EVERNEST SHIVSHRUSHTI
RG-MH-78711 · RERA P52100051305 · Last updated on MahaRERA portal: 25 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EVERNEST SHIVSHRUSHTI is a Residential / Group Housing project by EVERNEST PERFECTINFRA LLP in Pune, Maharashtra, registered with MahaRERA as P52100051305 on 8 Jun 2023. Possession is promised by 31 Dec 2026. 1 of the 5 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameEVERNEST SHIVSHRUSHTI
- TypeResidential / Group Housing
- Location
- LANDEWADI
- Bhosari
- Haveli
- Pune
- 411039
- Pincode411039
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100051305
- ReraGenie IDRG-MH-78711
Builder
- NameEVERNEST PERFECTINFRA LLP
- Entity typePartnership
- PartnersSUMIT KUMAR SHUBHASH SHARMA, DATTA MARUTI YEWALE, SURESH MAHADU NEWALE, RANJANA AJINATH BHOGAL
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Jun 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed79 files
Current status
Figures as on 25 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| EVERNEST SHIVSHRUSHTI | NA | 5 | 5 | 5 | 0 | 5 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.
EVERNEST SHIVSHRUSHTI: 47% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed31
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership10
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| ANIL SAYAJI BARNE | Pune (M Corp.) | Pune |
| RAJSHREE ANIL BARNE | Pune (M Corp.) | Pune |
| KUSUM SUNIL BARNE | Pune (M Corp.) | Pune |
| AMRUTA ANIL BARNE | Pune (M Corp.) | Pune |
| ATHARVA SUNIL BARNE | Pune (M Corp.) | Pune |
| GAURI SUNIL BARNE | Pune (M Corp.) | Pune |
| NALINEE SAYAJI BARNE | Pune (M Corp.) | Pune |
| PORNIMA ANIL BARNE | Pune (M Corp.) | Pune |
| RUTUJA ANIL BARNE | Pune (M Corp.) | Pune |
| SARTHAK ANIL BARNE | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| EVERNEST SHIVSHRUSHTI | NA | Rs 3.28 cr | Rs 1.93 cr |
| - | NA | Rs 25.00 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rahul Ashok Kalbhor |
| Engineer | Dattatraya Maruti Yewale |
| Chartered Accountant | PRATIK SHARAD KOTHARI |
| Chartered Accountant | AVHK AND ASSOCIATES |
| Chartered Accountant | Nishant R Patil |
| Partner | Role in project |
|---|---|
| EVERNEST PERFECTINFRA LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000441134 | PATIL TUKARAM GUND | EVERNEST PERFECTINFRA LLP | 18/06/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Apr 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 May 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: CA Form 5 _31 Mar 2026_Signed.pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: Arch Certificate 22 april 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 2File: ENG Certificate 22 april 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 3File: CA Form 3 22 april 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 1File: Arch Certificate Dec2025 Q3.pdf | 8 Apr 2026 |
| Withdrawal Update Form 2File: Eng Certificate Dec2025 Q3.pdf | 8 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 QTR 3.pdf | 8 Apr 2026 |
| Withdrawal Update Form 1File: Arch Certificate Dec2025 Q3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 1File: Arch Certificate Dec2025 Q3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 2File: Eng Certificate Dec2025 Q3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 2File: Eng Certificate Dec2025 Q3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 QTR 3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 QTR 3.pdf | 3 Apr 2026 |
| Withdrawal Update Form 1File: Arch Certificate Dec2025 Q3.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: Eng Certificate Dec2025 Q3.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: CA CERTIFICATE Q3.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Architect certificate Form 1.pdf | 9 Feb 2026 |
| Withdrawal Update Form 1File: Architect certificate Form 1.pdf | 9 Feb 2026 |
| Withdrawal Update Form 1File: Arch Certificate Form 1 Q2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 1File: Arch Certificate Form 1 Q2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 2File: Eng Certificare Form 2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 2File: Eng Certificare Form 2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 2File: Eng Certificate Form 2 Q2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 2File: Eng Certificate Form 2 Q2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 3File: Form_3 CA Certificate Upto Dec 2023.pdf | 9 Feb 2026 |
| Withdrawal Update Form 3File: From 3.pdf | 9 Feb 2026 |
| Withdrawal Update Form 3File: ca certificate Form 3 Q2.pdf | 9 Feb 2026 |
| Withdrawal Update Form 3File: ca certificate Form 3 Q2.pdf | 9 Feb 2026 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory.pdf | 8 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A 2023-24.pdf | 8 May 2025 |
| Building plan approvalFile: Revised Sanction Plan and Bulding Layout-compressed.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q1_2024-25.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2_2024-25.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3_2024-25.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4_2024-25.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2_2023-24.pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(Q4-FY 2024-25).pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(Q2-FY 2024-25).pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(Q1-FY 2024-25).pdf | 6 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(Q4-FY 2023-24).pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q1_2024-25.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q2_2024-25.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3_2024-25.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q4 2024-25.pdf | 6 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 6 May 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Revised Sanction Plan and Bulding Layout-compressed.pdf | 6 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Form 3(Q3-FY 2024-25).pdf | 6 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5 FY 2023-24.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneer Certificate 11-04-2024.pdf | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate evernest perfectinfra 11-Apr-2024 16-07-31.pdf | 9 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certficate.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3 CA Certificate Upto Sept 2023.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3 CA Certificate Upto Dec 2023.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Evernest Shivsurahti Form 1.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Evernest Shivshrushti 2024.pdf | 2 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate com.pdf | 1 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosureofinterestofdiretors.pdf | 1 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: Declaration for Non Encumbrance.pdf | 29 May 2023 |
| Details of encumbrances concerned to LegalFile: Declaration for Non Encumbrance.pdf | 29 May 2023 |
| Layout approvalFile: 9Copy of Layout Approval.pdf | 21 Apr 2023 |
| Building plan approvalFile: 8Building Plan Approval.pdf | 21 Apr 2023 |
| PAN CardFile: 22PANCard -.pdf | 21 Apr 2023 |
| Copy of the legal title reportFile: 2Legalsearchtitelreport.pdf | 21 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: 12 Noencuumbranceletter.pdf | 21 Apr 2023 |
| Details of encumbrances concerned to LegalFile: 12 Noencuumbranceletter.pdf | 21 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 9Copy of Layout Approval.pdf | 21 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 8Building Plan Approval.pdf | 21 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 10Commencement Certificate.pdf | 21 Apr 2023 |
| Declaration about Commencement CertificateFile: 20Declarationforcommencementcertificate.pdf | 21 Apr 2023 |
| Declaration in FORM BFile: 17BAnnexureBperfectinfra.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1Architectcetrificate.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2EngineerCertificate.pdf | 21 Apr 2023 |
| CERSAI detailsFile: CERSAI_SearchREPORT.pdf | 21 Apr 2023 |
| Proforma of Agreement for saleFile: 4Draftsale Agreement.pdf | 21 Apr 2023 |
| Proforma of Allotment letterFile: 6Allotmentletter.pdf | 21 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 19Declarationaboutspratebankaccount.pdf | 21 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: 7Diviationletterforallotmentletter.pdf | 21 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: 5Diviationforsaleagreement.pdf | 21 Apr 2023 |
| Other - LegalFile: 15MAVM Membership Certficate.pdf | 21 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep EVERNEST SHIVSHRUSHTI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near LANDEWADI13,700+ in Pune
Filed coordinates, straight-line distance. 29 registered projects within 2 km.
ABHISHEK MEADOWS
Abhishek Construction
VISION EXOTICA
VISION AVIS GROUPS
VISION EXOTICA PHASE-II
VISION AVIS GROUPS
DD SQUARE
DATTADIGAMBAR ASSOCIATES
Diamond hills
A Square Properties
MRUDULA RESIDENCY
SAMARTH ASSOCIATES
Builder: EVERNEST PERFECTINFRA LLP
EVERNEST PERFECTINFRA LLP has 1 registration on MahaRERA, including EVERNEST SHIVSHRUSHTI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if EVERNEST SHIVSHRUSHTI is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EVERNEST SHIVSHRUSHTI?
The registered promoter entity is EVERNEST PERFECTINFRA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EVERNEST SHIVSHRUSHTI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EVERNEST SHIVSHRUSHTI?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EVERNEST SHIVSHRUSHTI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EVERNEST SHIVSHRUSHTI?
The professionals named in the filing: Architect: Rahul Ashok Kalbhor; Engineer: Dattatraya Maruti Yewale; Chartered Accountant: PRATIK SHARAD KOTHARI; Chartered Accountant: AVHK AND ASSOCIATES; Chartered Accountant: Nishant R Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EVERNEST SHIVSHRUSHTI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback