ESTA RANJIT HOUSE

By ESTA RANJIT HOUSE

RG-MH-45925 · RERA P51900049166 · Last updated on MahaRERA portal: 27 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jun 2027Possession promisedmoved 18 months from the original
2 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
38 of 43Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

ESTA RANJIT HOUSE is a Others project by ESTA RANJIT HOUSE in MASJID BUNDER ROAD, 400003, registered with MahaRERA as P51900049166 on 3 Feb 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 18 months from the original filing. 5 of the 43 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameESTA RANJIT HOUSE
  • TypeOthers
  • Location
    • C.S. NO. 385
    • F.P. NO. 220
    • TPS-I
    • VILLAGE - VADGADI AT MANDAVI
    • SAMUEL STREET
    • MASJID BUNDER MUMBAI -400003
    • MASJID BUNDER ROAD
    • 400003
  • Pincode400003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900049166
  • ReraGenie IDRG-MH-45925

Builder

  • NameESTA RANJIT HOUSE
  • Entity typePartnership
  • PartnersANISH RAJKUMAR PARASRAMPURA, SHARADKUMAR KALAYNJI VASANT, MITEN SANAJY SHROOF

Key dates

this monthRegisteredFeb 2023First promiseDec 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2023
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed93 files

Current status

12%5 of 43 units booked
69.6%Work done, per cost certificate

Figures as on 27 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ESTA RANJIT HOUSENA2624321143

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

ESTA RANJIT HOUSE: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area158 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Dec 2025
LandownerVillageDistrict
M/S VIDHI BUILDERGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI2779.56
Proposed, not sanctioned1,466 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchROAD NO 3, GROUND FLOOR ABHINANDAN, CHS DR AMBDKAR ROAD, PAREL, MUMBAI 400012
Estimated costRs 13.96 cr
Cost incurredRs 9.72 cr
Work done69.64%
BuildingWingEstimatedIncurred
ESTA RANJIT HOUSENARs 13.86 crRs 9.72 cr
-NARs 10.00 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKADAKIA N K
EngineerPRAVIN R KULKARNI
Chartered AccountantJAIN DEDHIA AND ASSOCIATES LLP
Chartered AccountantSANAM RAJENDRA JAIN
Chartered AccountantKUNJ DEDHIA & ASSOCIATES
PartnerRole in project
ESTA RANJIT HOUSE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA13012619429Dec 2025 → Jun 2027

Reason as filed by the promoterTHE CONSTRUCTION PROJECT HAD TO BE PUT ON HOLD FOR A CONSIDERABLE AMOUNT OF TIME DUE TO UNANTICIPATED CIRCUMSTANCE BROUGHT ON BY THE COVID - 19 PANDEMIC. ADDITIONALLY, BECAUSE THE PROJECT IS SITUATED IN A HIGHLY CONGESTED MARKET AREA, LOGISTICAL CHALLENGES AND LIMITED WORKING CONDITIONS SIGNIFICANTLY SLOWED PROGRESS. CONSEQUENTLY, THE PROJECT WAS UNABLE TO BE FINISHED WITHIN THE INITIAL DEADLINE. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION TILL 30/06/2027

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - 30-06-2026.pdf27 Jul 2026
Withdrawal Update Form 2File: FORM 2 - 30-06-2026.pdf27 Jul 2026
Withdrawal Update Form 3File: FORM 3 - 30-06-2026.pdf27 Jul 2026
Withdrawal Update Form 1File: Form1 31-03-2026.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2 - 31-03-2026.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 - 31-03-2026.pdf24 Jul 2026
Form 5 (FY 2025-2026)File: FORM 5 - 25-26.pdf30 Apr 2026
Form 5 (FY 2023-2024)File: FORM-5- FY - 2023-24.pdf29 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 - 2024-25.pdf25 Apr 2026
Withdrawal Update Form 1File: FORM 1 - 31-12-2025.pdf27 Mar 2026
Withdrawal Update Form 2File: FORM 2 - 31-12-2025.pdf27 Mar 2026
Withdrawal Update Form 3File: FORM 3 31-12-2025.pdf27 Mar 2026
Withdrawal Update Form 1File: FORM 1 - ARCHITECTURE CERTIFICATE.pdf13 Jan 2026
Withdrawal Update Form 2File: FORM 2 - ENGEERING.pdf13 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf13 Jan 2026
Form 1File: FORM 1 - ARCHITECTURE CERTIFICATE.pdf3 Jan 2026
Form 2File: FORM 2 - ENGEERING.pdf3 Jan 2026
Form 3File: FORM 3 CA CERTIFICATE.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SOLD UNSOLD INVENTORY.pdf3 Jan 2026
Form 1File: Architect certificate.pdf22 Jul 2025
Form 2File: Engineer Certificate.pdf22 Jul 2025
Form 3File: CA certificate.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD -UNSOLD INVENTORY.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE CERTIFICAE.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 C A CERTIFICATE_11zon.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE-3.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE CERTIFICATE.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 C A CERTIFICATE.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -UNSOLD INVENTORY.pdf14 Jan 2025
Declaration about Commencement CertificateFile: NEW DECLARATION OF CC.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE (1).pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -UNSOLD INVENTORY (1).pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE CERTIFICATE.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE-1.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD -UNSOLD INVENTORY.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE FORM 3 compressed.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE Certificate.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneering certificate.pdf24 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 CA CERTIFICATE.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneering certificate.pdf22 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: C C RENEWED.pdf20 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: C C Revalidation Application 2024 (1).pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF s.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_compressed.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architecture certiicate.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneering certificate.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A CERTIFICATE_compressed.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture certificate.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneering certificate.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 C A CERTIFICATE (1).pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: BANK TRANSFER-UNSLOD INVENTOY -LEGAL PROFESSIONAL-3.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE (2)_compressed.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITETURE CERTIFICATE.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: disclouser sold -unsold inventory.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf22 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf21 Apr 2023
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: achitecture cetificate (1).pdf21 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE FINAL (1).pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL.pdf21 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf21 Apr 2023
Copy of the legal title reportFile: Legal Title Report 01.pdf31 Jan 2023
Copy of the legal title reportFile: Flow of Title 02.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEW CA.pdf31 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Esta Ranjit.pdf31 Jan 2023
Details of encumbrancesFile: ilovepdf_merged (13).pdf30 Jan 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf10 Jan 2023
Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter (1).pdf10 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Revalidation letter.pdf9 Jan 2023
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1) (1) (1).pdf9 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf14 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf12 Dec 2022
Proforma of Agreement for saleFile: MODEL DRAFT RERA AGREEMENT.pdf12 Dec 2022
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE LEGAL.pdf10 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK LETTER.pdf10 Dec 2022
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION AGREEMENT.pdf10 Dec 2022

Keep ESTA RANJIT HOUSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MASJID BUNDER ROAD

2 kmESTA RANJIT HOUSECompleted 1Lapsed / revoked 6Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: ESTA RANJIT HOUSE

ESTA RANJIT HOUSE has 1 registration on MahaRERA, including ESTA RANJIT HOUSE. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if ESTA RANJIT HOUSE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ESTA RANJIT HOUSE?

The registered promoter entity is ESTA RANJIT HOUSE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ESTA RANJIT HOUSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ESTA RANJIT HOUSE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ESTA RANJIT HOUSE?

The professionals named in the filing: Architect: KADAKIA N K; Engineer: PRAVIN R KULKARNI; Chartered Accountant: JAIN DEDHIA AND ASSOCIATES LLP; Chartered Accountant: SANAM RAJENDRA JAIN; Chartered Accountant: KUNJ DEDHIA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ESTA RANJIT HOUSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ESTA RANJIT HOUSE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ESTA RANJIT HOUSE to a free account