Home / Browse projects / Mumbai City, Maharashtra / Essgee Options One - Phase II

Registration lapsed No litigation declared Commercial project

Essgee Options One - Phase II

By Sheetal Sagar Builders & Developers Private Limited

RG-MH-28174 · RERA P51900026355 · Last updated on MahaRERA portal: 23 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 3%
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Essgee Options One - Phase II is a Commercial project by Sheetal Sagar Builders & Developers Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900026355 on 11 Sep 2020. Possession was promised by 30 Jun 2023 and is now 40 months past that date.

At a glance

Project

  • NameEssgee Options One - Phase II
  • TypeCommercial
  • Location
    • Senapati Bapat Road
    • Dadar
    • GNorth-400028
    • Ward GNorth
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900026355
  • ReraGenie IDRG-MH-28174

Builder

  • NameSheetal Sagar Builders & Developers Private Limited
  • Entity typeCompany
  • DirectorSuresh Gandhi

Key dates

40 months past promisethis monthRegisteredSep 2020PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Sep 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Essgee Options OneNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 3%.

Essgee Options One: 46% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure3%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes98%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes98%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes98%
Solid Waste Management And DisposalYes98%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,853 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
GMJ Builders & DevelopersMumbai CityMumbai City

Approvals and building plan

Permissible FSI5055.42
Proposed, not sanctioned4,821 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDalamal House, Nariman Point, Mumbai 400 021

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil Ambre & Associates
EngineerYashavi Sharma
Chartered AccountantJain & Talesara
Chartered AccountantM M Nissim & Co
PartnerRole in project
Sheetal Sagar Builders & Developers Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Aug 2022

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_SSBDPL II_19-01-23.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Q3_22-23_SS_Phase II Form 29.pdf6 Apr 2023
Disclosure of sold/ booked inventoryFile: Q4_22-23_SS_Phase II Form 29.pdf6 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2_20-21_Form1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3_20-21_Form 1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4_20-21_Form 1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1_21-22_Form1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2_21-22_Form 1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3_21-22_Form 1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4_21-22_Form 1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1_22-23_Form1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2_22-23_Form1_S2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3_22-23_Form1_S2.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2_20-21_Form 2_ S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3_20-21_Form 2_ S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4_20-21_Form 2_S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1_21-22_Form 2_ S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2_21-22_Form 2_S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3_21-22_Form 2_S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4_21-22_Form 2_S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1_22-23_Form 2_ S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2_22-23_Form 2_ S2.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3_22-23_Form 2_ S2.pdf8 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1_22-23_SS_Phasae II_Form3.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q2_22-23_SS_Phasae II_Form3.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3_22-23_Form 3_S2.pdf7 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_21-22_S2.pdf7 Feb 2023
Disclosure of sold/ booked inventoryFile: Q2_20-21_SS_PhaseII.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q3_20-21_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q4_20-21_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q1_21-22_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q2_21-22_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q3_21-22_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q4_21-22_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q1_22-23_SS_Phase II Form 29.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: Q2_22-23_SS_Phase II Form 29.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q2_20-21_SS_Phase II_Form3 .pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3_20-21_SS_Phase II.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q4_20-21_Form 3_S2.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1_21-22_SS_Phase II_Form3.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q2_21-22_Form 3_S2.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3_21-22_Form 3_S2.pdf31 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q4_21-22_Form 3_S2.pdf31 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation ack.pdf30 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A- SSBDL Ph 1 - Mar-22.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: Q2_22-23-Sold inventory-Phase-II.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: Q3_22-23-Sold inventory-Phase-II.pdf16 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SSBDL-Form 2A March-21.pdf21 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SSBDL-Form 2A June-21.pdf21 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SSBDL-Form 2A Sept-21.pdf21 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SSBDL-Form 2A Dec-21.pdf21 Dec 2022
Proforma of Agreement for saleFile: Agreement for sale.pdf21 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_Part_16 06 2022.pdf4 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_30-09-20-SSBDL.pdf24 May 2021
Proforma of Allotment letterFile: Agreement for sale_SSBDL_Phase II.pdf11 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SSBDL-Form 2A Sept-20 Ph2.pdf6 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SSBDL-Form 2A Dec 20 Ph2.pdf6 Jan 2021
Building plan approvalFile: Plan.pdf9 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf9 Sep 2020
Proforma of Allotment letterFile: Allotment letter.pdf9 Sep 2020
Layout approvalFile: Layout plan.pdf19 Mar 2020
Building plan approvalFile: Doc 7_IOD-13-04-17.PDF19 Mar 2020
Building plan approvalFile: Doc 8_IOD-02-07-18.pdf19 Mar 2020
Details of encumbrancesFile: Undertaking for encumbrances.pdf19 Mar 2020
Copy of Layout Approval (in case of layout)File: Layout plan.pdf19 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Doc 7_IOD-13-04-17.PDF19 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Doc 8_IOD-02-07-18.pdf19 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Doc 9_CC-20-06-17.pdf19 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: CC_8th Floor_18 02 2020.PDF19 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Doc 13_CC-18-02-20.PDF19 Mar 2020
Declaration in FORM BFile: Doc 2_Form B SSBDL.PDF19 Mar 2020
Proforma of Allotment letterFile: Doc 18_Undertaking for agree for sale.pdf19 Mar 2020
PAN CardFile: Doc 5_PAN_SSBDPL.pdf5 Mar 2020
Copy of the legal title reportFile: Doc 2_Title Certificate__31 07 18.pdf5 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SSBDPL_Architect Certificate_03 03 2020.PDF5 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SSBDL_Eng Cert_ RERA Phase II.pdf5 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_CA Cert_SSBDL_Reg.pdf5 Mar 2020

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Essgee Options One - Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dadar780+ in Mumbai City

2 kmEssgee Options One - PhaCompleted 55Lapsed / revoked 51Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: Sheetal Sagar Builders & Developers Private Limited

Sheetal Sagar Builders & Developers Private Limited has 1 registration on MahaRERA, including Essgee Options One - Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Essgee Options One - Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Essgee Options One - Phase II is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Essgee Options One - Phase II?

The registered promoter entity is Sheetal Sagar Builders & Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Essgee Options One - Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Essgee Options One - Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Essgee Options One - Phase II?

The professionals named in the filing: Architect: Sunil Ambre & Associates; Engineer: Yashavi Sharma; Chartered Accountant: Jain & Talesara; Chartered Accountant: M M Nissim & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Essgee Options One - Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Essgee Options One - Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Essgee Options One - Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.