Home / Browse projects / Aurangabad, Maharashtra / ESMERALDE BUILDING B1 B2 IB 6 TO 9

Registration lapsed No litigation declared Residential / Group Housing project

ESMERALDE BUILDING B1 B2 IB 6 TO 9

By SHREE KUNDALWAL AND SONS

RG-MH-01368 · RERA P51500005342 · Last updated on MahaRERA portal: 29 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
8 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 21%
26 of 28Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

ESMERALDE BUILDING B1 B2 IB 6 TO 9 is a Residential / Group Housing project by SHREE KUNDALWAL AND SONS in Aurangabad, Maharashtra, registered with MahaRERA as P51500005342 on 11 Aug 2017. Possession was promised by 31 Jul 2023 and is now 39 months past that date. 2 of the 28 units on this registration are recorded sold or booked, and 8 of 44 construction stages are filed complete.

At a glance

Project

  • NameESMERALDE BUILDING B1 B2 IB 6 TO 9
  • TypeResidential / Group Housing
  • Location
    • Paithan Road
    • Nakshatrawadi
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500005342
  • ReraGenie IDRG-MH-01368

Builder

  • NameSHREE KUNDALWAL AND SONS
  • Entity typePartnership
  • PartnersRAJENDRA BANSILAL KUNDALWAL, SANJAY BANSILAL KUNDELWAL
  • Other registrations5 more →
  • No longer live5 lapsed, de-registered or revoked

Key dates

39 months past promisethis monthRegisteredAug 2017PromisedJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion31 Jul 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed96 files

Current status

7%2 of 28 units booked

Figures as on 29 Jun 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING B 1NA7712012
BUILDING B2NA7712012
BUNGALOW IB 6-7NA32202
BUNGLOWNA32202

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 21%.

BUILDING B 18%
ActivityProgress
Excavation21%
Basement (if any)21%
Podiums (if any)0%
Plinth21%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B28%
ActivityProgress
Excavation21%
Basement (if any)21%
Podiums (if any)0%
Plinth21%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW IB 6-78%
ActivityProgress
Excavation21%
Basement (if any)21%
Podiums (if any)0%
Plinth21%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGLOW73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32
BuildingClosed/CoveredTotal
BUILDING B 11212
BUILDING B21212
BUNGALOW IB 6-744
BUNGLOW44

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,463 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
RAJENDRAKUNDALWALAurangabad (M Corp.)Aurangabad
SANJAY KUDELWALAurangabad (M Corp.)Aurangabad
SUHAS VAIDYAAurangabad (M Corp.)Aurangabad
SUNITA VAIDYAAurangabad (M Corp.)Aurangabad
KAMALKISHOR BAJAJAurangabad (M Corp.)Aurangabad
VISHNUDAS BAJAJAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAurangabad Municipal Corporation
Permissible FSI5105.3
Proposed, not sanctioned5,105 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKRANTI CHWOK

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAMIL ARCHITECS
EngineerAJAY KOTGIRE
EngineerCORE CONSULTANTS
EngineerPrasad Pingle
Chartered AccountantSNGP & Company
Chartered AccountantAshok Patil & Associates
PartnerRole in project
SHREE KUNDALWAL AND SONS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 23-24 Q4.pdf29 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: b1 b2 ib 6 to 9.pdf4 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sks B1 B2 IB 6 to 9.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf8 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf8 Mar 2024
Certificates of CA (Form 3)File: Form 3.pdf8 Mar 2024
Certificates of CA (Form 3)File: Form 3 30092023 NEWSIGN.pdf4 Jan 2024
Certificates of CA (Form 3)File: 6-9_11zon.pdf27 Dec 2023
Details of encumbrancesFile: Declaration_for_Encumbrances_format.pdf19 Aug 2023
Details of encumbrances concerned to FinanceFile: B Details of encumbrances concerned to Legal.pdf19 Aug 2023
Details of encumbrances concerned to LegalFile: B Details of encumbrances concerned to Legal.pdf19 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 6 To 9.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20-21.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf19 Aug 2023
Disclosure of sold/ booked inventoryFile: Sold 6-9.pdf19 Aug 2023
Certificates of CA (Form 3)File: BUILDING B1 B2 6 TO 9 31-03-2022.pdf19 Aug 2023
Certificates of CA (Form 3)File: BUILDING B1 B2 IB 6 TO 9 31-12-2022.pdf19 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Balkirshna_merged.pdf19 Aug 2023
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter (1).pdf19 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Account Declaration.pdf19 Aug 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf19 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf19 Aug 2023
Form 2AFile: Form 2A_B1, B2, IB 6-9_20-21.pdf12 Sep 2022
Form 2AFile: Form 2A_B1, B2, IB6-9_17-18.pdf12 Sep 2022
Certificates of CA (Form 3)File: B1,B2,IB6-9_Form 3.pdf12 Sep 2022
Declaration about Commencement CertificateFile: Decl B1 B2 IB6-9.pdf27 Aug 2022
Form 2AFile: Form 2A_B1B2 IB6-9.pdf27 Aug 2022
Certificates of CA (Form 3)File: Form 3_B1,B2,IB 6-9_11zon.pdf22 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 B1 B2 IB 6-9.pdf24 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 B1 B2 IB 6-9_compressed.pdf18 Sep 2021
Form 2AFile: Form 2 B1 B2 IB 6-9_compressed.pdf18 Sep 2021
Certificates of CA (Form 3)File: FORM 3 BULDG B-compressed_compressed.pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: B.pdf18 Sep 2021
Disclosure of sold/ booked inventoryFile: SKS B1 B2 IB 6-9.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: B1 B2.pdf10 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: B1 B2 IB 6-9.pdf10 Aug 2021
Certificates of CA (Form 5)File: B1 B2.pdf5 Aug 2021
Certificates of CA (Form 5)File: B1 B2 IB 6-9.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Building B1 B2 IB 6-9 Q4 FORM 1.pdf3 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Building B1 B2 IB 6-9 Q4 FORM 2.pdf3 Jun 2021
Form 2AFile: Building B1 B2 IB 6-9 Q4 FORM 2A.pdf3 Jun 2021
Certificates of CA (Form 3)File: Building B1 B2 IB 6-9 Q4 Form 3 1.pdf3 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q2 Form 2 19-20.pdf7 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q1 Form 1 19-20.pdf5 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q2 Form 1 19-20.pdf5 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q3 Form 1 19-20.pdf5 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q1 Form 2 19-20.pdf5 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ESM B1 B2 IB 6-9 Q3 Form 2 19-20.pdf5 Nov 2020
Form 2AFile: ESM B1 B2 IB 6-9 Q1 Form 2A 19-20_.PDF5 Nov 2020
Form 2AFile: ESM B1 B2 IB 6-9 Q2 Form 2A 19-20_.PDF5 Nov 2020
Form 2AFile: ESM B1 B2 IB 6-9 Q3 Form 2A 19-20_.PDF5 Nov 2020
Certificates of CA (Form 3)File: ESM B1 B2 IB 6-9 Q1 Form 3 19-20.pdf5 Nov 2020
Certificates of CA (Form 3)File: ESM B1 B2 IB 6-9 Q2 Form 3 19-20.pdf5 Nov 2020
Certificates of CA (Form 3)File: ESM B1 B2 IB 6-9 Q3 Form 3 19-20.pdf5 Nov 2020
Certificates of CA (Form 3)File: FORM 3_Q4_2018-19_ESM B1 B2 IB 6-9 2.pdf11 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 B1 B2, IB 6-9.pdf3 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 B1 B2 IB 6-9.pdf3 Aug 2019
Form 2AFile: Form 2A B1 B2 IB 6-9.pdf3 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_Q3_2018-19_ESM B1 B2 IB 6-9.pdf24 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_Q3_2018-19_ESM B1 B2 IB 6-9.pdf24 Apr 2019
Form 2AFile: FORM 2_Q3_2018-19_ESM B1 B2 IB6-9.pdf24 Apr 2019
Certificates of CA (Form 3)File: B.pdf24 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Q1_18-19_ESM B1,B2,IB6-9.pdf3 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Q2_ESM B1,B2,IB 6-9.pdf3 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FOrm 2_Q1_18-19_ESM B1, Br, IB 6-9.pdf3 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Q2_18-19_ESM B1,B2,IB6-9.pdf3 Jan 2019
Certificates of CA (Form 3)File: Form 3_Q1_2018-19_ESM B1,B2,IB 6-9.pdf3 Jan 2019
Certificates of CA (Form 3)File: FORM 3_Q2_2018-19_ESM B1,B2,IB6-9.pdf3 Jan 2019
Certificates of CA (Form 3)File: ESMERALDE - B1 B2 IB 6-9-ilovepdf-compressed.pdf15 Oct 2018
Certificates of CA (Form 5)File: Form 5 Esmeralde B1,B2,IB6-9.pdf15 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3 Esmeralde B1 B2 IB6 9 Arch cert.pdf30 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 Esmeralde B1 B2 IB6-9 engr cert.pdf28 Apr 2018
Certificates of CA (Form 3)File: Form3_Q2_Esmeralde B1 B2 IB6-9.pdf30 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Easmarald B1 B2 - arch certificate.pdf29 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ESMERALD B1 B2.pdf29 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Esmerald B1 B2 - Eng certificate.pdf29 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ESMERALD B1 B2 ARC.pdf31 Oct 2017
Certificates of CA (Form 3)File: ESMERALDE B1 B2 IB 6-9 pdf.pdf31 Oct 2017
Proforma of Allotment letterFile: ATS_Esmeralde_B1B2 IB 6-9.pdf31 Jul 2017

How this compares with Aurangabad

7%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep ESMERALDE BUILDING B1 B2 IB 6 TO 9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nakshatrawadi1,400+ in Aurangabad

2 kmESMERALDE BUILDING B1 B2Completed 4Lapsed / revoked 5Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: SHREE KUNDALWAL AND SONS

SHREE KUNDALWAL AND SONS has 6 registrations on MahaRERA, including ESMERALDE BUILDING D and ESMERALDE BUILDING C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that ESMERALDE BUILDING B1 B2 IB 6 TO 9 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ESMERALDE BUILDING B1 B2 IB 6 TO 9 is delayed beyond 31 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ESMERALDE BUILDING B1 B2 IB 6 TO 9?

The registered promoter entity is SHREE KUNDALWAL AND SONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ESMERALDE BUILDING B1 B2 IB 6 TO 9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ESMERALDE BUILDING B1 B2 IB 6 TO 9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ESMERALDE BUILDING B1 B2 IB 6 TO 9?

The professionals named in the filing: Architect: SHAMIL ARCHITECS; Engineer: AJAY KOTGIRE; Engineer: CORE CONSULTANTS; Engineer: Prasad Pingle; Chartered Accountant: SNGP & Company; Chartered Accountant: Ashok Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ESMERALDE BUILDING B1 B2 IB 6 TO 9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ESMERALDE BUILDING B1 B2 IB 6 TO 9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ESMERALDE BUILDING B1 B2 IB 6 TO 9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.