Gagan Aviva
RG-MH-47319 · RERA P52100018060 · Last updated on MahaRERA portal: 24 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 14 months past the filed date
- 15 complaints at MahaRERA
- Completion date moved by 36 months
- 4 extensions taken
- Rs 3.00 crore secured on the land, in favour of ABHIYAN MERCHANTTS PRIVATE LIMITED
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gagan Aviva is a Others project by Gagan Landmarks LLP in Pune, Maharashtra, registered with MahaRERA as P52100018060 on 10 Oct 2018. Possession was promised by 28 Aug 2025 and is now 14 months past that date. The completion date has moved by 36 months from the original filing. 151 of the 163 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 15 complaints are on record with the regulator.
At a glance
Project
- NameGagan Aviva
- TypeOthers
- Location
- Wagholi Kesnand road
- Kesnand
- Haveli
- Pune
- 412207
- Pincode412207
- RERA no.P52100018060
- ReraGenie IDRG-MH-47319
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Oct 2018
- Promised completion28 Aug 2025
- Revised completionRevised to 28 Aug 2025 (originally 28 Aug 2022)
- Buildings2 building records
- Documents filed157 files
Current status
Figures as on 24 Nov 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| wing A | NA | 15 | 13 | 76 | 6 | 82 |
| wing B | NA | 15 | 0 | 76 | 5 | 81 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.
wing A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
wing B80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Progress on shared amenities15
As on 24 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 78% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 35% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 70% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed24
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| wing A | 23 | 23 |
| wing B | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| M/s Avalon Developers | Pune (CB) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| wing A | NA | Rs 9.54 cr | Rs 8.74 cr |
| wing B | NA | Rs 9.54 cr | Rs 8.69 cr |
| - | NA | Rs 2.75 cr | Rs 2.72 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | R R Malwadkar |
| Architect | Jay Aeram and Associates |
| Architect | Malwadkar Architects Pvt. Ltd. |
| Engineer | Design Werkz Engineering Private Limited |
| Engineer | Ranjit Yadav |
| Chartered Accountant | K G Jhamvar & Co |
| Chartered Accountant | K.G. Jhamvar & Co. |
| Chartered Accountant | Birla & Company |
| Partner | Role in project |
|---|---|
| Gagan Landmarks LLP | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have completed more than 90% of the project and balance work pertaining to fitting and finishing and obtaining occupancy certificate is pending. The delay was on account of delay in obtaining approvals from various authorities during COVID period resulting in cascading effect of delays. We have employed additional employees to complete the project before the new extended date of completion.
Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN AVIVA” under implementation by us on land out of Gat No 94/1A/4, 94/1A/5 and 94/1A/6 situate, Village Kesnand within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100018060 dated 10/10/2010. 2) In anticipation that we would complete the said Project on or before 28/08/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 28/08/2023. However, due to unfore
Reason as filed by the promoter1) We are the Promoters of the Real Estate Project known as “GAGAN AVIVA” under implementation by us on land out of at Gat No. 94/1A/4/5/6/ Plot no 1,2,3,4 Village Kesnand within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100018060 dated 10/10/2018. 2) In anticipation that we would complete the said Project on or before 28/08/2022, in our Application to you for Registration of our Project, we had mentioned the date of Completion as 28/08/2022. However, due to the current
Reason as filed by the promoter1. As per the latest QPR the Construction of the project GAGAN AVIVA is approximately 90% completed. 2. The proposed completion date for the project was 28/08/2022 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.
Complaints filed with MahaRERA15
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000340794 | DADA GANGADHAR TIKHOLE | GAGAN LANDMARKS LLP | 18/04/2024 |
| CC005000000471365 | NOEL LAWRENCE BORDE | GAGAN LANDMARKS LLP | 23/07/2024 |
| CC12500648 | NEERAJ GHOSHAL | Gagan Landmarks LLP | 24/02/2025 |
| CC12501263 | Avery Bhattacharya | Gagan Landmarks LLP | 16/04/2025 |
| CC12501693 | Namrata Ishwar Gururfale | Gagan Landmarks LLP | 25/05/2025 |
| CC12503236 | Aniket Ashok Deshpande | Gagan Landmarks LLP | 12/09/2025 |
| CC12503398 | Abhijeet Balasaheb Deshpande | Gagan Landmarks LLP | 23/09/2025 |
| CC12503451 | Aditi Rajesh Kumar Sharma | Gagan Landmarks LLP | 27/09/2025 |
| CC12503577 | Prakash Shashikant Pathak | Gagan Landmarks LLP | 08/10/2025 |
| CC12503753 | Sanjay Kumar Chowbey | Gagan Landmarks LLP | 27/10/2025 |
| CC12503806 | KARTAR SINGH THAKUR | Gagan Landmarks LLP | 31/10/2025 |
| CC12504255 | ANUVINDER RANJIT SINGH | Gagan Landmarks LLP | 02/12/2025 |
| CC12600764 | Sunil Devidas Pahurkar | Gagan Landmarks LLP | 10/02/2026 |
| CC12600749 | SUMEET DEVIDAS PAHURKAR | Gagan Landmarks LLP | 09/02/2026 |
| CC12603021 | Vishal Gangadharan Nair | Gagan Landmarks LLP | 21/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Sep 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Sep 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed157
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 157 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 24 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 24 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 24 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Aug 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 19 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 30 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 30 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 18 Jan 2025 |
| PAN CardFile: PAN CARD .pdf | 9 Jan 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A_ gagan aviva.pdf | 9 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Rohit Garg (2).pdf | 9 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest Rahul garg.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_0001 gagan aviva.pdf | 9 Jan 2025 |
| Declaration in FORM BFile: FORM B AVIVA (1).pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Book AVIVA 30 09 2024.pdf | 29 Nov 2024 |
| Declaration in FORM BFile: Form B_0001.pdf | 26 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aviva Form 5.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Booked Inventory (1).pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 7 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1.pdf | 7 Oct 2024 |
| Declaration in FORM BFile: Form B.pdf | 11 Mar 2024 |
| Declaration about Commencement CertificateFile: decl of cc.pdf | 5 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 5 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 5 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 5 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023.pdf | 5 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sales.pdf | 5 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Book Inventory.pdf | 19 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 22 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 22 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 22 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Gagan Aviva.pdf | 22 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 17 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 17 Aug 2023 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 17 Aug 2023 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 9 Jun 2023 |
| Declaration in FORM BFile: Form B.pdf | 9 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sold booked inventory.pdf | 2 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 9 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 30 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 30 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019.pdf | 17 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 16 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 16 Dec 2022 |
| Certificates of CA (Form 3)File: Form 3.pdf | 16 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Gagan Aviva.pdf | 6 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 11 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Achitect Certificate.pdf | 11 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 11 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Achitect Certificate.pdf | 11 Oct 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Gagan Ela | S no 23 mohhamedwadi Pune 411048 | 227 | Completed | Dec 2020 | Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 157 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Gagan Aviva on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kesnand13,700+ in Pune
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: Gagan Landmarks LLP
Gagan Landmarks LLP has 3 registrations on MahaRERA, including Gagan Ela and Gagan Aviva. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Gagan Aviva shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Gagan Aviva is delayed beyond 28 Aug 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gagan Aviva?
The registered promoter entity is Gagan Landmarks LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gagan Aviva?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Gagan Aviva?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Gagan Aviva?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gagan Aviva?
The professionals named in the filing: Architect: R R Malwadkar; Architect: Jay Aeram and Associates; Architect: Malwadkar Architects Pvt. Ltd.; Engineer: Design Werkz Engineering Private Limited; Engineer: Ranjit Yadav; Chartered Accountant: K G Jhamvar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gagan Aviva?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.