Home / Browse projects / Satara, Maharashtra / DWARKAMAI RESIDENCY

Registered No litigation declared Residential / Group Housing project

DWARKAMAI RESIDENCY

By PRASHANT HANMANT SHEDGE

RG-MH-27711 · RERA P52700034868 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 45 months from the original
5 of 11Construction stages donefurthest along: Stilt Floor, 80%
9 of 12Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

DWARKAMAI RESIDENCY is a Residential / Group Housing project by PRASHANT HANMANT SHEDGE in Satara, Maharashtra, registered with MahaRERA as P52700034868 on 28 Apr 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 45 months from the original filing. 3 of the 12 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameDWARKAMAI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • R S NO 171/A/11/7
    • GODOLI
    • SATARA
    • GODOLI
    • Satara
    • 415002
  • Pincode415002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700034868
  • ReraGenie IDRG-MH-27711

Builder

  • NamePRASHANT HANMANT SHEDGE
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2022First promiseMar 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed117 files

Current status

25%3 of 12 units booked
73.5%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DWARKAMAI RESIDENCYNA6412012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.

DWARKAMAI RESIDENCY: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area500 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Mar 2026
LandownerVillageDistrict
PRASHANT HANMANT SHEDGESaidapurSatara
HANMANT SUDAM LOKHANDESataraSatara
VISHAL NARAYAN LOKHANDESataraSatara

Approvals and building plan

Sanctioning authoritySATARA MUNICIPAL CORPORATION
Permissible FSI550.76
Proposed, not sanctioned551 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND AND FIRST FLOOR, CTS NO 495, PLOT NO 37 TO 41, MUTHA COLONY, NEAR CIVIL HOSPITAL, SADAR BAZAR
Estimated costRs 1.80 cr
Cost incurredRs 1.32 cr
Work done73.49%
BuildingWingEstimatedIncurred
DWARKAMAI RESIDENCYNARs 1.80 crRs 1.32 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHALCHANDRA NAMDEV NIGADE
EngineerYUVRAJ BABURAO SAWANT
Chartered AccountantShital Sameer Shinde
Chartered AccountantM S B S & COMPANY
PartnerRole in project
PRASHANT HANMANT SHEDGE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700019472Mar 2024 → Mar 2025

Reason as filed by the promoter1] Till date no single booking is received for our project because, other project which is developed near to our site which is almost complete, hence our probable customers who visited our site for enquiry will prefer the nearby project which is almost near to completion. 2] As on date total funds of Rs.35 lacs approx. have invested by me as our own funds for the construction of project which is completed up to plinth level. So, we are expecting some bookings will be received and project will be completed in next 2 years. 3] Some customers who are visited to our site for project site and locat

EXT52700027985Mar 2024 → Mar 2026

Reason as filed by the promoter1] one flat sale on 03/02/2025 & project is almost 65% complete with sale proceeds from flat and our own contribution. 2] Initially we have expended large amount of our funds for development of rivulet / brook because of that our allocated construction funds was diverted for developing rivulet / brook. Previously It’s largely effects on bookings due to non-completion of certain percentage our project. 3] Two bookings are in the process which is almost final; hence we have required RERA extension up to 31/03/2026. 4] QPR for Q4 financial year 2024-2025 is uploaded. 5] updated notarized affidavi

EA15042620644Mar 2024 → Dec 2027

Reason as filed by the promoter1] Lack of Funds The project experienced a temporary financial crunch due to delayed inflow of funds from customers and financial institutions. This adversely impacted the cash flow required for continuous construction activities, resulting in slowdown of work progress. 2] Labour Shortage There was a significant shortage of skilled and unskilled labour during the year. Migration of labourers to their native places and reduced workforce availability led to interruptions in construction schedules and affected timely execution of project milestones. 3] Heavy Rainfall in 2025 The year 2025 witness

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Q4 FY 202526.pdf20 Jul 2026
Withdrawal Update Form 2File: FORM 2 Q4 FY 202526.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3 Q4 FY 202526.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A FY 2025-26.pdf27 Apr 2026
Form 5 (FY 2025-2026)File: FORM 5 FY 2025-26.pdf26 Apr 2026
Form 1File: FORM 1 Q1 2022-23.pdf15 Apr 2026
Form 2File: FORM 2 Q1 2022-23.pdf15 Apr 2026
Form 3File: FORM 3 Q1 2022-23.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q1 2022-23.pdf15 Apr 2026
Form 1File: FORM 1 Q2 2022-23.pdf15 Apr 2026
Form 2File: FORM 2 Q2 2022-23.pdf15 Apr 2026
Form 3File: FORM 3 Q2 2022-23.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q2 2022-23.pdf15 Apr 2026
Form 1File: FORM 1 Q3 2022-23.pdf15 Apr 2026
Form 2File: FORM 2 Q3 2022-23.pdf15 Apr 2026
Form 3File: FORM 3 Q3 2022-23.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q3 2022-23.pdf15 Apr 2026
Form 1File: FORM 1 Q4 2022-23.pdf15 Apr 2026
Form 2File: FORM 2 Q4 2022-23.pdf15 Apr 2026
Form 3File: Form 3_Q4 FY22-23.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q4 2022-23.pdf15 Apr 2026
Form 1File: FORM 1 Q1 2023-24.pdf15 Apr 2026
Form 2File: FORM 2 Q1 2023-24.pdf15 Apr 2026
Form 3File: FORM 3_Q1 FY 23-24.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q1 2023-24.pdf15 Apr 2026
Form 1File: FORM 1 Q2 2023-24.pdf15 Apr 2026
Form 2File: FORM 2 Q2 2023-24.pdf15 Apr 2026
Form 3File: FORM 3_Q2 FY 23-24.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q2 2023-24.pdf15 Apr 2026
Form 1File: FORM 1 Q3 2023-24.pdf15 Apr 2026
Form 2File: FORM 2 Q3 2023-24.pdf15 Apr 2026
Form 3File: FORM 3_Q3 FY 23-24.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q3 2023-24.pdf15 Apr 2026
Form 1File: FORM 1 Q4 2023-24.pdf15 Apr 2026
Form 2File: FORM 2 Q4 2023-24.pdf15 Apr 2026
Form 3File: FORM 3_Q4 FY 23-24.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q4 2023-24.pdf15 Apr 2026
Form 1File: FORM 1 Q1 FY 24-25 Architect certificate.pdf15 Apr 2026
Form 2File: FORM 2 Q1 FY 2024-25.pdf15 Apr 2026
Form 3File: FORM 3 Q1 FY 2024-25.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q1 2024-25.pdf15 Apr 2026
Form 1File: FORM 1 Q2 FY 24-25 Architect certificate.pdf15 Apr 2026
Form 2File: FORM 2 Q2 FY 2024-25.pdf15 Apr 2026
Form 3File: FORM 3 Q2 FY 2024-25.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q2 2024-25.pdf15 Apr 2026
Form 1File: FORM 1 Q3 FY 24-25 Architect certificate.pdf15 Apr 2026
Form 2File: FORM 2 Q3 FY 2024-25.pdf15 Apr 2026
Form 3File: FORM 3 Q3 FY 2024-25.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q3 2024-25.pdf15 Apr 2026
Form 1File: FORM 1 Q4 FY 24-25 Architect certificate.pdf15 Apr 2026
Form 2File: Form - 2 Engineer Certi _ Q4 FY 2024-25.pdf15 Apr 2026
Form 3File: FORM NO 3 Q4 FY24-25_CA SHITAL SHINDE.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q4 2024-25.pdf15 Apr 2026
Form 2A (FY 2022-2023)File: Form 2A 2023.pdf15 Apr 2026
Form 2A (FY 2023-2024)File: Form 2A 2024.pdf15 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A 2025.pdf15 Apr 2026
Form 5 (FY 2022-2023)File: FORM 5 FY 2022-23.pdf14 Apr 2026
Form 5 (FY 2023-2024)File: FORM 5 FY 2023-24.pdf14 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25.pdf14 Apr 2026
Form 1File: FORM 1.pdf28 Mar 2026
Form 2File: FORM 2.pdf28 Mar 2026
Form 3File: FORM 3.pdf28 Mar 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY.pdf28 Mar 2026
Form 1File: FORM 1 - Architect Certificate.pdf17 Nov 2025
Form 2File: Form - 2 Engineer Certificate.pdf17 Nov 2025
Form 3File: Form 3 - CA Certificate.pdf17 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf17 Nov 2025
Form 1File: FORM 1_compressed.pdf27 Jul 2025
Form 2File: FORM 2_compressed.pdf27 Jul 2025
Form 3File: FORM 3_compressed.pdf27 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf27 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q4 FY 24-25 Architect certificate.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM NO 3 Q4 FY24-25_CA SHITAL SHINDE.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer Certi _ Q4 FY 2024-25.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q1 FY 24-25 Architect certificate.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q2 FY 24-25 Architect certificate.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3 FY 24-25 Architect certificate.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q1 FY 2024-25.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q2 FY 2024-25.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 FY 2024-25.pdf24 Jan 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
NANACompletedMar 2022Mar 2022

How this compares with Satara

25%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 45 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep DWARKAMAI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GODOLI1,100+ in Satara

2 kmDWARKAMAI RESIDENCYCompleted 34Lapsed / revoked 39Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: PRASHANT HANMANT SHEDGE

PRASHANT HANMANT SHEDGE has 1 registration on MahaRERA, including DWARKAMAI RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if DWARKAMAI RESIDENCY is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DWARKAMAI RESIDENCY?

The registered promoter entity is PRASHANT HANMANT SHEDGE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DWARKAMAI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DWARKAMAI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DWARKAMAI RESIDENCY?

The professionals named in the filing: Architect: BHALCHANDRA NAMDEV NIGADE; Engineer: YUVRAJ BABURAO SAWANT; Chartered Accountant: Shital Sameer Shinde; Chartered Accountant: M S B S & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DWARKAMAI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DWARKAMAI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DWARKAMAI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.