Home / Browse projects / Pune, Maharashtra / F PREMIUM

Registered Litigation declared Residential / Group Housing project

F PREMIUM

By ESSEN LANDMARKS

RG-MH-05606 · RERA P52100056429 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Rs 50.00 crore secured on the land, in favour of Kotak Mahindra Bank LTD

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedno revision filed
16 of 88Construction stages doneacross 8 buildings; furthest along: Slabs of Super Structure, 91%
246 of 576Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 199 documents Report an error

F PREMIUM is a Residential / Group Housing project by ESSEN LANDMARKS in Pune, Maharashtra, registered with MahaRERA as P52100056429 on 31 May 2024. Possession is promised by 21 Mar 2029. 330 of the 576 units on this registration are recorded sold or booked, and 16 of 88 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameF PREMIUM
  • TypeResidential / Group Housing
  • Location
    • MUMBAI - BANGOLAR HIGHWAY
    • BEHIND ZUDIO
    • PUNAWALE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100056429
  • ReraGenie IDRG-MH-05606

Builder

  • NameESSEN LANDMARKS
  • Entity typePartnership
  • PartnersNARENDRA BHIMSEN AGARWAL, RAMESH RAMCHANDRA AGARWAL, VINOD PREMCHAND CHANDWANI, NIRMAL DEEPAK JESWANI
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2024PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 May 2024
  • Promised completion21 Mar 2029
  • Revised completionNone
  • Buildings8 building records
  • Documents filed199 files

Current status

57%330 of 576 units booked
51.7%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA16060060
B BUILDINGNA3201240124
C BUILDINGNA30808
D BUILDING - MHADANA1601110111
E BUILDINGNA22084084
F BUILDINGNA2301690169
G BUILDINGNA20808
COMMERCIAL BUILDINGNA3001212

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Slabs of Super Structure, at 91%.

A BUILDING52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure91%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises36%
Sanitary Fittings within the flats / premises13%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks68%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.33%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
B BUILDING42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure64%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises22%
Sanitary Fittings within the flats / premises6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks46%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.3%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
C BUILDING17%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure6%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D BUILDING - MHADA17%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure3%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E BUILDING47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure79%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises33%
Sanitary Fittings within the flats / premises16%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks58%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
F BUILDING53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises46%
Sanitary Fittings within the flats / premises19%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.8%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
G BUILDING9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIAL BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed504

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots504
Closed/Covered504
BuildingClosed/CoveredTotal
A BUILDING118118
B BUILDING124124
C BUILDING44
D BUILDING - MHADA5656
E BUILDING8383
F BUILDING8585
G BUILDING44
COMMERCIAL BUILDING3030

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area33,162 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofKotak Mahindra Bank LTD
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on11 Feb 2026
LandownerVillageDistrict
M/S ESVEE DREAM HOMES LLPPunawalePune

Approvals and building plan

Sanctioning authorityEssen landmark
Permissible FSI195911.15
Proposed, not sanctioned65,911 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 - 8, GROUND FLOOR, F - WING, PREMIER PLAZA, OLD MUMBAI - PUNE HIGHWAY, CHINCHWAD, PUNE - 4
Estimated costRs 330.24 cr
Cost incurredRs 170.61 cr
Work done51.66%
BuildingWingEstimatedIncurred
A BUILDINGNARs 67.78 crRs 54.43 cr
F BUILDINGNARs 46.25 crRs 26.64 cr
G BUILDINGNARs 45.97 crRs 5.06 cr
B BUILDINGNARs 45.12 crRs 29.24 cr
C BUILDINGNARs 44.87 crRs 12.92 cr
E BUILDINGNARs 44.17 crRs 34.98 cr
D BUILDING - MHADANARs 21.15 crRs 6.09 cr
-NARs 8.73 crRs 1.26 cr
COMMERCIAL BUILDINGNARs 6.18 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANOJ TATOOSKAR
EngineerUmesh Shewale
EngineerSNEHA SWANT
Chartered AccountantOSWAL SOLANKI AND ASSOCIATES
Chartered AccountantOSWAL SOLANKI
Chartered AccountantSHEETAL JINDAL
PartnerRole in project
ESSEN LANDMARKS-

Litigation declared1

CaseCourtStatus
2170/2024Shree S K DhekaleOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501011Kalpana Vikas BhingareESSEN LANDMARKS24/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 21 Mar 2029

Documents filed199

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 199 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: F premium form 1.pdf24 Apr 2026
Withdrawal Update Form 2File: F Premium form 2.pdf24 Apr 2026
Withdrawal Update Form 3File: f premium form 3 March.pdf24 Apr 2026
Withdrawal Update Form 1File: F premium form 1 Dec.pdf17 Mar 2026
Withdrawal Update Form 2File: F premium form 2 Dec.pdf17 Mar 2026
Withdrawal Update Form 3File: F premium form 3 Dec.pdf17 Mar 2026
Withdrawal Update Form 1File: F premium form 1 Dec.pdf9 Mar 2026
Withdrawal Update Form 2File: F premium form 2 Dec.pdf9 Mar 2026
Withdrawal Update Form 3File: F premium form 3 Dec.pdf9 Mar 2026
Form 2A (FY 2024-2025)File: F Premium Form 2 A.pdf23 Feb 2026
Form 5 (FY 2024-2025)File: f premium form 5.pdf13 Feb 2026
Withdrawal Update Form 1File: F premium form 1 Dec.pdf27 Jan 2026
Withdrawal Update Form 2File: F premium form 2 Dec.pdf27 Jan 2026
Withdrawal Update Form 3File: F premium form 3 Dec.pdf27 Jan 2026
Withdrawal Update Form 1File: F premium form sep-25.pdf25 Oct 2025
Withdrawal Update Form 2File: F Premium form 2 sep - 25.pdf25 Oct 2025
Withdrawal Update Form 3File: F Premium form 3 september - 2025 (1).pdf25 Oct 2025
Withdrawal Update Form 1File: F premium form 1 june - 25 (1).pdf20 Oct 2025
Withdrawal Update Form 2File: F-Premium Form 2 June 25 (2).pdf20 Oct 2025
Withdrawal Update Form 3File: F Premium Form 3 June 25 (1).pdf20 Oct 2025
Building plan approvalFile: 2_29.pdf23 Sep 2025
Building plan approvalFile: 3_29.pdf23 Sep 2025
Building plan approvalFile: 4_29.pdf23 Sep 2025
Building plan approvalFile: 5_29.pdf23 Sep 2025
Building plan approvalFile: 6_29.pdf23 Sep 2025
Building plan approvalFile: 7_29.pdf23 Sep 2025
Building plan approvalFile: 8_29.pdf23 Sep 2025
Building plan approvalFile: 9_29.pdf23 Sep 2025
Building plan approvalFile: 10_29.pdf23 Sep 2025
Building plan approvalFile: 11_29.pdf23 Sep 2025
Building plan approvalFile: 12_29.pdf23 Sep 2025
Building plan approvalFile: 13_29.pdf23 Sep 2025
Building plan approvalFile: 14_29.pdf23 Sep 2025
Building plan approvalFile: 15_29.pdf23 Sep 2025
Building plan approvalFile: 16_29.pdf23 Sep 2025
Building plan approvalFile: 17_29.pdf23 Sep 2025
Building plan approvalFile: 18_29.pdf23 Sep 2025
Building plan approvalFile: 19_29.pdf23 Sep 2025
Building plan approvalFile: 20_29.pdf23 Sep 2025
Building plan approvalFile: 21_29.pdf23 Sep 2025
Building plan approvalFile: 22_29.pdf23 Sep 2025
Building plan approvalFile: 23_29.pdf23 Sep 2025
Building plan approvalFile: 24_29.pdf23 Sep 2025
Building plan approvalFile: 25_29.pdf23 Sep 2025
Building plan approvalFile: 26_29.pdf23 Sep 2025
Building plan approvalFile: 27_29.pdf23 Sep 2025
Building plan approvalFile: 28_29.pdf23 Sep 2025
Building plan approvalFile: 29_29.pdf23 Sep 2025
Layout approvalFile: New building layout.pdf4 Sep 2025
Form 1File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 4 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 3 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf19 Aug 2025
Form 2File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf19 Aug 2025
Form 3File: 2 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf19 Aug 2025
Form 1File: FORM 1 Q4 JAN-MARCH 2025 F PREMIUM.pdf18 Aug 2025
Form 2File: FORM 2 Q4 JAN-MARCH 2025 F PREMIUM.pdf18 Aug 2025
Form 3File: FORM 3 JAN-MARCH 2025 F PREMIUM_compressed (1).pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD BOOKED INVENTORY Q4- JAN-MARCH 2025 F PREMIUM_compressed (1).pdf18 Aug 2025
Other - LegalFile: MHPU010127222023_1_2025-05-03.pdf7 May 2025
Other - LegalFile: 3691-2015 manyatapatra manda kedari compressed.pdf4 May 2025
Other - LegalFile: 6765-2012 CONFRMATION DEED MANOJ SURYAKANT OVHAL 15-06-2012 compressed.pdf4 May 2025
Other - LegalFile: DEED OF CONFIRMATION DOC NO 4154-2006 DATE 14-06-2006.pdf4 May 2025
Other - LegalFile: Application 0 7 R 11.pdf4 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 31-03-2025 f premium.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JAN-MARCH 2025 F PREMIUM compressed.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q4 JAN-MARCH 2025 F PREMIUM.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4 JAN-MARCH 2025 F PREMIUM.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD BOOKED INVENTORY Q4- JAN-MARCH 2025 F PREMIUM.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3 OCT-DEC 2024 F PREMIUM.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 OCT-DEC 2024 F PREMIUM compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 OCT-DEC 2024 F PREMIUM.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold booked inventory F PREMIUM compressed.pdf20 Jan 2025
Proforma of Agreement for saleFile: 16-10-2024 F Premium_Agreement.pdf21 Oct 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AISHWARYAM HAMARA ABHIMAANP52100052847CHIKHALI, Pune560Oct 2023OngoingDec 2025Not delivered

How this compares with Pune

57%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep F PREMIUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNAWALE13,700+ in Pune

2 kmF PREMIUMCompleted 89Lapsed / revoked 32Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 234 registered projects within 2 km.

Builder: ESSEN LANDMARKS

ESSEN LANDMARKS has 1 registration on MahaRERA, including F PREMIUM. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if F PREMIUM is delayed beyond 21 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of F PREMIUM?

The registered promoter entity is ESSEN LANDMARKS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in F PREMIUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against F PREMIUM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for F PREMIUM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at F PREMIUM?

The professionals named in the filing: Architect: MANOJ TATOOSKAR; Engineer: Umesh Shewale; Engineer: SNEHA SWANT; Chartered Accountant: OSWAL SOLANKI AND ASSOCIATES; Chartered Accountant: OSWAL SOLANKI; Chartered Accountant: SHEETAL JINDAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in F PREMIUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About F PREMIUM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save F PREMIUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.