ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Emerald Pacific

Registration lapsed No litigation declared Others project

Emerald Pacific

By APR Realty

RG-MH-06129 · RERA P51700051779 · Last updated on MahaRERA portal: 19 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 90%
13 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Emerald Pacific is a Others project by APR Realty in Thane, Maharashtra, registered with MahaRERA as P51700051779 on 3 Jul 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 15 months from the original filing. 7 of the 20 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameEmerald Pacific
  • TypeOthers
  • Location
    • Village - Gajbandhan Patharli
    • Domobivali (E)
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • RERA no.P51700051779
  • ReraGenie IDRG-MH-06129

Builder

  • NameAPR Realty
  • Entity typePartnership
  • PartnersPrashant Vitthal Jadhav, Ajit Jalandar Munde
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredJul 2023First promiseSep 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Jul 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2024)
  • Buildings1 building record
  • Documents filed59 files

Current status

35%7 of 20 units booked
66.3%Work done, per cost certificate

Figures as on 19 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Emerald PacificNA8812820

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

Emerald Pacific: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 19 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered7
Open Space12

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area279 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jun 2025
LandownerVillageDistrict
Sai Villa Co. Op. Hsg. SocietyDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI877.17
Proposed, not sanctioned877 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPatkar Building, Station Road Opp Bus Stand, Dombivli East
Estimated costRs 2.50 cr
Cost incurredRs 1.66 cr
Work done66.32%
BuildingWingEstimatedIncurred
Emerald PacificNARs 2.50 crRs 1.66 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA. S. Dastane & Associates
EngineerRahul B Hedulkar
Chartered AccountantR H Pothiwal & Associates
PartnerRole in project
APR Realty-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025533Sep 2024 → Dec 2025

Reason as filed by the promoterThe delay was caused by unforeseen circumstances beyond our control. Despite our best efforts, we were unable to complete the project within the stipulated timeline. Therefore, we request an extension until 31 December 2025.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: RERA Audit_Emrald Pacific_FY 24-25.pdf19 Mar 2026
Withdrawal Update Form 1File: Architect Certificate Emerald Pacific- Dec 25.pdf7 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate Emerald Pacific - Dec 25.pdf7 Mar 2026
Withdrawal Update Form 3File: CA Certificate_Emerald Pacific_Dec-25.pdf7 Mar 2026
Withdrawal Update Form 1File: Architect Certificate - Sep 25 (Emerald Pacific).pdf19 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate - Sep 25 (Emerald Pacific).pdf19 Nov 2025
Withdrawal Update Form 3File: CA Certificate_Sep-25_Emerald Pacific.pdf19 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_March-25 Emerald Pacific.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Emerald Pacific - March 25.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Emerald Pacific_March 25.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Emerald Pacific - Dec 24.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Emerald Pacific - Dec 24.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Emerald Pacific - Dec 24.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit Report_2023-24.pdf10 Dec 2024
Declaration in FORM BFile: Developers Form B - Emerald Pacific.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Emerald Pacific - Jun 24.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Emerald Pacific - Sep 24.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Jun-24_1.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Sep-24_1.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Emerald Pacific - Jun 24.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Emerald Pacific - Sep 24.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Emerald Pacific.pdf9 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - FY - 2023-24 - Emerald Pacific.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1-Architech Certificate - Sep 23.pdf22 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2-Architech Certificate - Dec 23.pdf22 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3-Architech Certificate - March 24.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Sep 23 Sign Copy.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Dec 23 Sign Copy.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_March 24 Sign Copy.pdf22 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate_Sept 23 - Sign Copy.pdf22 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate_Dec 23 - Sign Copy.pdf22 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3-CA Certificate March 24.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Emerald Pacific - March 24.pdf17 Apr 2024
Other - TechnicalFile: Form 2A - Emerald Pacific - March 24.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Emerald Pacific - Sep 23.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Emerald Pacific - Dec 23.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal Form 3 Final.pdf23 Jun 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf16 Jun 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance - Emerald Pacific.pdf15 Jun 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal - Emerald Pacific.pdf15 Jun 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance - Emerald Pacific.pdf15 Jun 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal - Emerald Pacific.pdf15 Jun 2023
Layout approvalFile: Building Plan.pdf14 Jun 2023
Building plan approvalFile: Building Plan.pdf14 Jun 2023
PAN CardFile: Firm Pan Card.pdf14 Jun 2023
Copy of the legal title reportFile: Legal Title Report.pdf14 Jun 2023
Copy of the legal title reportFile: Search Report.pdf14 Jun 2023
Copy of Layout Approval (in case of layout)File: Building Plan.pdf14 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf14 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf14 Jun 2023
Declaration about Commencement CertificateFile: Form D.pdf14 Jun 2023
Declaration in FORM BFile: Form B of Developers.pdf14 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf14 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest 02.pdf14 Jun 2023
Proforma of Allotment letterFile: Allotment Letter.pdf14 Jun 2023
Proforma of Agreement for saleFile: Agreement for Sale.pdf14 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details.pdf14 Jun 2023
Deviation Report with respect to Allotment letterFile: Deviation of AL.pdf14 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation of AFS.pdf14 Jun 2023

How this compares with Thane

35%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 15 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Emerald Pacific on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Domobivali (E)7,600+ in Thane

Builder: APR Realty

APR REALTY has 7 registrations on MahaRERA, including EMERALD and EMERALD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Emerald Pacific shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Emerald Pacific is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Emerald Pacific?

The registered promoter entity is APR Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Emerald Pacific?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Emerald Pacific?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Emerald Pacific?

The professionals named in the filing: Architect: A. S. Dastane & Associates; Engineer: Rahul B Hedulkar; Chartered Accountant: R H Pothiwal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Emerald Pacific?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Emerald Pacific. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Emerald Pacific to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.