Home / Browse projects / Pune, Maharashtra / EISHA BASILLA
EISHA BASILLA
RG-MH-10841 · RERA P52100004253 · Last updated on MahaRERA portal: 26 Dec 2019
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 72 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 22 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EISHA BASILLA is a Others project by EISHA CONCORD REALTORS in Pune, Maharashtra, registered with MahaRERA as P52100004253 on 9 Aug 2017. Possession was promised by 30 Oct 2020 and is now 72 months past that date. The completion date has moved by 22 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameEISHA BASILLA
- TypeOthers
- Location
- Kondhwa Road
- Kondhwa Budruk
- kondhwa BK
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100004253
- ReraGenie IDRG-MH-10841
Builder
- NameEISHA CONCORD REALTORS
- Entity typePartnership
- PartnersSWARANSINGH GYANSINGH SOHAL, RANJEETSINGH NANDLAL HOODA
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion30 Oct 2020
- Revised completionRevised to 30 Oct 2020 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed42 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| EISHA BASILLA | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 97%.
EISHA BASILLA: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 97% |
| Podiums (if any) | 96% |
| Plinth | 97% |
| Stilt Floor | 92% |
| Slabs of Super Structure | 83% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 94% |
| Sanitary Fittings within the flats / premises | 68% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 72% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 96% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 82% |
Progress on shared amenities15
As on 26 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 88% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 98% |
| Storm Water Drains | Yes | 98% |
| Landscaping & Tree Planting | Yes | 65% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 60% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 92% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 45% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 60% |
| Open Parking | No | Not applicable |
Parking filed127
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VILAS TARWADI |
| Engineer | DESIGN WERKZ ENGINEERING PVT LTD |
| Partner | Role in project |
|---|---|
| EISHA CONCORD REALTORS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have received the revised sanction in June-2017 wherein one upper floor of B-Bldg., and 2 upper floors of commercial Bldg., were not sanctioned as the DP Road going through the said project was pending for final survey and handover to Pune Municipal Corporation and It is due to their internal departmental decision where we have no role to play or we have not kept any document pending from our end for the said DP road. Hence we have inwarded the application for final sanctioning on 10-Jan-2018 for which we were granted the final sanction by first week of August -2018 thus hampering the work
Reason as filed by the promoterDear Sir, There was delay in receiving final sanction from Municipal Authorities which halted the project for a long time which we did mention in our last extension. Project was delayed for a reason beyond our control and due to this even we came under financial burden wherein during the same period we had to complete repayment of the project loan taken from State Bank Of India further accompanied with non-payment by customers due to delay. We even requested our customers to make payments as per the clause 16(V) (copy attached) mentioned in agreement however they ensured us of balance payments
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000177837 | Madhukar Shankar Dhandekar | M/s. EISHA Concord Realtors Through its Partner/s Mr. Bharat Mithalal Nagori | 02/12/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed42
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrancesFile: Encumbrance - Index-2.pdf | 26 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_compressed.pdf | 23 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_compressed.pdf | 23 Sep 2019 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form - 2A_compressed.pdf | 23 Sep 2019 |
| Certificates of CA (Form 3)File: CA Certificate_compressed.pdf | 23 Sep 2019 |
| OtherFile: Part Completion - 2018.PDF | 30 Jan 2019 |
| Certificates of CA (Form 5)File: Form-5.pdf | 25 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 25 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 25 Dec 2018 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 25 Dec 2018 |
| Certificates of CA (Form 3)File: C A CERTIFICATE.pdf | 1 Aug 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 23 Jul 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf | 23 Jul 2018 |
| OtherFile: Development_Agreement-1_10.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_11_20.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_21_30.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_41_50.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_51_60.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_61_70.pdf | 13 Apr 2018 |
| OtherFile: Development_Agreement_71-83.pdf | 13 Apr 2018 |
| Proforma of Allotment letterFile: Agreement Draft_Basilla_Revised.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Allotment_ Draft_Basilla_Revised.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: 1-10.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 11-20.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 21-20.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 41-50.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 51-60.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 61-70.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 71-80.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 81-92.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: 92-104.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf | 28 Jul 2017 |
| Building plan approvalFile: Plan No 1.pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: Eisha Basilla Title Report 2017.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: Plan No 1.pdf | 27 Jul 2017 |
| Declaration in FORM BFile: Form B _Eisha Concord Realtors.pdf | 27 Jul 2017 |
| Layout approvalFile: Plan No 1.pdf | 23 Jul 2017 |
| PAN CardFile: ECR_Pan Card.PDF | 23 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Plan No 1.pdf | 23 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Basilla_Revised_CC_Pages 1 to 4-ilovepdf-compressed.pdf | 23 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| EISHA BELLAVISTA PHASE 3 | SR NO. 15 KONDHWA BUDRUK PUNE-411048 | 47 | Completed | Mar 2011 | Late, Nov 2011 |
| EISHA BELLAVISTA PHASE 2 | SR NO. 15 KONDHWA BUDRUK PUNE-411048 | 118 | Completed | Mar 2011 | Late, Nov 2011 |
| EISHA BELLAVISTA PHASE 1 | SR NO. 15 KONDHWA BUDRUK PUNE-411048 | 117 | Completed | Apr 2009 | Late, Jul 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 42 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep EISHA BASILLA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kondhwa Budruk13,700+ in Pune
Filed coordinates, straight-line distance. 189 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: EISHA CONCORD REALTORS
EISHA CONCORD REALTORS has 1 registration on MahaRERA, including EISHA BASILLA. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that EISHA BASILLA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if EISHA BASILLA is delayed beyond 30 Oct 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EISHA BASILLA?
The registered promoter entity is EISHA CONCORD REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EISHA BASILLA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EISHA BASILLA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EISHA BASILLA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EISHA BASILLA?
The professionals named in the filing: Architect: VILAS TARWADI; Engineer: DESIGN WERKZ ENGINEERING PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EISHA BASILLA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback