Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DUDHWALA AQUAGEM is a Residential / Group Housing project by CASTLE REALTORS PRIVATE LIMITED in 400008, 400010, registered with MahaRERA as P51900011349 on 31 Aug 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameDUDHWALA AQUAGEM
- TypeResidential / Group Housing
- Location
- Nesbit Road
- 400008
- 400010
- Pincode400010
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900011349
- ReraGenie IDRG-MH-25222
Builder
- NameCASTLE REALTORS PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorNISAR AHMED PATEL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
- Buildings3 building records
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1-4th to 35th FLOORS | NA | 38 | 0 | 0 | 0 | 0 |
| BUILDING NO 2 - 4th to 18th FLOORS | NA | 20 | 0 | 0 | 0 | 0 |
| BUILDIG NO 3-REHAB UNITS | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
BUILDING NO 1-4th to 35th FLOORS90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
BUILDING NO 2 - 4th to 18th FLOORS74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 85% |
| Plinth | 90% |
| Stilt Floor | 82% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 43% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 55% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 62% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 72% |
BUILDIG NO 3-REHAB UNITS3%
| Activity | Progress |
|---|---|
| Excavation | 34% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities18
As on 20 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 93% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 45% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | Yes | 55% |
| Open Parking | No | Not applicable |
| Swimming Pool | Yes | 80% |
| Compound Wall | Yes | 90% |
| Gymnasium | Yes | 100% |
Parking filed230
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING NO 1-4th to 35th FLOORS | 191 | 191 |
| BUILDING NO 2 - 4th to 18th FLOORS | 32 | 32 |
| BUILDIG NO 3-REHAB UNITS | 7 | 7 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vivek Bhartu Consultants Pvt. Ltd. |
| Architect | D A DESIGN |
| Engineer | Hanware Consultants |
| Partner | Role in project |
|---|---|
| CASTLE REALTORS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid 19 the real estate market is suffering huge loss and till date could not achieve recover, due to financial instability and other major issues we could not the said project on time.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 211/2014 | BOMBAY HIGH COURT | ACTIVE |
| 213/2017 | BOMBAY HIGH COURT | ACTIVE |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000374839 | Mohammed Arif | Castle Realtors Private Limited | 23/03/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Nov 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5)File: Form5.pdf | 20 Sep 2019 |
| Proforma of Allotment letterFile: Agreement for Sale_AQUAGEM.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: Annex-AFS.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: Annex-2-AFS.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: Annex-3-AFS.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: Annex-4-AFS.pdf | 14 Mar 2018 |
| Proforma of Allotment letterFile: AQUAGEM FINAL ALLOTMENT LETTER.pdf | 21 Feb 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate13112017.pdf | 28 Nov 2017 |
| Building plan approvalFile: 2085333_OC_signed.pdf | 7 Nov 2017 |
| Building Plan Approval (IOD)File: 2085333_OC_signed.pdf | 7 Nov 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_ 04-07-2017.pdf | 7 Nov 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH castle.pdf | 31 Jul 2017 |
| OtherFile: annexcastle-.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended letter.pdf | 30 Jul 2017 |
| Layout approvalFile: layout-castle.PDF | 30 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE AQUAGEM.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Declaration Non encumb.PDF | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout-castle.PDF | 30 Jul 2017 |
| Building Plan Approval (IOD)File: Amended letter.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Final.PDF | 30 Jul 2017 |
| Declaration in FORM BFile: FORM B.PDF | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Mazgaon form 2.PDF | 30 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificat.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Declaration Allot-afs.PDF | 30 Jul 2017 |
| PAN CardFile: castle PAN CARD.pdf | 28 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 25 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DUDHWALA AQUAGEM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near 400008
Filed coordinates, straight-line distance. 42 registered projects within 2 km.
Piramal Aranya - Wing B
Glider Buildcon Realtors Private Limited
TARABAUG
DARSHAN DEVELOPERS
A. M. Residency
ALFA MANA REALTORS PVT LTD
Piramal Aranya - Wing C
Glider Buildcon Realtors Private Limited
Piramal Aranya - Ahan 2
Glider Buildcon Realtors Private Limited
10 HARBOUR ESTATES
NAN ENTERPRISES
Builder: CASTLE REALTORS PRIVATE LIMITED
CASTLE REALTORS PRIVATE LIMITED has 1 registration on MahaRERA, including DUDHWALA AQUAGEM. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that DUDHWALA AQUAGEM shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DUDHWALA AQUAGEM is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DUDHWALA AQUAGEM?
The registered promoter entity is CASTLE REALTORS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DUDHWALA AQUAGEM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DUDHWALA AQUAGEM?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DUDHWALA AQUAGEM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DUDHWALA AQUAGEM?
The professionals named in the filing: Architect: Vivek Bhartu Consultants Pvt. Ltd.; Architect: D A DESIGN; Engineer: Hanware Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DUDHWALA AQUAGEM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback