ELEGANZIA ROYALE
RG-MH-35462 · RERA P51800004209 · Last updated on MahaRERA portal: 22 Jun 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- 22 complaints at MahaRERA
- Completion date moved by 33 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ELEGANZIA ROYALE is a Residential / Group Housing project by ANMOL ALLIANCE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004209 on 9 Aug 2017. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 33 months from the original filing. 22 complaints are on record with the regulator.
At a glance
Project
- NameELEGANZIA ROYALE
- TypeResidential / Group Housing
- Location
- J P Road
- andheri w
- Andheri
- Mumbai Suburban
- 400053
- Pincode400053
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004209
- ReraGenie IDRG-MH-35462
Builder
- NameANMOL ALLIANCE
- Entity typePartnership
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion31 Mar 2024
- Revised completionRevised to 31 Mar 2024 (originally 30 Jun 2021)
- Buildings1 building record
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Eleganzia Royale | NA | 28 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 90%.
Eleganzia Royale: 93% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 90% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 89% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 89% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 82% |
Progress on shared amenities16
As on 22 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 20% |
| Open Parking | No | Not applicable |
| Fitness Centre | Yes | 0% |
Parking filed123
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ellora Project Consultants Pvt Ltd |
| Engineer | Sihavat Consultancy Services |
| Partner | Role in project |
|---|---|
| ANMOL ALLIANCE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. Stop of Work on site due to Status Quo Order passed by the Hon.ble Bombay High Court on 19.10.2018 and modified on 09.07.2019 ,which result in no construction work on site for 263 days . 2. Lock down due to the pandemic 3. shortage of manpower /work due to pandemic.
Reason as filed by the promoterDue to some Legal dispute we are not able to complete the project in time. Hence we request you to grant extension up to 30.03.2024
Litigation declared10
| Case | Court | Status |
|---|---|---|
| 1159/2018 | High Court BOmbay | Status quo maintain |
| 347/2019 | High Court BOmbay | Court Order |
| Suit No 740 of 2019/2019 | Bombay High Court | Matter Settled Suit withdrawn |
| Suit No 747 of 2019/2019 | High Court Bombay | for add interim relief |
| Suit No 742 of 2019/2019 | High Court Bombay | Matter Settled Suit withdrawn |
| Suit No 739 of 2019/2019 | High Court Bombay | Matter Settled Suit withdrawn |
| Suit No 743 of 2019/2019 | High Court Bombay | Matter Settled Suit withdrawn |
| Suit No 741 of 2019/2019 | High Court Bombay | Matter Settled Suit withdrawn |
| Suit No 737 of 2019/2019 | High Court Bombay | Matter Settled Suit withdrawn |
| Suit No 738 of 2019 /2019 | High Court Bombay | Matter Settled Suit withdrawn |
Complaints filed with MahaRERA22
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000023100 | Vanraj Vinod Shah (HUF) and Anr | (1.)Anmol Alliance, (2.)Amkhim Holdings Private Limited (3.) Vasant Kotak & Bros.Trading and Invest | 25/01/2018 |
| CC006000000090031 | Vinod Punjabi | Anmol Alliance | 09/07/2019 |
| CC006000000090036 | Vinod N Punjabi | Anmol Alliance | 09/07/2019 |
| CC006000000090030 | Mrs. Raju N Punjabi | Anmol Alliance | 09/07/2019 |
| CC006000000090033 | Raju N. Punjabi | Anmol Alliance | 09/07/2019 |
| CC006000000090029 | Ganesh G Chhabria | Anmol Alliance | 09/07/2019 |
| CC006000000090032 | Bharati M Kalra | Anmol Alliance | 09/07/2019 |
| CC006000000090034 | Bharati M Kalra | Anmol Alliance | 09/07/2019 |
| CC006000000090035 | Anil N Panjabi | Anmol Alliance | 09/07/2019 |
| CC006000000110662 | Mahesh Makhija | Anmol Alliance | 23/08/2019 |
| CC006000000161276 | Alkesh Kumar Suresh Gangwal | M/S ANMOL ALLIANCE | 17/10/2019 |
| CC006000000181966 | Rohit Satish Shah | M/s Anmol Alliance | 28/01/2021 |
| CC006000000193667 | Eleganzia Royale Association of Allotees | Anmol Alliance | 09/08/2020 |
| CC006000000198473 | Rajendra Singh Toor | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198474 | Mahesh Makhija | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198475 | Ganesh Chhabria | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198478 | Tolaram Kalwani | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198479 | Ramesh Lakhwani | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198509 | Neil Lestourgeon | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198510 | Mrunal Sawant | M/s Anmol Alliance | 04/10/2021 |
| CC006000000198522 | Ashish Bhatnagar | M/s Anmol Alliance | 04/10/2021 |
| CC006000000044442 | Prabha Dinesh Kannan | Anmol Alliance | 08/05/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed38
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: FORM 'B'.pdf | 22 Jun 2023 |
| Declaration in FORM BFile: Form B.pdf | 20 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 20 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 20 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A.pdf | 20 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory List.pdf | 20 Jun 2023 |
| Certificates of CA (Form 3)File: form 3_compressed.pdf | 20 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22 fORM 5.pdf | 6 Apr 2023 |
| PAN CardFile: PAN Card.pdf | 22 Sep 2022 |
| Declaration about Commencement CertificateFile: 20220921 Formet -D.pdf | 22 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 08-19-2022 Form 1.pdf | 22 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_July 2022.pdf | 22 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: 20220921 Sold unsold.pdf | 22 Sep 2022 |
| Certificates of CA (Form 3)File: 20220823 Form 3.pdf | 22 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual report on Statement of Account 2018-19.pdf | 22 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual report on Statement of Account 2019-20.pdf | 22 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual report on Statement of Account 2020-21.pdf | 22 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 20220921_ Formet -A.pdf | 22 Sep 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: HIGH COURT ORDER.pdf | 18 Mar 2019 |
| OtherFile: HIGH COURT ORDER.pdf | 18 Mar 2019 |
| Building plan approvalFile: anmol ioa.pdf | 31 Jul 2017 |
| Building plan approvalFile: anmol plan.pdf | 31 Jul 2017 |
| Layout approvalFile: anmol plan.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate New.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Fed Bank Index II.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: SBI Index II.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Security_Letter_for_Loan.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Security Letter 1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: anmol plan.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: anmol ioa.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: anmol plan.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Anmol C C.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Declaration Form.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHIV_SHAKTI_FORM2_signed.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3.pdf | 31 Jul 2017 |
| Certificates of CA (Form 5)File: Form 5.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Anmol Alliance Draft Allotment letter Agreement for sale.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 38 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ELEGANZIA ROYALE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near andheri w6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 238 registered projects within 2 km.
LIVSMART KURLA
D. K. REALTY (INDIA) PVT. LTD.
MOONGIPA ARCADE
MOONGIPA REALTY PRIVATE LIMITED
LINKBAY RESIDENCES PHASE I
PORTSMOUTH BUILDCON PRIVATE LIMITED
Purva Estrella
Puravankara Ltd
78 LAKE TOWN
ANIRDESH DEVELOPERS PRIVATE LIMITED
Transcon Triumph Tower 2
Transcon Triumph Phase 2 Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: ANMOL ALLIANCE
ANMOL ALLIANCE has 1 registration on MahaRERA, including ELEGANZIA ROYALE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ELEGANZIA ROYALE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ELEGANZIA ROYALE is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ELEGANZIA ROYALE?
The registered promoter entity is ANMOL ALLIANCE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ELEGANZIA ROYALE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ELEGANZIA ROYALE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ELEGANZIA ROYALE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ELEGANZIA ROYALE?
The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Engineer: Sihavat Consultancy Services. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ELEGANZIA ROYALE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.