Home / Browse projects / Mumbai Suburban, Maharashtra / ESTO ARKIS
ESTO ARKIS
RG-MH-00229 · RERA P51800081007 · Last updated on MahaRERA portal: 30 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 4 months
- 1 extension taken
- Rs 20.00 crore secured on the land, in favour of VISTRA ITCL INDIA LIMITED
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ESTO ARKIS is a Residential / Group Housing project by REN REALITY LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800081007 on 10 Oct 2025. Possession is promised by 30 Apr 2031. The completion date has moved by 4 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameESTO ARKIS
- TypeResidential / Group Housing
- Location
- S.V.P NAGAR
- ANDHERI
- Varsova
- Mumbai Suburban
- 400053
- Pincode400053
- RERA no.P51800081007
- ReraGenie IDRG-MH-00229
Builder
- NameREN REALITY LLP
- Entity typePartnership
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Oct 2025
- Promised completion30 Apr 2031
- Revised completionRevised to 30 Apr 2031 (originally 31 Dec 2030)
- Buildings2 building records
- Documents filed42 files
Current status
Figures as on 30 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 2 | 0 | 0 | 0 | 0 |
| B WING | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.
A WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| VERSOVA ANDHERI UTSAHI CO OPERATIVE HOUSING SOCIET | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 31.96 cr | Rs 34.85 lakh |
| B WING | NA | Rs 31.96 cr | Rs 34.85 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SP ASSOCIATES |
| Architect | Mitie designers & planners pvt ltd |
| Engineer | abc |
| Engineer | M.S. Shaikh |
| Chartered Accountant | ROHIT KUMAR TAWARI |
| Chartered Accountant | DEVESH SHAH & CO |
| Chartered Accountant | Kanu Doshi Associates LLP |
| Partner | Role in project |
|---|---|
| REN REALITY LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| SM12600113 | Bhakti Achrekar | REN REALITY LLP | 06/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 May 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 May 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2031
Documents filed42
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A The Ren Reality LLP_30092026.pdf | 30 Sep 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 REN REALITY LLP 30092026.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 30 06 2026.pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 30 06 2026 SIGN.pdf | 27 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30 06 2026.pdf | 27 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 12-09-2025.pdf | 18 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 31 03 2026.pdf | 18 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 31-12-2025.pdf | 18 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 31 03 2026.pdf | 18 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 (1).pdf | 18 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Q4.pdf | 18 Jun 2026 |
| Other - TechnicalFile: Rera Affidavit 24092025.pdf | 6 Oct 2025 |
| CERSAI detailsFile: Asset Based Search.pdf | 30 Sep 2025 |
| Other - TechnicalFile: CC VERIFICATION MAIL.pdf | 30 Sep 2025 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance.pdf | 22 Sep 2025 |
| CERSAI detailsFile: Cersai IOM 400094115254.pdf | 22 Sep 2025 |
| CERSAI detailsFile: Cersai Decleration Esto.pdf | 22 Sep 2025 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance.pdf | 22 Sep 2025 |
| Other - TechnicalFile: Declration 06-10-2025.pdf | 22 Sep 2025 |
| Building plan approvalFile: IOA.pdf | 2 May 2025 |
| Copy of the legal title reportFile: Title Report - RERA.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 06-10-2025.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Building Plan Approval _ NA Order for plotted development (20).pdf | 2 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: utsahi CHS plinth CC.pdf | 2 May 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf | 2 May 2025 |
| Declaration about Commencement CertificateFile: CC Covering Letter 30-09-2025.pdf | 2 May 2025 |
| Layout approvalFile: drawing_EE_Sign (2).pdf | 24 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: drawing_EE_Sign (2).pdf | 24 Jul 2024 |
| Proforma of Allotment letterFile: ESTO ARKIS ALLOTMENT LETTER.pdf | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 12-09-2025.pdf | 24 Jul 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation report - allotment.pdf | 24 Jul 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement for Sale final_11zon.pdf | 24 Jul 2024 |
| Proforma of Agreement for saleFile: AFS- Draft-12925 (1).pdf | 24 Jul 2024 |
| PAN CardFile: REN PAN.pdf | 8 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Financial Encumbrance.pdf | 8 Jul 2024 |
| Declaration in FORM BFile: Affidavit Ren Reality.pdf | 8 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A 130925.pdf | 8 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Financial Encumbrance.pdf | 8 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: aditya Doi.pdf | 8 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: shakendra doi.pdf | 8 Jul 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 8 Jul 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: ilovepdf_merged (19).pdf | 8 Jul 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 42 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ESTO ARKIS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ANDHERI6,700+ in Mumbai Suburban
LIVSMART KURLA
D. K. REALTY (INDIA) PVT. LTD.
MOONGIPA ARCADE
MOONGIPA REALTY PRIVATE LIMITED
LINKBAY RESIDENCES PHASE I
PORTSMOUTH BUILDCON PRIVATE LIMITED
Purva Estrella
Puravankara Ltd
78 LAKE TOWN
ANIRDESH DEVELOPERS PRIVATE LIMITED
Transcon Triumph Tower 2
Transcon Triumph Phase 2 Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: REN REALITY LLP
REN REALITY LLP has 1 registration on MahaRERA, including ESTO ARKIS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if ESTO ARKIS is delayed beyond 30 Apr 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ESTO ARKIS?
The registered promoter entity is REN REALITY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ESTO ARKIS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ESTO ARKIS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ESTO ARKIS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ESTO ARKIS?
The professionals named in the filing: Architect: SP ASSOCIATES; Architect: Mitie designers & planners pvt ltd; Engineer: abc; Engineer: M.S. Shaikh; Chartered Accountant: ROHIT KUMAR TAWARI; Chartered Accountant: DEVESH SHAH & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ESTO ARKIS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback