D & T PROPERTIES: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

D & T PROPERTIES has 8 registrations in this build, including GAYTRI APARTMENT and GEETANJALI NAMANA APARTMENT. Its filings disclose 6 earlier MahaRERA projects: 2 of 4 past projects completed on time.

8Registrations in this build
6Past projects disclosed
+12 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
GAYTRI APARTMENTPune, Maharashtra--Completed
GEETANJALI NAMANA APARTMENTPune, Maharashtra--Completed
Rajkamal Park Co-Op Housing Society LtdPune, Maharashtra--Registration lapsed
MOUNTAIN VIEW CO-OPRATIVE HOUSING SOCIETYPune, Maharashtra--Registered
PRATHAMESH CO-OPRATIVE HOUSING SOCIETY LIMITEDPune, Maharashtra--Registered
GANESHBAUG CO-OPERATIVE HOUSING SOCIETY LTD. AND SUCHITRA TERRACE CO-OPERATIVE HOUSING SOCIETY LTD.Pune, Maharashtra--Registered
KADAM HERITAGE SURVEY NO.4/7/1 AND 4/7/2Pune, Maharashtra16354%Registered
MEDHAPune, Maharashtra140%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
GAYTRI APRTMENT
27 Jul 20181 Oct 2020+26 months
GAYATRI APARTMENT
1 Apr 202011 Feb 2020On time
Gayatri Apartment
1 Apr 202011 Feb 2020On time
GEETANJALI NAMANA APARTMENT
7 Sep 202030 Jun 2023+34 months
MOUNTAIN VIEW CO-OPRATIVE HOUSING SOCIETY
P52100046991
31 Dec 2026Not completed yetOngoing
PRATHAMESH CO-OPRATIVE HOUSING SOCIETY LIMITED
P52100053715
31 Dec 2026Not completed yetOngoing

Frequently asked questions

How do I verify D & T PROPERTIES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with D & T PROPERTIES?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.