High Yield Fortune Pvt Ltd: RERA track record
CIN U45401PN2020PTC192582 · Company · attribution by exact filing name, entity resolution in progress
High Yield Fortune Pvt Ltd has 3 registrations on MahaRERA, including Foresta Phase II and Arkaya Phase I. Its filings disclose 10 earlier MahaRERA projects: declares 4 of 7 past projects completed on time.
Projects by this developer
Showing all 3 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Shere PalaceP52100080187 | Shere, Pune, 412108 | 83 | 36% | 6 May 2025 | Registered |
| Arkaya Phase IP52100054318 | Bori Bhadak, Pune, 412202 | 40 | 35% | 15 Jan 2024 | Registered |
| Foresta Phase IIP52100046937 | Near Mahindra International College, Pune, 412108 | 32 | 97% | 20 Sep 2022 | Registered |
What this promoter declares as its own experience
High Yield Fortune Pvt Ltd declares experience on 10 earlier projects. 3 of them carry a registration number we could match on MahaRERA, of which 1 is registered under a different promoter name.
3 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. It changes nothing about whether that project was delivered on time.
| Declared project | Registered to | Status |
|---|---|---|
| Rivera Residence Phase 1 | M/s High Yield Fortune Pvt Ltd | Registered |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| ELITE PH-I | 30 Jun 2012 | 31 Jul 2015 | +37 months |
| Golden Acres | 30 Jun 2012 | 31 Aug 2016 | +50 months |
| Elite | 23 Jul 2015 | 23 Jul 2015 | On time |
| ELITE PH-II | 31 Dec 2015 | 31 Aug 2016 | +8 months |
| Golden Acers | 19 Aug 2016 | 19 Aug 2016 | On time |
| Wai woods | 7 Feb 2018 | 7 Feb 2018 | On time |
| ELITE PHII | 31 Jan 2019 | 31 Jan 2019 | On time |
| Foresta Phase II P52100046937 | 29 Nov 2025 | Not completed yet | Ongoing |
| Arkaya Phase I P52100054318 | 31 Oct 2028 | Not completed yet | Ongoing |
| Rivera Residence Phase 1 P52100079629 | 31 Dec 2029 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify High Yield Fortune Pvt Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45401PN2020PTC192582 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with High Yield Fortune Pvt Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.