Home / Browse projects / Pune, Maharashtra / Foresta Phase II

Registered No litigation declared Residential / Group Housing project

Foresta Phase II

By High Yield Fortune Pvt Ltd

RG-MH-39004 · RERA P52100046937 · Last updated on MahaRERA portal: 18 Aug 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 21 months
  • 2 extensions taken
  • Rs 8.00 crore secured on the land, in favour of Aditya Birla Finance Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
55 of 55Construction stages doneacross 5 buildings; every applicable stage filed complete
1 of 32Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 231 documents Report an error

Foresta Phase II is a Residential / Group Housing project by High Yield Fortune Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100046937 on 20 Sep 2022. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 21 months from the original filing. 31 of the 32 units on this registration are recorded sold or booked, and 55 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameForesta Phase II
  • TypeResidential / Group Housing
  • Location
    • PAUD BHADAS ROAD
    • Near Mahindra International College
    • Ravade
    • Mulshi
    • Pune
    • 412108
  • Pincode412108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046937
  • ReraGenie IDRG-MH-39004

Builder

  • NameHigh Yield Fortune Pvt Ltd
  • Entity typeCompany
  • CINU45401PN2020PTC192582
  • DirectorsVishal Vilas Chavan, Jyotiprasad Vilas Chavan, Rupesh Vilas Chavan, Mugdha Rupesh Chavan
  • Other registrations2 more →
  • Past their filed date1
  • Declared earlier projects10 →

Key dates

2 months past promisethis monthRegisteredSep 2022First promiseNov 2024Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Sep 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 30 Nov 2024)
  • Buildings5 building records
  • Documents filed231 files

Current status

97%31 of 32 units booked
112.1%Work done, per cost certificate

Figures as on 18 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG - 02 - ANA22404
BLDG - 02 - BNA22404
BLDG - 02 - CNA22404
BLDG - 02 - DNA22404
BLDG - 01 - ENA2216016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

55 of 55 construction stages are filed complete across 5 buildings.

BLDG - 02 - A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLDG - 02 - B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLDG - 02 - C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLDG - 02 - D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BLDG - 01 - E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Open Space25
BuildingOpen SpaceTotal
BLDG - 02 - A55
BLDG - 02 - B55
BLDG - 02 - C55
BLDG - 02 - D55
BLDG - 01 - E55

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,624 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Limited
Secured amountRs 8.00 crore
CERSAI search filedYes
Declared on15 May 2025

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority
Permissible FSI1461.42
Proposed, not sanctioned1,461 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFatimanagar,Wanowrie,Pune-411040
Estimated costRs 9.95 cr
Cost incurredRs 11.16 cr
Work done112.11%
BuildingWingEstimatedIncurred
BLDG - 01 - ENARs 4.32 crRs 5.02 cr
-NARs 1.31 crRs 1.43 cr
BLDG - 02 - ANARs 1.08 crRs 1.36 cr
BLDG - 02 - BNARs 1.08 crRs 1.12 cr
BLDG - 02 - CNARs 1.08 crRs 1.12 cr
BLDG - 02 - DNARs 1.08 crRs 1.12 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEpic Design Pvt ltd
EngineerKishor Nikam
EngineerBhausaheb Arote
EngineerSantosh Tatyasaheb Deshpande
Chartered AccountantAshwin Kapoor
Chartered AccountantJSVL and CO
Chartered AccountantPritesh Munot
Chartered AccountantKunal Joshi
PartnerRole in project
High Yield Fortune Pvt Ltd-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024967Nov 2024 → Nov 2025

Reason as filed by the promoterThe extension is majorly due to significant Material shortages, which severely have impacted the construction timeline, delaying important stages of project. However, we are nearing the project completion and preparing to apply for OC. Hence, additional time is required to address the delays, requesting you to grant us the same.

EA11052620902Nov 2024 → Aug 2026

Reason as filed by the promoterWe have received the Full Occupancy Certificate (OC) for the Foresta Phase II Project from the competent authority, and we have already applied for the Completion of the project (Ref No: CU/P52100046937/1) as the Full OC has been received in the project. However, the application got rejected by the authority by raising scrutiny that " Project Completion for Occupancy Certificate is Rejected because project details BUA , no of floors etc are not tallying with sanctioned plans or OC details. Please get the project details as per the sanctioned plans by filing correction application and thereafte

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000471309Suraj Pravin ShahHigh Yield Fortune Pvt. Ltd.14/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed231

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 231 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q1 2026-27.pdf18 Aug 2026
Withdrawal Update Form 2File: Form 2 Q1 2026-27.pdf18 Aug 2026
Withdrawal Update Form 3File: Form 3 Q1 2026-27.pdf18 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A Final.pdf30 Jun 2026
Building plan approvalFile: 01-27 Foresta - Site Layout c.pdf20 May 2026
Building plan approvalFile: 02-27 Foresta - Amalgamation c.pdf20 May 2026
Building plan approvalFile: 03-27 Foresta Contour Survey Parking Layout.pdf20 May 2026
Building plan approvalFile: 10-27 Foresta - Building 2(A Block).pdf20 May 2026
Building plan approvalFile: 11-27 Foresta - Building 2(B Block).pdf20 May 2026
Building plan approvalFile: 12-27 Foresta - Building 2(C Block).pdf20 May 2026
Building plan approvalFile: 13-27 Foresta - Building 2(D Block).pdf20 May 2026
Building plan approvalFile: 14-27 Foresta - Building 3(E Block).pdf20 May 2026
Layout approvalFile: 01-27 Foresta - Site Layout c.pdf20 May 2026
Withdrawal Update Form 1File: Form 1 Q4 25-26 Foresta 2.pdf20 May 2026
Withdrawal Update Form 2File: Form 2 Q4 25-26 Foresta 2.pdf20 May 2026
Withdrawal Update Form 3File: Form 3 Q4 25-26 Foresta 2c.pdf20 May 2026
Form 5 (FY 2024-2025)File: RERA Form -5 Foresta-II (2024-25).pdf12 May 2026
Form 2A (FY 2024-2025)File: Foresta-II Form-2A(2024-25).pdf11 May 2026
Withdrawal Update Form 1File: Form-1-Q3-Foresta-2.pdf1 Apr 2026
Withdrawal Update Form 2File: Form-2-Q3-Foresta-2.pdf1 Apr 2026
Withdrawal Update Form 3File: Form-3-Q3 25-26-Foresta Phase II (1).pdf1 Apr 2026
Withdrawal Update Form 1File: Form 1 Q2.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2 Q2.pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3 Foresta P2 Q2 25-26.pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1 Q2.pdf5 Dec 2025
Withdrawal Update Form 2File: Form 2 Q2.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3 Foresta P2 Q2 25-26.pdf5 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf26 Sep 2025
Withdrawal Update Form 2File: Form 2 Foresta P2.pdf26 Sep 2025
Withdrawal Update Form 3File: Signed Form 3 Foresta Phase II Q1 25-26.pdf26 Sep 2025
Form 1File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3).pdf28 Jun 2025
Form 2File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (3).pdf28 Jun 2025
Form 3File: 1 CA Certificate on Project Cost & Fund withdrawal (Form 3) (4).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory (2).pdf28 Jun 2025
Form 1File: Form 1 - Q3 Architect.pdf28 Jun 2025
Form 2File: Form 2 Q3 Engineer.pdf28 Jun 2025
Form 3File: CA - Certificate Phase II C.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory (2).pdf28 Jun 2025
Form 1File: Form 1 - Q4 Architect.pdf28 Jun 2025
Form 2File: Form 2 - Q4 Engineer.pdf28 Jun 2025
Form 3File: Form 3 Q4 (1)_compressed.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q4.pdf28 Jun 2025
Form 1File: Form 1 F2 Q1.pdf28 Jun 2025
Form 2File: Form 2 F2 Q1.pdf28 Jun 2025
Form 3File: Form 3 Q1.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q1.pdf28 Jun 2025
Form 1File: Form 1 F2 Q2.pdf28 Jun 2025
Form 2File: Form 2 F2 Q2.pdf28 Jun 2025
Form 3File: Form 3 Q2.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q2.pdf28 Jun 2025
Form 1File: Form 1 F2 Q3.pdf28 Jun 2025
Form 2File: Form 2 F2 Q3.pdf28 Jun 2025
Form 3File: Form 3 Q3.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q3.pdf28 Jun 2025
Form 1File: Form 1 Q4 Architect.pdf28 Jun 2025
Form 2File: Form 2 Q4 Enginner.pdf28 Jun 2025
Form 3File: Form 3 Q4 CA.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q4.pdf28 Jun 2025
Form 1File: Form 1 Q1 Architect.pdf28 Jun 2025
Form 2File: Form 2 Q1 Enginner.pdf28 Jun 2025
Form 3File: Form 3 - FY 24-25 - Q1c.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q1.pdf28 Jun 2025
Form 1File: Form 1 Q2 Architect.pdf28 Jun 2025
Form 2File: Form 2 Q2 Enginner.pdf28 Jun 2025
Form 3File: Form 3 - FY 24-25 - Q2 - Final.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q2.pdf28 Jun 2025
Form 1File: Form 1 - Q3 Architect.pdf28 Jun 2025
Form 2File: Form 2 - Q3 Engineer.pdf28 Jun 2025
Form 3File: Form 3.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold booked inventory Q3.pdf28 Jun 2025
Form 1File: Form 1 - Q4 Architect.pdf28 Jun 2025
Form 2File: Form 2 -Foresta 2.pdf28 Jun 2025
Form 3File: Form_3_Q4_FY_24-25_Foresta_Phase_II_Final.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory.pdf28 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q4 Architect.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_Q4_FY_24-25_Foresta_Phase_II_Final.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Foresta 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory.pdf19 Apr 2025
Declaration in FORM BFile: Form B 500 Stamp Paper.pdf19 Mar 2025
Declaration in FORM BFile: form B final.pdf3 Mar 2025

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationStatusPromisedDelivered
ELITE PHIIBORIANDICompletedJan 2019Jan 2019
Wai woodsGat No 618 635 636 207 warkhadi wadi Tal Wai Dist SataraCompletedFeb 2018Feb 2018
Golden AcersGat no 44 Borate Vasti Tal Daund Dist PuneCompletedAug 2016Aug 2016
EliteGat No 407 Boribhadak Tal Daund Dist PuneCompletedJul 2015Jul 2015

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 21 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Foresta Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Mahindra International College13,700+ in Pune

2 kmForesta Phase IICompleted 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: High Yield Fortune Pvt Ltd

High Yield Fortune Pvt Ltd has 3 registrations on MahaRERA, including Foresta Phase II and Arkaya Phase I. Its filings disclose 10 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Foresta Phase II is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Foresta Phase II?

The registered promoter entity is High Yield Fortune Pvt Ltd, a company as per the filing. Its CIN U45401PN2020PTC192582 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Foresta Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Foresta Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Foresta Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Foresta Phase II?

The professionals named in the filing: Architect: Epic Design Pvt ltd; Engineer: Kishor Nikam; Engineer: Bhausaheb Arote; Engineer: Santosh Tatyasaheb Deshpande; Chartered Accountant: Ashwin Kapoor; Chartered Accountant: JSVL and CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Foresta Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Foresta Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Foresta Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.