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 GaneshBaug 30062025.PDF | 15 Jan 2026 |
| Withdrawal Update Form 2File: GB Form 2 30092025.PDF | 15 Jan 2026 |
| Withdrawal Update Form 3File: CA cert.pdf | 15 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 30062025 GB.PDF | 15 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 30092025 GB.PDF | 15 Jan 2026 |
| Form 1File: Form 1 31122023.PDF | 2 Jan 2026 |
| Form 2File: Form 2 Certificate 31122023.pdf | 2 Jan 2026 |
| Form 3File: Form 3 31122023.pdf | 2 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE 31122023.PDF | 2 Jan 2026 |
| Layout approvalFile: Sanction Plan SH1 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH2 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH3 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH4 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH5 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH6 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH7 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH8 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH9 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH10 19062025.pdf | 23 Jun 2025 |
| Building plan approvalFile: Sanction Plan SH11 19062025.pdf | 23 Jun 2025 |
| Building plan approval or NA orderFile: CC 19062025.pdf | 23 Jun 2025 |
| Form 1File: Form 1 31032024 GB.PDF | 13 Jun 2025 |
| Form 2File: Form 2 31032024.pdf | 13 Jun 2025 |
| Form 3File: Form 3 31032024.PDF | 13 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD 31032024.PDF | 13 Jun 2025 |
| Form 1File: Form 1 30092024.pdf | 13 Jun 2025 |
| Form 2File: Form 2 30092024.pdf | 13 Jun 2025 |
| Form 3File: Form 3 30092024 GB.PDF | 13 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF INVENTORY GB 30092024.PDF | 13 Jun 2025 |
| Form 1File: Form I- 31032025.pdf | 11 Jun 2025 |
| Form 2File: Form 2 31032025.PDF | 11 Jun 2025 |
| Form 3File: Form 3 31032025.pdf | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE 31032025.PDF | 11 Jun 2025 |
| Form 1File: Form 1 31122024.pdf | 11 Jun 2025 |
| Form 2File: Form 2 31122024.pdf | 11 Jun 2025 |
| Form 3File: Form 3 31122024.pdf | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF INVENTORY GB 31122024.PDF | 11 Jun 2025 |
| Form 1File: Form 1 30062024.pdf | 11 Jun 2025 |
| Form 2File: Form 2 30062024.pdf | 11 Jun 2025 |
| Form 3File: Form 3 June 30 2024.PDF | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF INVENTORY GB 30062024.PDF | 11 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: GB Encumbrances.pdf | 8 Feb 2025 |
| Details of encumbrances concerned to LegalFile: GB Encumbrances.pdf | 8 Feb 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: GB -Format B.pdf | 8 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: GB Secured Unsecured Finance.pdf | 8 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KH ENGG CERTIFICATE 30092024.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form I- 100524.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 - 30062024.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032024.PDF | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 30 2024.PDF | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ganesh Baugh-Engineer's Certificate.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ganeshbaug Engg Certificate Jun 2024.pdf | 15 Oct 2024 |
| Proforma of Agreement for saleFile: Ganeshbaug Aggreement.pdf | 1 Nov 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviations sheet.pdf | 1 Nov 2023 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 25 Oct 2023 |
| Declaration in FORM BFile: Ganeshbaug (1).pdf | 25 Oct 2023 |
| CERSAI detailsFile: CERSAI (2).pdf | 25 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Certificate.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cert.pdf | 12 Oct 2023 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 12 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details (1).pdf | 12 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Allotment letter Deviation letter.pdf | 12 Oct 2023 |
| Layout approvalFile: PLAN 01.pdf | 9 Oct 2023 |
| Building plan approvalFile: PLAN 02.pdf | 9 Oct 2023 |
| Building plan approvalFile: PLAN 03.pdf | 9 Oct 2023 |
| Building plan approvalFile: PLAN 04.pdf | 9 Oct 2023 |
| PAN CardFile: D and T properties Pan Card 080422.pdf | 9 Oct 2023 |
| Copy of the legal title reportFile: Title Report Dated 21082023.pdf | 9 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrances.pdf | 9 Oct 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrances.pdf | 9 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KOTHRUD13,700+ in Pune
Filed coordinates, straight-line distance. 311 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: D & T PROPERTIES
D & T PROPERTIES has 8 registrations on MahaRERA, including GAYTRI APARTMENT and GEETANJALI NAMANA APARTMENT. Its filings disclose 6 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD. is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.?
The registered promoter entity is D & T PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.?
The professionals named in the filing: Architect: AR RUPESH JAMKHINDIKAR Kishor Jamkhindikar; Engineer: AJAY BHILARY AND ASSOCIATES; Engineer: Karan Dipak Tambe; Chartered Accountant: MGSP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback