ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / FORTUNE SKYLINE

Registered No litigation declared Others project

FORTUNE SKYLINE

By SRIJAY BUILDERS

RG-MH-19096 · RERA P51500078137 · Last updated on MahaRERA portal: 7 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Stilt Floor, 50%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

FORTUNE SKYLINE is a Others project by SRIJAY BUILDERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500078137 on 25 Nov 2024. Possession is promised by 30 Dec 2029.

At a glance

Project

  • NameFORTUNE SKYLINE
  • TypeOthers
  • Location
    • PAITHAN ROAD
    • ITKHEDA
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500078137
  • ReraGenie IDRG-MH-19096

Builder

  • NameSRIJAY BUILDERS
  • Entity typePartnership
  • PartnerSAGAR SHANKARSINGH THAKUR

Key dates

this monthRegisteredNov 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Nov 2024
  • Promised completion30 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FORTUNE SKYLINENA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.

FORTUNE SKYLINE: 34% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed132

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots132
Closed/Covered38
Open Space94

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,337 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
JAY CONSTRUCTIONAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityChhatrapati Sambhajinagar Municipal Corportion, Chhatrapati Sambhajinagar
Permissible FSI7009.47
Proposed, not sanctioned3,509 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGHAI CHAMBERS PLOT NO 20 CIDCO TOWN CENTRE JALNA ROAD AURANGABAD 431003

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SRIJAY BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2029

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form-1 March 25.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CA Fortune Skyline (Modified).pdf7 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form-2 March 25.pdf7 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 18-01-25.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Declaration 18-01-25.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 18-01-25.pdf12 Feb 2025
Other - FinanceFile: Fortune Skyline Cost 11-11-24.pdf11 Nov 2024
Other - FinanceFile: Srijay Area Declaration.pdf29 Oct 2024
Other - TechnicalFile: Srijay Area Declaration.pdf29 Oct 2024
Other - TechnicalFile: CC VERIFICATION MAIL.pdf11 Oct 2024
Building plan approvalFile: DWG 3 of 3 - Building Plan 2_compressed.pdf13 Aug 2024
Building plan approvalFile: DWG 2 of 3 - Building Plan_compressed.pdf13 Aug 2024
Layout approvalFile: DWG 1 of 3 - Layout_compressed.pdf13 Aug 2024
Layout approvalFile: Amalgamation Plan.pdf13 Aug 2024
PAN CardFile: srijay Pan .pdf13 Aug 2024
Copy of the legal title reportFile: Fortune Search Report.pdf13 Aug 2024
Details of encumbrances concerned to FinanceFile: NO ENC Legal And Finance.pdf13 Aug 2024
Copy of Layout Approval (in case of layout)File: Amalgamation Plan.pdf13 Aug 2024
Copy of Layout Approval (in case of layout)File: DWG 1 of 3 - Layout_compressed.pdf13 Aug 2024
Proforma of Allotment letterFile: SRIJAY MODIFIED ALLOT LETTER.pdf13 Aug 2024
Declaration in FORM BFile: Shrijay Builders Form-B.pdf13 Aug 2024
Declaration in FORM BFile: Jay Construction Form-B.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Fortune Skyline Form-1 .pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 With Declaration.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Fortune Skyline Form-2 10-Aug-24.pdf13 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: CSMC - CC.pdf13 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Amalgamation Order.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: DWG 2 of 3 - Building Plan_compressed.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: DWG 3 of 3 - Building Plan 2_compressed.pdf13 Aug 2024
Other - LegalFile: Srijay - Partnership Deed_compressed.pdf13 Aug 2024
Other - LegalFile: Jay Constructions Revised Partnership Deed.pdf13 Aug 2024
Declaration about Commencement CertificateFile: Format D.pdf13 Aug 2024
CERSAI detailsFile: CERSAI Declaration.pdf13 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Shrijay Builders Format-A.pdf13 Aug 2024
Deviation Report with respect to Allotment letterFile: No Deviation - Allotment.pdf13 Aug 2024
Details of encumbrances concerned to LegalFile: NO ENC Legal And Finance.pdf13 Aug 2024
Other - FinanceFile: 1 Other - Technical.pdf13 Aug 2024
Other - FinanceFile: 1 Other - Legal.pdf13 Aug 2024
Other - TechnicalFile: Annexure A Technical.pdf13 Aug 2024
Other - TechnicalFile: Amenities Declaration Annexure-1.pdf13 Aug 2024
Other - TechnicalFile: Fortune Joint Declaration.pdf13 Aug 2024
Deviation Report with respect to model copy of AgreementFile: No Deviataion - Agreement.pdf13 Aug 2024
Proforma of Agreement for saleFile: Agreement with Amenities.pdf13 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disc of Int - Vishal Shikhare.pdf13 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disc of Int - Sagar Thakur.pdf13 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disc of Int - Ajay Patil.pdf13 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disc of Int - Shamsing Dedwal.pdf13 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disc of Int - Sonia Pathania.pdf13 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Shrijay Builders Format-B.pdf13 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Fortune Skyline Finance Availed .pdf13 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Fortune Skyline Finance Availed 13-Aug-24.pdf13 Aug 2024

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep FORTUNE SKYLINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ITKHEDA1,400+ in Aurangabad

2 kmFORTUNE SKYLINECompleted 16Lapsed / revoked 10Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: SRIJAY BUILDERS

SRIJAY BUILDERS has 1 registration on MahaRERA, including FORTUNE SKYLINE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if FORTUNE SKYLINE is delayed beyond 30 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FORTUNE SKYLINE?

The registered promoter entity is SRIJAY BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FORTUNE SKYLINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for FORTUNE SKYLINE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in FORTUNE SKYLINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FORTUNE SKYLINE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FORTUNE SKYLINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.